Published in: Neural Computing and Applications 7/2021

29-06-2020 | Original Article

An innovative interval type-2 fuzzy approach for multi-scenario multi-project cash flow evaluation considering TODIM and critical chain with an application to energy sector

Authors: Seyed Ali Mirnezami, Seyed Meysam Mousavi, Vahid Mohagheghi

Published in: Neural Computing and Applications | Issue 7/2021

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Project management has been proven to be an effective tool to manage sophisticated activities. Various techniques of project management have played an essential role for successful project implementation in different areas. Managing projects, especially in a multi-project environment, involves a complex situation because of its distinguishing feature in which a number of projects are being executed simultaneously, that is, they are followed in parallel. Therefore, applying human resources will be more effective and more idle time will be eliminated as well. More so, it can enable people to share their lessons learned from one project to another. With respect to handling a number of projects at the same time by most firms, it is sophisticated for contractors to cope with financial issues of projects, which involve different project cash inflows and outflows. Thus, taking an accurate cash flow prediction into account for projects has been changed into a crucial matter for firms, and lack of this consideration may result in the failure of projects as well. Moreover, there is a desperate need for uncertainties to be addressed thoroughly regarding their vital role for suitable project management. With these in mind, an innovative approach is proposed in this paper to anticipate the cash flow of project by considering type-2 fuzzy extension of both critical chain project management (CCM) for project scheduling and TODIM (an acronym in Portuguese for interactive Multi-Criteria Decision Making) method for selecting the best scenario in a multi-project environment. Hence, type-2 fuzzy numbers are utilized in order to state uncertainties. Eventually, a real-world project in a petro-refinery firm is applied to indicate the capability of the presented approach.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Appendix
Available only for authorised users
Literature
1.
go back to reference Adjei EAG, Fugar FDK, Adinyira E (2019) A review on appropriate tool to predict profitability of building projects using established significant cash flow factors. In: 14th international postgraduate research conference 2019: contemporary and future directions in the built environment, pp 38–44 Adjei EAG, Fugar FDK, Adinyira E (2019) A review on appropriate tool to predict profitability of building projects using established significant cash flow factors. In: 14th international postgraduate research conference 2019: contemporary and future directions in the built environment, pp 38–44
2.
go back to reference Al-Bahar JF, Crandall KC (1990) Systematic risk management approach for construction projects. J Constr Eng Manag 116(3):533–546 Al-Bahar JF, Crandall KC (1990) Systematic risk management approach for construction projects. J Constr Eng Manag 116(3):533–546
3.
go back to reference Balin A, Baraçli H (2017) A fuzzy multi-criteria decision making methodology based upon the interval type-2 fuzzy sets for evaluating renewable energy alternatives in Turkey. Technol Econ Dev Econ 23(5):742–763 Balin A, Baraçli H (2017) A fuzzy multi-criteria decision making methodology based upon the interval type-2 fuzzy sets for evaluating renewable energy alternatives in Turkey. Technol Econ Dev Econ 23(5):742–763
4.
go back to reference Batselier J, Vanhoucke M (2017) Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting. Int J Project Manag 35:28–43 Batselier J, Vanhoucke M (2017) Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting. Int J Project Manag 35:28–43
5.
go back to reference Camps JA (1996) Simple steps help minimize costs risks in project management. Oil Gas J 94(4):32–36 Camps JA (1996) Simple steps help minimize costs risks in project management. Oil Gas J 94(4):32–36
6.
go back to reference Castillo O, Amador-Angulo L, Castro JR, Garcia-Valdez M (2016) A comparative study of type-1 fuzzy logic systems, interval type-2 fuzzy logic systems and generalized type-2 fuzzy logic systems in control problems. Inf Sci 354:257–274 Castillo O, Amador-Angulo L, Castro JR, Garcia-Valdez M (2016) A comparative study of type-1 fuzzy logic systems, interval type-2 fuzzy logic systems and generalized type-2 fuzzy logic systems in control problems. Inf Sci 354:257–274
7.
go back to reference Castillo O, Cervantes L, Soria J, Sanchez M, Castro JR (2016) A generalized type-2 fuzzy granular approach with applications to aerospace. Inf Sci 354:165–177 Castillo O, Cervantes L, Soria J, Sanchez M, Castro JR (2016) A generalized type-2 fuzzy granular approach with applications to aerospace. Inf Sci 354:165–177
8.
go back to reference Celik E, Akyuz E (2018) An interval type-2 fuzzy AHP and TOPSIS methods for decision-making problems in maritime transportation engineering: the case of ship loader. Ocean Eng 155:371–381 Celik E, Akyuz E (2018) An interval type-2 fuzzy AHP and TOPSIS methods for decision-making problems in maritime transportation engineering: the case of ship loader. Ocean Eng 155:371–381
9.
