CIGI2011: A heuristic method for resource-constrained project scheduling with activity overlapping

verfasst von: Lucas Grèze, Robert Pellerin, Patrice Leclaire, Nathalie Perrier

Erschienen in: Journal of Intelligent Manufacturing | Ausgabe 4/2014

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

The overlapping of activities is a common practice to accelerate the execution of engineering projects. This technique consists in executing in parallel two activities, normally executed in a sequential way, by allowing the downstream activity to start before the end of the upstream activity based on preliminary information. In this paper, we propose a constructive heuristic for the resource-constrained project scheduling problem with overlapping modes (RCPSP-OM). Given a set of activities to execute, the RCPSP-OM consists in determining the order of execution in time of a set of activities so as to minimize the total project duration, while respecting precedence relations, resource constraints and overlapping possibilities. The heuristic implies that rework tasks related to overlapping are added to downstream activities and that the consumption of the resources is constant throughout the execution of the project (including rework). The method also considers that the possible overlapping modes for every couple of activities and the duration of rework tasks associated with every mode are known in advance. Results show that, when the objective consists in minimizing the project duration, the consideration of the costs associated to activity overlapping allows to significantly reducing the cost of reworks. On the other hand, when the objective consists in maximizing the gains related to the project execution, the search for the best trade-off between acceleration and increase of project costs enables to avoid losses.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Banaszak, Z. A., & Zaremba, M. B. (2006). Project-driven planning and scheduling support for virtual manufacturing. Journal of Intelligent Manufacturing, 17(6), 641–651.CrossRef Banaszak, Z. A., & Zaremba, M. B. (2006). Project-driven planning and scheduling support for virtual manufacturing. Journal of Intelligent Manufacturing, 17(6), 641–651.CrossRef
Zurück zum Zitat Bartusch, M., Möhring, R. H., & Radermacher, F. J. (1988). Scheduling project networks with resource constraints and time windows. Annals of Operations Research, 16(1), 199–240.CrossRef Bartusch, M., Möhring, R. H., & Radermacher, F. J. (1988). Scheduling project networks with resource constraints and time windows. Annals of Operations Research, 16(1), 199–240.CrossRef
Zurück zum Zitat Berthaut, F., Grèze, L., Pellerin, R., Perrier, N., & Hajji, A. (2011). Optimal resource-constrained project scheduling with overlapping modes. In Proceedings of international conference on industrial engineering and systems management (pp. 299–308). Metz, France: International Institute for Innovation, Industrial Engineering and Entrepreneurship. Berthaut, F., Grèze, L., Pellerin, R., Perrier, N., & Hajji, A. (2011). Optimal resource-constrained project scheduling with overlapping modes. In Proceedings of international conference on industrial engineering and systems management (pp. 299–308). Metz, France: International Institute for Innovation, Industrial Engineering and Entrepreneurship.
Zurück zum Zitat Berthaut, F., Pellerin, R., Perrier, N., & Hajji, A. (2012). Time-cost trade-offs in resource-constrained project scheduling problems with overlapping modes. International Journal of Project Organisation and Management (to appear). Berthaut, F., Pellerin, R., Perrier, N., & Hajji, A. (2012). Time-cost trade-offs in resource-constrained project scheduling problems with overlapping modes. International Journal of Project Organisation and Management (to appear).
Zurück zum Zitat Blazewicz, J., & Lenstra, J. K. (1983). Scheduling subject to resource constraints: Classification and complexity. Discrete Applied Mathematics, 5(1), 11–24.CrossRef Blazewicz, J., & Lenstra, J. K. (1983). Scheduling subject to resource constraints: Classification and complexity. Discrete Applied Mathematics, 5(1), 11–24.CrossRef
Zurück zum Zitat Bogus, S. M., Molenaar, K. R., & Diekmann, J. E. (2005a). Concurrent engineering approach to reducing design delivery time. Journal of Construction Engineering and Management, 131(11), 1179–1185.CrossRef Bogus, S. M., Molenaar, K. R., & Diekmann, J. E. (2005a). Concurrent engineering approach to reducing design delivery time. Journal of Construction Engineering and Management, 131(11), 1179–1185.CrossRef
Zurück zum Zitat Bogus, S. M., Diekmann, J. E., & Molenaar, K. R. (2005b). Evaluating the consequences of overlapping dependent activities. In Proceedings of the construction research congress 2005, San Diego, Paper 7539, pp. 1–10. Bogus, S. M., Diekmann, J. E., & Molenaar, K. R. (2005b). Evaluating the consequences of overlapping dependent activities. In Proceedings of the construction research congress 2005, San Diego, Paper 7539, pp. 1–10.
