39. Causes of Delays in Mega Projects—Case of the Zambian Transmission Power Projects

verfasst von : Chaali Kalebuka, Erastus Mwanaumo, Wellington Didibhuku Thwala

Erschienen in: Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate

Verlag: Springer Singapore

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Zambia is experiencing unprecedentedly high levels of construction activities in the electrical transmission power sector with investments in excess of USD 1 Billion. However, delay has been identified as one of the major recurring problems in these projects with many negative effects such as cost overruns, schedule overruns, lost business opportunities and delayed project benefits. This study aimed at identifying the most important causes of delay and their effects in large transmission power projects in Zambia. A combination of a case study and survey approach was adopted. The questionnaires were distributed to contractors and clients involved in transmission power projects in Zambia. The data collected was analyzed and the factors (causes) of delays ranked to determine the importance and the effects of delays. The results show that the following are the most important causes of delays in transmission power projects in Zambia: rain effect on construction activities; type of project bidding and award; difficulties in financing project by client/owner; delay in approving major changes in the scope by the client; and delays in progress payments by owner. Some of the recommendations made based on the study results were: need for adequate planning and scheduling; engaging of fully dedicated project implementation units (PIUs) which should hasten the approval processes; and to make adjustments to the criteria for contract award to focus less on price (lowest bidder) and more on the contractor’s capabilities and past performances.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Aziz RF (2013) Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Eng J 52:388 Aziz RF (2013) Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Eng J 52:388
Zurück zum Zitat Bruzelius N, Flyvbjerg B, Rothengatter W (2002) Big decisions, big risks. Improving accountability in mega projects. Transp Policy 9:144 Bruzelius N, Flyvbjerg B, Rothengatter W (2002) Big decisions, big risks. Improving accountability in mega projects. Transp Policy 9:144
Zurück zum Zitat Flyvbjerg B (2014a) What you should know about megaprojects and why: an overview. Project Manage J 45(2):7CrossRef Flyvbjerg B (2014a) What you should know about megaprojects and why: an overview. Project Manage J 45(2):7CrossRef
Zurück zum Zitat Flyvbjerg B, Bruzelius N, Rothengatter W (2003) Megaprojects and risk: an anatomy of ambition, 1st ed. Cambridge University Press, Cambridge Flyvbjerg B, Bruzelius N, Rothengatter W (2003) Megaprojects and risk: an anatomy of ambition, 1st ed. Cambridge University Press, Cambridge
Zurück zum Zitat Flyvbjerg B (2014b) What you should know about megaprojects and why: an overview. Project Manage J 45(2):6–19CrossRef Flyvbjerg B (2014b) What you should know about megaprojects and why: an overview. Project Manage J 45(2):6–19CrossRef
Zurück zum Zitat Haidar A, Ellis RD (2010) Analysis and improvement of megaprojects. In: Engineering project organizations conference, South Lake Tahoe, CA Haidar A, Ellis RD (2010) Analysis and improvement of megaprojects. In: Engineering project organizations conference, South Lake Tahoe, CA
Zurück zum Zitat Haseeb M, Bibi A, Rabbani W (2011) Problems of projects and effects of delays in the construction industry of Pakistan. Aust J Bus Manage Res 1(5):41–50 Haseeb M, Bibi A, Rabbani W (2011) Problems of projects and effects of delays in the construction industry of Pakistan. Aust J Bus Manage Res 1(5):41–50
Zurück zum Zitat Koushki PA, Al-Rashid K, Kartam N (2005) Delays and cost increases in the construction of private residential projects in Kuwait. Constr Manage and Econ 23:293CrossRef Koushki PA, Al-Rashid K, Kartam N (2005) Delays and cost increases in the construction of private residential projects in Kuwait. Constr Manage and Econ 23:293CrossRef
Zurück zum Zitat Le-Hoai L, Dai Lee Y, Lee JY (2008) Delay and cost overruns in vietnam large construction projects: a comparison with other selected countries. KSCE J Civ Eng 12(6):368 Le-Hoai L, Dai Lee Y, Lee JY (2008) Delay and cost overruns in vietnam large construction projects: a comparison with other selected countries. KSCE J Civ Eng 12(6):368
Zurück zum Zitat Odeh AM, Battaineh HT (2002) Causes of construction delay: traditional contracts. Int J Project Manage 20:70CrossRef Odeh AM, Battaineh HT (2002) Causes of construction delay: traditional contracts. Int J Project Manage 20:70CrossRef
Zurück zum Zitat Othman AAE (2013) Challenges of mega construction projects in developing countries. Organ Technol Manage Constr Int J 5(1):731 Othman AAE (2013) Challenges of mega construction projects in developing countries. Organ Technol Manage Constr Int J 5(1):731
Zurück zum Zitat Othman AAE (2013b) Challenges of mega construction projects in developing countries. Organ Technol Manage Constr Int J 5(1):734 Othman AAE (2013b) Challenges of mega construction projects in developing countries. Organ Technol Manage Constr Int J 5(1):734
Zurück zum Zitat Ruuska I, Artto K, Aaltonen K, Lehtonen P (2009) Dimensions of distance in a project network: exploring Olkiluoto 3 nuclear power plant project. Int J Project Manage 27:142 Ruuska I, Artto K, Aaltonen K, Lehtonen P (2009) Dimensions of distance in a project network: exploring Olkiluoto 3 nuclear power plant project. Int J Project Manage 27:142
Zurück zum Zitat Sanderson J (2012) Risk, uncertainty and governance in megaprojects: a critical discussion of alternative explanations. Int J Project Manage 30:432CrossRef Sanderson J (2012) Risk, uncertainty and governance in megaprojects: a critical discussion of alternative explanations. Int J Project Manage 30:432CrossRef
Zurück zum Zitat Shore B, Cross BJ (2005) Exploring the role of national culture in the management of large-scale international science projects. Int J Project Manage 23:55–64CrossRef Shore B, Cross BJ (2005) Exploring the role of national culture in the management of large-scale international science projects. Int J Project Manage 23:55–64CrossRef
Zurück zum Zitat Sturup S (2009) Mega projects and governmentality. World Acad Sci Eng Technol 3:833 Sturup S (2009) Mega projects and governmentality. World Acad Sci Eng Technol 3:833
Zurück zum Zitat van Marrewijk A, Clegg SR, Pitsis TS, Veenswijk M (2008) Managing public–private megaprojects: paradoxes, complexity, and project design. Int J Project Manage 26:591–600 van Marrewijk A, Clegg SR, Pitsis TS, Veenswijk M (2008) Managing public–private megaprojects: paradoxes, complexity, and project design. Int J Project Manage 26:591–600
Zurück zum Zitat Zesco (2013) Zesco business plan. Lusaka: s.n Zesco (2013) Zesco business plan. Lusaka: s.n
Metadaten
Titel
Causes of Delays in Mega Projects—Case of the Zambian Transmission Power Projects
verfasst von
Chaali Kalebuka
Erastus Mwanaumo
Wellington Didibhuku Thwala
Copyright-Jahr
2018
Verlag
Springer Singapore
DOI
https://doi.org/10.1007/978-981-10-6190-5_39