go back to reference Celik E, Gumus AT, Alegoz M (2014) A trapezoidal type-2 fuzzy MCDM method to identify and evaluate critical success factors for humanitarian relief logistics management. J Intell Fuzzy Syst 27(6):2847–2855 Celik E, Gumus AT, Alegoz M (2014) A trapezoidal type-2 fuzzy MCDM method to identify and evaluate critical success factors for humanitarian relief logistics management. J Intell Fuzzy Syst 27(6):2847–2855
10.
go back to reference Chaharsooghi SK, Seyfi Sariqaya M, Rahimnezhad F (2019) Optimization of project cash flow under uncertainty by genetic algorithm. Int J Ind Eng Manag Sci 6(1):24–37 Chaharsooghi SK, Seyfi Sariqaya M, Rahimnezhad F (2019) Optimization of project cash flow under uncertainty by genetic algorithm. Int J Ind Eng Manag Sci 6(1):24–37
11.
go back to reference Chapman CB, Ward S (1997) Project risk management: processes, techniques and insights. Wiley, New YorkMATH Chapman CB, Ward S (1997) Project risk management: processes, techniques and insights. Wiley, New YorkMATH
12.
go back to reference Chen T-Y, Chang C-H, Lu J-FR (2013) The extended QUALIFLEX method for multiple criteria decision analysis based on interval type- 2 fuzzy sets and applications to medical decision making. Eur J Oper Res 226(3):615–625MathSciNetMATH Chen T-Y, Chang C-H, Lu J-FR (2013) The extended QUALIFLEX method for multiple criteria decision analysis based on interval type- 2 fuzzy sets and applications to medical decision making. Eur J Oper Res 226(3):615–625MathSciNetMATH
13.
go back to reference Chen SM, Hong JA (2014) Fuzzy multiple attributes group decision-making based on ranking interval type-2 fuzzy sets and the TOPSIS method. IEEE Trans Syst Man Cybern Syst 44(12):1665–1673 Chen SM, Hong JA (2014) Fuzzy multiple attributes group decision-making based on ranking interval type-2 fuzzy sets and the TOPSIS method. IEEE Trans Syst Man Cybern Syst 44(12):1665–1673
14.
go back to reference Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the interval type-2 TOPSIS method. Expert Syst Appl 37(4):2790–2798 Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the interval type-2 TOPSIS method. Expert Syst Appl 37(4):2790–2798
15.
go back to reference Debnath J, Biswas A (2018) Assessment of occupational risks in construction sites using interval type-2 fuzzy analytic hierarchy process. In: Industry interactive innovations in science, engineering and technology. Springer, Singapore, pp 283–297 Debnath J, Biswas A (2018) Assessment of occupational risks in construction sites using interval type-2 fuzzy analytic hierarchy process. In: Industry interactive innovations in science, engineering and technology. Springer, Singapore, pp 283–297
16.
go back to reference Dereli T, Baykasoglu A, Altun K, Durmusoglu A, Türksen IB (2011) Industrial applications of type-2 fuzzy sets and systems: a concise review. Comput Ind 62(2):125–137 Dereli T, Baykasoglu A, Altun K, Durmusoglu A, Türksen IB (2011) Industrial applications of type-2 fuzzy sets and systems: a concise review. Comput Ind 62(2):125–137
17.
go back to reference Dong JY, Wan SP (2016) Virtual enterprise partner selection integrating LINMAP and TOPSIS. J Oper Res Soc 67(10):1288–1308 Dong JY, Wan SP (2016) Virtual enterprise partner selection integrating LINMAP and TOPSIS. J Oper Res Soc 67(10):1288–1308
18.
go back to reference Dorfeshan Y, Mousavi SM, Mohagheghi V, Vahdani B (2018) Selecting project-critical path by a new interval type-2 fuzzy decision methodology based on MULTIMOORA, MOOSRA and TPOP methods. Comput Ind Eng 120:160–178 Dorfeshan Y, Mousavi SM, Mohagheghi V, Vahdani B (2018) Selecting project-critical path by a new interval type-2 fuzzy decision methodology based on MULTIMOORA, MOOSRA and TPOP methods. Comput Ind Eng 120:160–178
19.