Zurück zum Zitat Bogus, S. M., Molenaar, K. R., & Diekmann, J. E. (2006). Strategies for overlapping dependent design activities. Construction Management and Economics, 24, 829–837.CrossRef Bogus, S. M., Molenaar, K. R., & Diekmann, J. E. (2006). Strategies for overlapping dependent design activities. Construction Management and Economics, 24, 829–837.CrossRef
Zurück zum Zitat Browning, T. R. (2001). Applying the design structure matrix to system decomposition and integration problems: A review and new directions. IEEE Transactions on Engineering Management, 48(3), 292–306. Browning, T. R. (2001). Applying the design structure matrix to system decomposition and integration problems: A review and new directions. IEEE Transactions on Engineering Management, 48(3), 292–306.
Zurück zum Zitat Browning, T. R., & Eppinger, S. D. (2002). Modeling impacts of process architecture on cost and schedule risk in product development. IEEE Transactions on Engineering Management, 49(4), 428–442.CrossRef Browning, T. R., & Eppinger, S. D. (2002). Modeling impacts of process architecture on cost and schedule risk in product development. IEEE Transactions on Engineering Management, 49(4), 428–442.CrossRef
Zurück zum Zitat Brucker, P., Drexl, A., Möhring, R., Neumann, K., & Pesch, E. (1999). Resource-constrained project scheduling: Notation, classification, models, and methods. European Journal of Operational Research, 112(1), 3–41.CrossRef Brucker, P., Drexl, A., Möhring, R., Neumann, K., & Pesch, E. (1999). Resource-constrained project scheduling: Notation, classification, models, and methods. European Journal of Operational Research, 112(1), 3–41.CrossRef
Zurück zum Zitat Chen, S. J., & Li, L. (2003). Decomposition of interdependent task group for concurrent engineering. Computers and Industrial Engineering, 44(3), 435–459.CrossRef Chen, S. J., & Li, L. (2003). Decomposition of interdependent task group for concurrent engineering. Computers and Industrial Engineering, 44(3), 435–459.CrossRef
Zurück zum Zitat Cho, S. H., & Eppinger, S. D. (2005). A simulation-based process model for managing complex design projects. IEEE Transactions on Engineering Management, 52(3), 316–328.CrossRef Cho, S. H., & Eppinger, S. D. (2005). A simulation-based process model for managing complex design projects. IEEE Transactions on Engineering Management, 52(3), 316–328.CrossRef
Zurück zum Zitat De Reyck, B., & Herroelen, W. (1998). Branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations. European Journal of Operational research, 111(1), 152–174.CrossRef De Reyck, B., & Herroelen, W. (1998). Branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations. European Journal of Operational research, 111(1), 152–174.CrossRef
Zurück zum Zitat Eppinger, S. D., Whitney, D. E., Smith, R. P., & Gebala, D. A. (1994). A model-based method for organizing tasks in product development. Research in Engineering Design-Theory Applications and Concurrent Engineering, 6(1), 1–13. Eppinger, S. D., Whitney, D. E., Smith, R. P., & Gebala, D. A. (1994). A model-based method for organizing tasks in product development. Research in Engineering Design-Theory Applications and Concurrent Engineering, 6(1), 1–13.
Zurück zum Zitat Fayez, M., Axelsson, P., Oloufa, A. A., & Hosni, Y. (2003). DSM versus CPM: Issues for planning design and construction activities. In Proceedings of the construction research congress, winds of change: Integration and innovation in construction (pp. 181–188). Honolulu, HI: American Society of Civil Engineers. Fayez, M., Axelsson, P., Oloufa, A. A., & Hosni, Y. (2003). DSM versus CPM: Issues for planning design and construction activities. In Proceedings of the construction research congress, winds of change: Integration and innovation in construction (pp. 181–188). Honolulu, HI: American Society of Civil Engineers.
