Erschienen in: Production Engineering 5/2021

10.04.2021 | Production Management

An alternative for improving setup times and time between failures aiming at manufacturing lead time reduction

verfasst von: Marcel Heimar Ribeiro Utiyama, Moacir Godinho Filho, Pedro Carlos Oprime

Erschienen in: Production Engineering | Ausgabe 5/2021

Einloggen, um Zugang zu erhalten
share
TEILEN

Abstract

The main goal of this study is to propose an alternative approach to improve manufacturing setup time and the time between failures. This approach focuses on eliminating the outliers concerning manufacturing setup times and time between failures. With this aim, we performed simulations to compare the effect on the lead time of both improvement strategies with the traditional strategies of reducing the mean or variability. The simulation results indicate that for low variability, the best strategy is to focus on the mean setup time and time between failures and the worst-case strategy emerges as an excellent practical alternative. For environments with moderate variability, investing in eliminating the worst-case setup time and time between failures is suggested as the best option. Both options presented results like the strategies of improving the mean and variability and it is generally achieved with a lower cost and easier implementation. Therefore, the results of the present study indicate that the worst-case strategy is an important improvement option and can be adopted by companies in practice, deserving further investigation in manufacturing and operations-management studies.

Sie möchten Zugang zu diesem Inhalt erhalten? Dann informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 69.000 Bücher
  • über 500 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Testen Sie jetzt 15 Tage kostenlos.

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 50.000 Bücher
  • über 380 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




Testen Sie jetzt 15 Tage kostenlos.