go back to reference Dorfeshan Y, Mousavi SM, Vahdani B, Siadat A (2019) Determining project characteristics and critical path by a new approach based on modified NWRT method and risk assessment under an interval type-2 fuzzy environment. Sci Iran 26(4):2579–2600 Dorfeshan Y, Mousavi SM, Vahdani B, Siadat A (2019) Determining project characteristics and critical path by a new approach based on modified NWRT method and risk assessment under an interval type-2 fuzzy environment. Sci Iran 26(4):2579–2600
20.
go back to reference Ekhtiari M, Yadegari E, Sadidi G (2016) Ranking enterpreneurship main risks in non-profit financial funds by Todim technique under grey conditions (a case study in Iran). Econ Comput Econ Cybern Stud Res 50(3):319–336 Ekhtiari M, Yadegari E, Sadidi G (2016) Ranking enterpreneurship main risks in non-profit financial funds by Todim technique under grey conditions (a case study in Iran). Econ Comput Econ Cybern Stud Res 50(3):319–336
21.
go back to reference Elbeltagi E, Ammar M, Sanad H, Kassab M (2016) Overall multiobjective optimization of construction projects scheduling using particle swarm. Eng Constr Archit Manag 23(3):265–282 Elbeltagi E, Ammar M, Sanad H, Kassab M (2016) Overall multiobjective optimization of construction projects scheduling using particle swarm. Eng Constr Archit Manag 23(3):265–282
23.
go back to reference Eshghi A, Mousavi SM, Mohagheghi V (2019) A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study). Neural Comput Appl 31:5109–5133 Eshghi A, Mousavi SM, Mohagheghi V (2019) A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study). Neural Comput Appl 31:5109–5133
24.
go back to reference Facci AL, Ubertini S (2018) Meta-heuristic optimization for a high-detail smart management of complex energy systems. Energy Convers Manag 160:341–353 Facci AL, Ubertini S (2018) Meta-heuristic optimization for a high-detail smart management of complex energy systems. Energy Convers Manag 160:341–353
25.
go back to reference Ghorabaee MK, Amiri M, Sadaghiani JS, Goodarzi GH (2014) Multiple criteria group decision-making for supplier selection based on COPRAS method with interval type-2 fuzzy sets. Int J Adv Manuf Technol 75(5–8):1115–1130 Ghorabaee MK, Amiri M, Sadaghiani JS, Goodarzi GH (2014) Multiple criteria group decision-making for supplier selection based on COPRAS method with interval type-2 fuzzy sets. Int J Adv Manuf Technol 75(5–8):1115–1130
26.
go back to reference Ghorabaee MK, Zavadskas EK, Amiri M, Esmaeili A (2016) Multi-criteria evaluation of green suppliers using an extended WASPAS method with interval type-2 fuzzy sets. J Clean Prod 137:213–229 Ghorabaee MK, Zavadskas EK, Amiri M, Esmaeili A (2016) Multi-criteria evaluation of green suppliers using an extended WASPAS method with interval type-2 fuzzy sets. J Clean Prod 137:213–229
27.
go back to reference Goldratt EM (1997) Critical chain: a business novel. The North River Press, Great Barrington Goldratt EM (1997) Critical chain: a business novel. The North River Press, Great Barrington
28.
go back to reference Gomes LFAM (2009) An application of the TODIM method to the multicriteria rental evaluation of residential properties. Eur J Oper Res 193(1):204–211MATH Gomes LFAM (2009) An application of the TODIM method to the multicriteria rental evaluation of residential properties. Eur J Oper Res 193(1):204–211MATH
29.
go back to reference Gonzalez CI, Melin P, Castro JR, Mendoza O, Castillo O (2017) General type-2 fuzzy edge detection in the preprocessing of a face recognition system. In: Melin P, Castillo O, Kacprzyk J (eds) Nature-inspired design of hybrid intelligent systems. Springer International Publishing, Berlin, pp 3–18 Gonzalez CI, Melin P, Castro JR, Mendoza O, Castillo O (2017) General type-2 fuzzy edge detection in the preprocessing of a face recognition system. In: Melin P, Castillo O, Kacprzyk J (eds) Nature-inspired design of hybrid intelligent systems. Springer International Publishing, Berlin, pp 3–18
30.
go back to reference Gou X, Xu Z, Liao H (2016) Alternative queuing method for multiple criteria decision making with hybrid fuzzy and ranking information. Inf Sci 357:144–160 Gou X, Xu Z, Liao H (2016) Alternative queuing method for multiple criteria decision making with hybrid fuzzy and ranking information. Inf Sci 357:144–160
31.
go back to reference Guildford WS (1998) Practical risk assessment for project management. Int J Project Manag 16(2):130–131 Guildford WS (1998) Practical risk assessment for project management. Int J Project Manag 16(2):130–131
32.