Zurück zum Zitat Gerk, J. E. V., & Qassim, R. Y. (2008). Project acceleration via activity crashing, overlapping, and substitution. IEEE Transactions on Engineering Management, 55(4), 590–601.CrossRef Gerk, J. E. V., & Qassim, R. Y. (2008). Project acceleration via activity crashing, overlapping, and substitution. IEEE Transactions on Engineering Management, 55(4), 590–601.CrossRef
Zurück zum Zitat Globerson, S. (1994). Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), 165–171.CrossRef Globerson, S. (1994). Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), 165–171.CrossRef
Zurück zum Zitat Gray, C. F., Langevin, Y., & Larson, E. W. (2007). Management de projet. Montréal: Chenelière McGraw-Hill. Gray, C. F., Langevin, Y., & Larson, E. W. (2007). Management de projet. Montréal: Chenelière McGraw-Hill.
Zurück zum Zitat Grèze, L., Pellerin, R., Leclaire, P., & Perrier, N. (2011). Evaluating the effectiveness of task overlapping as a risk response strategy in engineering projects. International Journal of Project Organisation and Management (to appear). Grèze, L., Pellerin, R., Leclaire, P., & Perrier, N. (2011). Evaluating the effectiveness of task overlapping as a risk response strategy in engineering projects. International Journal of Project Organisation and Management (to appear).
Zurück zum Zitat Hartmann, S. (1999). Project scheduling under limited resources. Berlin: Springer.CrossRef Hartmann, S. (1999). Project scheduling under limited resources. Berlin: Springer.CrossRef
Zurück zum Zitat Hartmann, S., & Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research, 207(1), 1–14.CrossRef Hartmann, S., & Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research, 207(1), 1–14.CrossRef
Zurück zum Zitat Hasgül, S., Saricicek, I., Ozkan, M., & Parlaktuna, O. (2009). Project-oriented task scheduling for mobile robot team. Journal of Intelligent Manufacturing, 20(2), 151–158.CrossRef Hasgül, S., Saricicek, I., Ozkan, M., & Parlaktuna, O. (2009). Project-oriented task scheduling for mobile robot team. Journal of Intelligent Manufacturing, 20(2), 151–158.CrossRef
Zurück zum Zitat Hegazy, T. (2002). Computer-based construction project management. Upper Saddle River, NJ: Prentice Hall. Hegazy, T. (2002). Computer-based construction project management. Upper Saddle River, NJ: Prentice Hall.
Zurück zum Zitat Herroelen, W., De Reyck, B., & Demeulemeester, E. (1998). Resource constrained project scheduling—A survey of recent developments. Computers and Operations Research, 25(4), 279–302.CrossRef Herroelen, W., De Reyck, B., & Demeulemeester, E. (1998). Resource constrained project scheduling—A survey of recent developments. Computers and Operations Research, 25(4), 279–302.CrossRef
Zurück zum Zitat Herroelen, W. (2005). Project scheduling—Theory and practice. Production and Operations Management, 14(4), 413–432.CrossRef Herroelen, W. (2005). Project scheduling—Theory and practice. Production and Operations Management, 14(4), 413–432.CrossRef
Zurück zum Zitat Jung, Y., & Woo, S. (2004). Flexible work breakdown structure for integrated cost and schedule control. Journal of Construction Engineering and Management-ASCE, 130(5), 616–625.CrossRef Jung, Y., & Woo, S. (2004). Flexible work breakdown structure for integrated cost and schedule control. Journal of Construction Engineering and Management-ASCE, 130(5), 616–625.CrossRef
Zurück zum Zitat Kolisch, R. (1999). Resource allocation capabilities of commercial project management software packages. Interfaces, 29(4), 19–31.CrossRef Kolisch, R. (1999). Resource allocation capabilities of commercial project management software packages. Interfaces, 29(4), 19–31.CrossRef
Zurück zum Zitat Kolisch, R., & Hartmann, S. (2006). Experimental investigation of heuristics for resource-constrained project scheduling: An update. European Journal of Operational Research, 174(1), 23–37.CrossRef Kolisch, R., & Hartmann, S. (2006). Experimental investigation of heuristics for resource-constrained project scheduling: An update. European Journal of Operational Research, 174(1), 23–37.CrossRef
Zurück zum Zitat Kolisch, R., & Sprecher, A. (1997). PSPLIB—A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef Kolisch, R., & Sprecher, A. (1997). PSPLIB—A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef
Zurück zum Zitat Kolisch, R., Sprecher, A., & Drexl, A. (1995). Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science, 41(10), 1693–1703.CrossRef Kolisch, R., Sprecher, A., & Drexl, A. (1995). Characterization and generation of a general class of resource-constrained project scheduling problems. Management Science, 41(10), 1693–1703.CrossRef