Literatur
1.
Zurück zum Zitat Diaby M, Cruz JM, Nsakanda AL (2013) Shortening cycle times in multi-product, capacitated production environments through quality level improvements and set up reduction. Eur J Oper Res 228(3):526–535 CrossRef Diaby M, Cruz JM, Nsakanda AL (2013) Shortening cycle times in multi-product, capacitated production environments through quality level improvements and set up reduction. Eur J Oper Res 228(3):526–535 CrossRef
2.
Zurück zum Zitat Ericksen PD, Stoflet NJ, Suri R (2007) Manufacturing critical-path time (MCT): the QRM Metric for lead time. In: Technical report, Center for QRM, Wisconsin-Madison Ericksen PD, Stoflet NJ, Suri R (2007) Manufacturing critical-path time (MCT): the QRM Metric for lead time. In: Technical report, Center for QRM, Wisconsin-Madison
3.
Zurück zum Zitat Sarkar B, Buddhadev M, Sarkar S (2015) Quality improvement and backorder price discount under controllable lead time in an inventory model. J Manuf Syst 35:26–36 CrossRef Sarkar B, Buddhadev M, Sarkar S (2015) Quality improvement and backorder price discount under controllable lead time in an inventory model. J Manuf Syst 35:26–36 CrossRef
4.
Zurück zum Zitat Stalk G, Hout TM (1990) Competing against time: how time-based competition is reshaping global markets. Free Press, New York CrossRef Stalk G, Hout TM (1990) Competing against time: how time-based competition is reshaping global markets. Free Press, New York CrossRef
5.
Zurück zum Zitat Suri R (1998) Quick response manufacturing: a companywide approach to reducing lead times. Productivity Press, Portland Suri R (1998) Quick response manufacturing: a companywide approach to reducing lead times. Productivity Press, Portland
6.
Zurück zum Zitat Suri R (2010) It´s about time: the competitive advantage of quick response manufacturing. Productivity Press, New York CrossRef Suri R (2010) It´s about time: the competitive advantage of quick response manufacturing. Productivity Press, New York CrossRef
7.
Zurück zum Zitat Samaddar S (2001) The effect of setup time reduction on its variance. Omega 29(3):243–247 CrossRef Samaddar S (2001) The effect of setup time reduction on its variance. Omega 29(3):243–247 CrossRef
8.
Zurück zum Zitat Cakmakci M (2009) Process improvement: performance analysis of the setup time reduction-SMED in the automobile industry. Int J Adv Manuf Technol 41(1–2):168–179 CrossRef Cakmakci M (2009) Process improvement: performance analysis of the setup time reduction-SMED in the automobile industry. Int J Adv Manuf Technol 41(1–2):168–179 CrossRef
9.
Zurück zum Zitat Waeyenbergh G, Pintelon L (2004) Maintenance concept development: a case study. Int J Prod Econ 89(3):395–405 CrossRef Waeyenbergh G, Pintelon L (2004) Maintenance concept development: a case study. Int J Prod Econ 89(3):395–405 CrossRef
11.
Zurück zum Zitat Braglia M, Carmignani G, Frosolini M (2012) Data classification and MTBF prediction with a multivariate analysis approach. Reliab Eng Syst Saf 97(1):27–35 CrossRef Braglia M, Carmignani G, Frosolini M (2012) Data classification and MTBF prediction with a multivariate analysis approach. Reliab Eng Syst Saf 97(1):27–35 CrossRef
12.
Zurück zum Zitat Varuvel AG, Pruno PX (2019) Reliability allocation technique for complex system of systems. Int J Reliab Saf 13(1–2):61–82 CrossRef Varuvel AG, Pruno PX (2019) Reliability allocation technique for complex system of systems. Int J Reliab Saf 13(1–2):61–82 CrossRef
13.
Zurück zum Zitat Yang J, Deane RH (1993) Setup time reduction and competitive advantage in a closed manufacturing cell. Eur J Oper Res 69:413–423 CrossRef Yang J, Deane RH (1993) Setup time reduction and competitive advantage in a closed manufacturing cell. Eur J Oper Res 69:413–423 CrossRef
15.
Zurück zum Zitat Godinho Filho M, Utiyama MHR (2016) Comparing the effect of different strategies of continuous improvement programmes on repair time to reduce lead time. Int J Adv Manuf Technol 87:315–327 CrossRef Godinho Filho M, Utiyama MHR (2016) Comparing the effect of different strategies of continuous improvement programmes on repair time to reduce lead time. Int J Adv Manuf Technol 87:315–327 CrossRef
16.
Zurück zum Zitat Almomani MA, Aladeemy M, Abelhadi A, Mumani A (2013) A proposed approach for setup time reduction through integrating conventional SMED method with multiple criteria decision making techniques. Comput Ind Eng 66:461–469 CrossRef Almomani MA, Aladeemy M, Abelhadi A, Mumani A (2013) A proposed approach for setup time reduction through integrating conventional SMED method with multiple criteria decision making techniques. Comput Ind Eng 66:461–469 CrossRef
17.
Zurück zum Zitat Hopp WJ, Spearman ML (2011) Factory physics: foundations of manufacturing management. McGraw Hill Higher Education, Nova Iorque, p 720p Hopp WJ, Spearman ML (2011) Factory physics: foundations of manufacturing management. McGraw Hill Higher Education, Nova Iorque, p 720p