go back to reference Gul M, Celik E, Gumus AT, Guneri AF (2016) Emergency department performance evaluation by an integrated simulation and interval type-2 fuzzy MCDM-based scenario analysis. Eur J Ind Eng 10(2):196–223 Gul M, Celik E, Gumus AT, Guneri AF (2016) Emergency department performance evaluation by an integrated simulation and interval type-2 fuzzy MCDM-based scenario analysis. Eur J Ind Eng 10(2):196–223
33.
go back to reference Haghighi MH, Mousavi SM, Mohagheghi V (2019) A new soft computing model based on linear assignment and linear programming technique for multidimensional analysis of preference with interval type-2 fuzzy sets. Appl Soft Comput 77:780–796 Haghighi MH, Mousavi SM, Mohagheghi V (2019) A new soft computing model based on linear assignment and linear programming technique for multidimensional analysis of preference with interval type-2 fuzzy sets. Appl Soft Comput 77:780–796
34.
go back to reference Hashemi ST, Kaur H (2017) A hybrid conceptual cost estimating model using ANN and GA for power plant projects. Neural Comput Appl 31:1–12 Hashemi ST, Kaur H (2017) A hybrid conceptual cost estimating model using ANN and GA for power plant projects. Neural Comput Appl 31:1–12
35.
go back to reference He Y, Zhang J, He Z (2019) Metaheuristic algorithms for multimode multiproject scheduling with the objective of positive cash flow balance. IEEE Access 7:157427–157436 He Y, Zhang J, He Z (2019) Metaheuristic algorithms for multimode multiproject scheduling with the objective of positive cash flow balance. IEEE Access 7:157427–157436
36.
go back to reference Hu J, Zhang Y, Chen X, Liu Y (2013) Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl-Based Syst 43:21–29 Hu J, Zhang Y, Chen X, Liu Y (2013) Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl-Based Syst 43:21–29
37.
go back to reference Jo SH, Lee EB, Pyo KY (2018) Integrating a procurement management process into critical chain project management (CCPM): a case-study on oil and gas projects, the piping process. Sustainability 10(6):1817 Jo SH, Lee EB, Pyo KY (2018) Integrating a procurement management process into critical chain project management (CCPM): a case-study on oil and gas projects, the piping process. Sustainability 10(6):1817
38.
go back to reference Kaka A, Price AD (1991) Net cash flow models: are they reliable? Constr Manag Econ 9(3):291–308 Kaka A, Price AD (1991) Net cash flow models: are they reliable? Constr Manag Econ 9(3):291–308
39.
go back to reference Kilic M, Kaya İ (2015) Investment project evaluation by a decision making methodology based on type-2 fuzzy sets. Appl Soft Comput 27:399–410 Kilic M, Kaya İ (2015) Investment project evaluation by a decision making methodology based on type-2 fuzzy sets. Appl Soft Comput 27:399–410
40.
go back to reference Le T, Vu T, Nguyen V (2020) Identifying factors influencing on the cash flow of construction companies: evidence from Vietnam stock exchange. Manag Sci Lett 10(1):255–264 Le T, Vu T, Nguyen V (2020) Identifying factors influencing on the cash flow of construction companies: evidence from Vietnam stock exchange. Manag Sci Lett 10(1):255–264
41.
go back to reference Leach LP (2014) Critical chain project management. Artech House, Norwood Leach LP (2014) Critical chain project management. Artech House, Norwood
42.
go back to reference Liu D, Qi X, Li M, Zhu W, Zhang L, Faiz MA, Cui S (2019) A resilience evaluation method for a combined regional agricultural water and soil resource system based on Weighted Mahalanobis distance and a Gray-TOPSIS model. J Clean Prod 229:667–679 Liu D, Qi X, Li M, Zhu W, Zhang L, Faiz MA, Cui S (2019) A resilience evaluation method for a combined regional agricultural water and soil resource system based on Weighted Mahalanobis distance and a Gray-TOPSIS model. J Clean Prod 229:667–679
43.
go back to reference Liu HC, Hu YP, Wang JJ, Sun M (2018) Failure mode and effects analysis using two-dimensional uncertain linguistic variables and alternative queuing method. IEEE Trans Reliab 68(2):554–565 Liu HC, Hu YP, Wang JJ, Sun M (2018) Failure mode and effects analysis using two-dimensional uncertain linguistic variables and alternative queuing method. IEEE Trans Reliab 68(2):554–565
44.
go back to reference Liu SS, Wang CJ (2010) Profit optimization for multiproject scheduling problems considering cash flow. J Constr Eng Manag 136(12):1268–1278 Liu SS, Wang CJ (2010) Profit optimization for multiproject scheduling problems considering cash flow. J Constr Eng Manag 136(12):1268–1278
45.