Zurück zum Zitat Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, 29(3), 249–272.CrossRef Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, 29(3), 249–272.CrossRef
Zurück zum Zitat Krishnan, V. (1996). Managing the simultaneous execution of coupled phases in concurrent product development. IEEE Transactions on Engineering Management, 43(2), 210–217.CrossRef Krishnan, V. (1996). Managing the simultaneous execution of coupled phases in concurrent product development. IEEE Transactions on Engineering Management, 43(2), 210–217.CrossRef
Zurück zum Zitat Krishnan, V., Eppinger, S. D., & Whitney, D. E. (1997). A model-based framework to overlap product development activities. Management Science, 43(4), 437–451.CrossRef Krishnan, V., Eppinger, S. D., & Whitney, D. E. (1997). A model-based framework to overlap product development activities. Management Science, 43(4), 437–451.CrossRef
Zurück zum Zitat Lee, Y.-H., Kumara, S. R. T., & Chatterjee, K. (2003). Multiagent based dynamic resource scheduling for distributed multiple projects using a market mechanism. Journal of Intelligent Manufacturing, 14(5), 471–484. Lee, Y.-H., Kumara, S. R. T., & Chatterjee, K. (2003). Multiagent based dynamic resource scheduling for distributed multiple projects using a market mechanism. Journal of Intelligent Manufacturing, 14(5), 471–484.
Zurück zum Zitat Liberatore, M. J., & Pollack-Johnson, B. (2006). Extending project time-cost analysis by removing precedence relationships and task streaming. International Journal of Project Management, 24(6), 529–535.CrossRef Liberatore, M. J., & Pollack-Johnson, B. (2006). Extending project time-cost analysis by removing precedence relationships and task streaming. International Journal of Project Management, 24(6), 529–535.CrossRef
Zurück zum Zitat Lin, J., Chai, K. H., Brombacher, A. C., & Wong, Y. S. (2009). Optimal overlapping and functional interaction in product development. European Journal of Operational Research, 196(3), 1158–1169. Lin, J., Chai, K. H., Brombacher, A. C., & Wong, Y. S. (2009). Optimal overlapping and functional interaction in product development. European Journal of Operational Research, 196(3), 1158–1169.
Zurück zum Zitat Lin, J., Qian, Y., Cui, W., & Miao, Z. (2010). Overlapping and communication policies in product development. European Journal of Operational Research, 201(3), 737–750.CrossRef Lin, J., Qian, Y., Cui, W., & Miao, Z. (2010). Overlapping and communication policies in product development. European Journal of Operational Research, 201(3), 737–750.CrossRef
Zurück zum Zitat Loch, C. H., & Terwiesch, C. (1998). Communication and uncertainty in concurrent engineering. Management Science, 44(8), 1032–1048.CrossRef Loch, C. H., & Terwiesch, C. (1998). Communication and uncertainty in concurrent engineering. Management Science, 44(8), 1032–1048.CrossRef
Zurück zum Zitat Maheswari, J. U., & Varghese, K. (2005). Project scheduling using dependency structure matrix. International Journal of Project Management, 23(3), 223–230.CrossRef Maheswari, J. U., & Varghese, K. (2005). Project scheduling using dependency structure matrix. International Journal of Project Management, 23(3), 223–230.CrossRef
Zurück zum Zitat Neumann, K., & Zhan, J. (1995). Heuristics for the minimum project-duration problem with minimal and maximal time lags under fixed resource constraints. Journal of Intelligent Manufacturing, 6(2), 145–154.CrossRef Neumann, K., & Zhan, J. (1995). Heuristics for the minimum project-duration problem with minimal and maximal time lags under fixed resource constraints. Journal of Intelligent Manufacturing, 6(2), 145–154.CrossRef
Zurück zum Zitat Oddi, A., Cesta, A., Policella, N., & Smith, S. F. (2010). Iterative flattening search for resource constrained scheduling. Journal of Intelligent Manufacturing, 21(1), 17–30.CrossRef Oddi, A., Cesta, A., Policella, N., & Smith, S. F. (2010). Iterative flattening search for resource constrained scheduling. Journal of Intelligent Manufacturing, 21(1), 17–30.CrossRef
Zurück zum Zitat Pellerin, R. (1997). Modèle d’ordonnancement dynamique de projets de réfection, Ph.D. Thesis. Montréal: École Polytechnique de Montréal. Pellerin, R. (1997). Modèle d’ordonnancement dynamique de projets de réfection, Ph.D. Thesis. Montréal: École Polytechnique de Montréal.