18.
Zurück zum Zitat Sarkar D, Zangwill WI (1991) Variance effects in cyclic production systems. Manag Sci 37(4):444–453 CrossRef Sarkar D, Zangwill WI (1991) Variance effects in cyclic production systems. Manag Sci 37(4):444–453 CrossRef
19.
Zurück zum Zitat Samaddar S, Kaul TK (1995) Variance effects in cyclic production systems. Manag Sci 41(5):1263–1265 CrossRef Samaddar S, Kaul TK (1995) Variance effects in cyclic production systems. Manag Sci 41(5):1263–1265 CrossRef
20.
Zurück zum Zitat Hong J, Hayya JC (1993) Dynamic lot sizing with setup reduction. Comput Ind Eng 24(2):209–218 CrossRef Hong J, Hayya JC (1993) Dynamic lot sizing with setup reduction. Comput Ind Eng 24(2):209–218 CrossRef
21.
Zurück zum Zitat Filho M, Uzsoy R (2008) Combining system dynamics and factory physics approach to study the effect of continuous improvement on lot size–cycle time relationships. In: Proceedings on production and operation management society (POMS), 19, La Jolla, Californi Filho M, Uzsoy R (2008) Combining system dynamics and factory physics approach to study the effect of continuous improvement on lot size–cycle time relationships. In: Proceedings on production and operation management society (POMS), 19, La Jolla, Californi
22.
Zurück zum Zitat Filho MG, Uzsoy R (2010) Estudo do efeito de programas de Melhoria Contínua em variáveis do chão de fábrica na relação entre tamanho de lote de produção e lead time. Gestão Produção 17(1):137–148 CrossRef Filho MG, Uzsoy R (2010) Estudo do efeito de programas de Melhoria Contínua em variáveis do chão de fábrica na relação entre tamanho de lote de produção e lead time. Gestão Produção 17(1):137–148 CrossRef
23.
Zurück zum Zitat Shingo S (1985) A revolution in manufacturing, the SMED system. Productivity Press Shingo S (1985) A revolution in manufacturing, the SMED system. Productivity Press
24.
Zurück zum Zitat Shingo S (1996) O Sistema Toyota de Produção do ponto de vista da Engenharia de Produção. Bookman, Porto Alegre Shingo S (1996) O Sistema Toyota de Produção do ponto de vista da Engenharia de Produção. Bookman, Porto Alegre
25.
Zurück zum Zitat Antosz K, Pacana A (2018) Comparative analysis of the implementation of the SMED method on selected production stands. Tehnički vjesnik 25(Supplement 2):276–282 Antosz K, Pacana A (2018) Comparative analysis of the implementation of the SMED method on selected production stands. Tehnički vjesnik 25(Supplement 2):276–282
26.
Zurück zum Zitat Bidarra T, Godina R, Matias JCO, Azevedo SG (2018) SMED methodology implementation in an automotive industry using a case study method. Int J Ind Eng Manag 9(1):1–16 Bidarra T, Godina R, Matias JCO, Azevedo SG (2018) SMED methodology implementation in an automotive industry using a case study method. Int J Ind Eng Manag 9(1):1–16
27.
Zurück zum Zitat Silva IB, Godinho Filho M (2019) Single-minute exchange of die (SMED): a state-of-the-art literature review. Int J Adv Manuf Technol 102(9–12):4289–4307 CrossRef Silva IB, Godinho Filho M (2019) Single-minute exchange of die (SMED): a state-of-the-art literature review. Int J Adv Manuf Technol 102(9–12):4289–4307 CrossRef
28.
Zurück zum Zitat Allahverdi A (2015) The third comprehensive survey on scheduling problems with setup times/costs. Eur J Oper Res 246(2):345–378 MathSciNetCrossRef Allahverdi A (2015) The third comprehensive survey on scheduling problems with setup times/costs. Eur J Oper Res 246(2):345–378 MathSciNetCrossRef
29.
Zurück zum Zitat Zeidi JR, MohammadHosseini S (2015) Scheduling unrelated parallel machines with sequence-dependent setup times. Int J Adv Manuf Technol 81(9–12):1487–1496 CrossRef Zeidi JR, MohammadHosseini S (2015) Scheduling unrelated parallel machines with sequence-dependent setup times. Int J Adv Manuf Technol 81(9–12):1487–1496 CrossRef
33.
Zurück zum Zitat Masruroh NA, Fauziah HA, Sulistyo SR (2020) Integrated production scheduling and distribution allocation for multi-products considering sequence-dependent setups: a practical application. Prod Eng Res Dev 14(2):191–206 CrossRef Masruroh NA, Fauziah HA, Sulistyo SR (2020) Integrated production scheduling and distribution allocation for multi-products considering sequence-dependent setups: a practical application. Prod Eng Res Dev 14(2):191–206 CrossRef
34.
Zurück zum Zitat Filho M, Utiyama MHR (2015) Comparing different strategies for the allocation of improvement programmes in a flow shop environment. Int J Adv Manuf Technol 77:1365–1385 CrossRef Filho M, Utiyama MHR (2015) Comparing different strategies for the allocation of improvement programmes in a flow shop environment. Int J Adv Manuf Technol 77:1365–1385 CrossRef
35.