Zurück zum Zitat Pritsker, A. A. B., Watters, L. J., & Wolfe, P. M. (1969). Multi-project scheduling with limited resources: A zero-one programming approach. Management Science, 16(1), 93–108.CrossRef Pritsker, A. A. B., Watters, L. J., & Wolfe, P. M. (1969). Multi-project scheduling with limited resources: A zero-one programming approach. Management Science, 16(1), 93–108.CrossRef
Zurück zum Zitat Roemer, T. A., Ahmadi, R., & Wang, R. H. (2000). Time-cost trade-offs in overlapped product development. Operations Research, 48(6), 858–865.CrossRef Roemer, T. A., Ahmadi, R., & Wang, R. H. (2000). Time-cost trade-offs in overlapped product development. Operations Research, 48(6), 858–865.CrossRef
Zurück zum Zitat Shue, L.-Y., & Zamani, R. (1999). Intelligent search method for project scheduling problems. Journal of Intelligent Manufacturing, 10(3), 279–288.CrossRef Shue, L.-Y., & Zamani, R. (1999). Intelligent search method for project scheduling problems. Journal of Intelligent Manufacturing, 10(3), 279–288.CrossRef
Zurück zum Zitat Steward, D. V. (1981). The design structure system: A method for managing the design of complex systems. IEEE Transactions on Engineering Management, 28(3), 71–74.CrossRef Steward, D. V. (1981). The design structure system: A method for managing the design of complex systems. IEEE Transactions on Engineering Management, 28(3), 71–74.CrossRef
Zurück zum Zitat Terwiesch, C., & Loch, C. H. (1999). Measuring the effectiveness of overlapping development activities. Management Science, 45(4), 455–465.CrossRef Terwiesch, C., & Loch, C. H. (1999). Measuring the effectiveness of overlapping development activities. Management Science, 45(4), 455–465.CrossRef
Zurück zum Zitat Thiagarasu, V., & Devi, T. (2009). Multi-agent coordination in project scheduling: priority rules based resource allocation. International Journal of Recent Trends in Engineering, 1(2), 42–46. Thiagarasu, V., & Devi, T. (2009). Multi-agent coordination in project scheduling: priority rules based resource allocation. International Journal of Recent Trends in Engineering, 1(2), 42–46.
Zurück zum Zitat Wang, J. T., & Lin, Y. I. (2009). An overlapping process model to assess schedule risk for new product development. Computers and Industrial Engineering, 57(2), 460–474.CrossRef Wang, J. T., & Lin, Y. I. (2009). An overlapping process model to assess schedule risk for new product development. Computers and Industrial Engineering, 57(2), 460–474.CrossRef
Metadaten
Titel
CIGI2011: A heuristic method for resource-constrained project scheduling with activity overlapping
verfasst von
Lucas Grèze
Robert Pellerin
Patrice Leclaire
Nathalie Perrier
Publikationsdatum
01.08.2014
Verlag
Springer US
Erschienen in
Journal of Intelligent Manufacturing / Ausgabe 4/2014
Print ISSN: 0956-5515
Elektronische ISSN: 1572-8145
DOI
https://doi.org/10.1007/s10845-012-0719-5

Weitere Artikel der Ausgabe 4/2014

Journal of Intelligent Manufacturing 4/2014 Zur Ausgabe

    Marktübersichten

    Die im Laufe eines Jahres in der „adhäsion“ veröffentlichten Marktübersichten helfen Anwendern verschiedenster Branchen, sich einen gezielten Überblick über Lieferantenangebote zu verschaffen.