Zurück zum Zitat Renna P, Ambrico M (2019) The allocation of improvement programs in a flow shop for single and multi-products: a simulation assessment. Int J Agile Syst Manag 12(3):228–244 CrossRef Renna P, Ambrico M (2019) The allocation of improvement programs in a flow shop for single and multi-products: a simulation assessment. Int J Agile Syst Manag 12(3):228–244 CrossRef
36.
Zurück zum Zitat Willmott P (1997) Tpm experience: showing the way to better equipment care through teamwork. Findlay Publications, Horton Kirby Willmott P (1997) Tpm experience: showing the way to better equipment care through teamwork. Findlay Publications, Horton Kirby
37.
Zurück zum Zitat Asha G, Unnikrishnan Nair N (2010) Reliability properties of mean time to failure in age replacement models. Int J Reliab Qual Saf Eng 17(01):15–26 CrossRef Asha G, Unnikrishnan Nair N (2010) Reliability properties of mean time to failure in age replacement models. Int J Reliab Qual Saf Eng 17(01):15–26 CrossRef
38.
Zurück zum Zitat Shin J, Morrison JR, Kalir A (2016) Optimization of preventive maintenance plans in G/G/M queueing networks and numerical study with models based on semiconductor Wafer Fabs. Int J Ind Eng 23(5):302–317 Shin J, Morrison JR, Kalir A (2016) Optimization of preventive maintenance plans in G/G/M queueing networks and numerical study with models based on semiconductor Wafer Fabs. Int J Ind Eng 23(5):302–317
39.
Zurück zum Zitat Kamel G, Aly MF, Mohib A, Afefy IH (2020) Optimization of a multilevel integrated preventive maintenance scheduling mathematical model using genetic algorithm. Int J Manag Sci Eng Manag 15(4):247–257 Kamel G, Aly MF, Mohib A, Afefy IH (2020) Optimization of a multilevel integrated preventive maintenance scheduling mathematical model using genetic algorithm. Int J Manag Sci Eng Manag 15(4):247–257
40.
Zurück zum Zitat Savaliya R, Abdul-Kader W (2020) Performance evaluation of the remanufacturing system prone to random failure and repair. Int J Sustain Eng 13(1):33–44 CrossRef Savaliya R, Abdul-Kader W (2020) Performance evaluation of the remanufacturing system prone to random failure and repair. Int J Sustain Eng 13(1):33–44 CrossRef
41.
Zurück zum Zitat Utiyama MHR, Correia FC, Alliprandini DH (2020) Allocation of improvement strategies in a flow shop with two capacity constrained resources. Int J Oper Quant Manag 26(2):79–93 CrossRef Utiyama MHR, Correia FC, Alliprandini DH (2020) Allocation of improvement strategies in a flow shop with two capacity constrained resources. Int J Oper Quant Manag 26(2):79–93 CrossRef
42.
Zurück zum Zitat Tamás P (2017) Decision support simulation method for process improvement of intermittent production systems. Appl Sci 7(9):950 CrossRef Tamás P (2017) Decision support simulation method for process improvement of intermittent production systems. Appl Sci 7(9):950 CrossRef
43.
Zurück zum Zitat Filho MG, Uzsoy R (2014) Assessing the impact of alternative continuous improvement programmes in a flow shop using system dynamics. Int J Prod Res 52:1–18 CrossRef Filho MG, Uzsoy R (2014) Assessing the impact of alternative continuous improvement programmes in a flow shop using system dynamics. Int J Prod Res 52:1–18 CrossRef
44.
Zurück zum Zitat Carlson JG (1987) Improvement curve analysis of changeovers in JIT environments. Eng Costs Prod Econ 12:259–266 CrossRef Carlson JG (1987) Improvement curve analysis of changeovers in JIT environments. Eng Costs Prod Econ 12:259–266 CrossRef
45.
Zurück zum Zitat Ouyang LY, Chen CK, Chang HC (2002) Quality improvement, setup cost and lead-time reductions in lot size reorder point models with an imperfect production process. Comput Oper Res 29(12):1701–1717 CrossRef Ouyang LY, Chen CK, Chang HC (2002) Quality improvement, setup cost and lead-time reductions in lot size reorder point models with an imperfect production process. Comput Oper Res 29(12):1701–1717 CrossRef
46.
Zurück zum Zitat Montgomery DC (2009) Design and analysis of experiments. John Wiley, New York Montgomery DC (2009) Design and analysis of experiments. John Wiley, New York
47.
Zurück zum Zitat Womack JP, Jones DT (1996) Lean thinking. Simon and Schuster, New York Womack JP, Jones DT (1996) Lean thinking. Simon and Schuster, New York
Metadaten
Titel
An alternative for improving setup times and time between failures aiming at manufacturing lead time reduction
verfasst von
Marcel Heimar Ribeiro Utiyama
Moacir Godinho Filho
Pedro Carlos Oprime
Publikationsdatum
10.04.2021
Verlag
Springer Berlin Heidelberg
Erschienen in
Production Engineering / Ausgabe 5/2021
Print ISSN: 0944-6524
Elektronische ISSN: 1863-7353
DOI
https://doi.org/10.1007/s11740-021-01048-0

Weitere Artikel der Ausgabe 5/2021

Production Engineering 5/2021 Zur Ausgabe

Premium Partner

    Marktübersichten

    Die im Laufe eines Jahres in der „adhäsion“ veröffentlichten Marktübersichten helfen Anwendern verschiedenster Branchen, sich einen gezielten Überblick über Lieferantenangebote zu verschaffen.