go back to reference Lova A, Tormos P (2001) Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling. Ann Oper Res 102(1–4):263–286MathSciNetMATH Lova A, Tormos P (2001) Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling. Ann Oper Res 102(1–4):263–286MathSciNetMATH
46.
go back to reference Maravas A, Pantouvakis JP (2012) Project cash flow analysis in the presence of uncertainty in activity duration and cost. Int J Project Manag 30(3):374–384 Maravas A, Pantouvakis JP (2012) Project cash flow analysis in the presence of uncertainty in activity duration and cost. Int J Project Manag 30(3):374–384
47.
go back to reference Mazlum M, Güneri AF (2015) CPM, PERT and project management with fuzzy logic technique and implementation on a business. Proc-Soc Behav Sci 210:348–357 Mazlum M, Güneri AF (2015) CPM, PERT and project management with fuzzy logic technique and implementation on a business. Proc-Soc Behav Sci 210:348–357
48.
go back to reference Mendel JM (2003) Type-2 fuzzy sets: some questions and answers, IEEE connections, newsletter of the IEEE. Neural Netw Soc 1:10–13 Mendel JM (2003) Type-2 fuzzy sets: some questions and answers, IEEE connections, newsletter of the IEEE. Neural Netw Soc 1:10–13
49.
go back to reference Mendel JM, John RI, Liu F (2006) Interval type-2 fuzzy logic systems made simple. IEEE Trans Fuzzy Syst 14(6):808–821 Mendel JM, John RI, Liu F (2006) Interval type-2 fuzzy logic systems made simple. IEEE Trans Fuzzy Syst 14(6):808–821
50.
go back to reference Mohagheghi V, Mousavi SM, Vahdani B (2017) An assessment method for project cash flow under interval-valued fuzzy environment. J Optim Ind Eng 10(22):73–80 Mohagheghi V, Mousavi SM, Vahdani B (2017) An assessment method for project cash flow under interval-valued fuzzy environment. J Optim Ind Eng 10(22):73–80
51.
go back to reference Mohagheghi V, Mousavi SM, Vahdani B (2017) Analyzing project cash flow by a new interval type-2 fuzzy model with an application to construction industry. Neural Comput Appl 28(11):3393–3411 Mohagheghi V, Mousavi SM, Vahdani B (2017) Analyzing project cash flow by a new interval type-2 fuzzy model with an application to construction industry. Neural Comput Appl 28(11):3393–3411
52.
go back to reference Mohagheghi V, Mousavi SM, Vahdani B, Siadat A (2017) A mathematical modeling approach for high and new technology-project portfolio selection under uncertain environments. J Intell Fuzzy Syst 32(6):4069–4079MATH Mohagheghi V, Mousavi SM, Vahdani B, Siadat A (2017) A mathematical modeling approach for high and new technology-project portfolio selection under uncertain environments. J Intell Fuzzy Syst 32(6):4069–4079MATH
53.
go back to reference Mousakhani S, Nazari-Shirkouhi S, Bozorgi-Amiri A (2017) A novel interval type-2 fuzzy evaluation model based group decision analysis for green supplier selection problems: a case study of battery industry. J Clean Prod 168:205–218 Mousakhani S, Nazari-Shirkouhi S, Bozorgi-Amiri A (2017) A novel interval type-2 fuzzy evaluation model based group decision analysis for green supplier selection problems: a case study of battery industry. J Clean Prod 168:205–218
54.
go back to reference Moradi N, Mousavi SM, Vahdani B (2018) An interval type-2 fuzzy model for project-earned value analysis under uncertainty. J Mult-Valued Logic Soft Comput 30:79–103MATH Moradi N, Mousavi SM, Vahdani B (2018) An interval type-2 fuzzy model for project-earned value analysis under uncertainty. J Mult-Valued Logic Soft Comput 30:79–103MATH
55.
go back to reference Ontiveros-Robles E, Melin P, Castillo O (2018) Comparative analysis of noise robustness of type 2 fuzzy logic controllers. Kybernetika 54(1):175–201MathSciNetMATH Ontiveros-Robles E, Melin P, Castillo O (2018) Comparative analysis of noise robustness of type 2 fuzzy logic controllers. Kybernetika 54(1):175–201MathSciNetMATH
56.
go back to reference Oztaysi B (2015) A group decision making approach using project selection. J Mult Valued Logic Soft Comput 24(5):1–15MathSciNet Oztaysi B (2015) A group decision making approach using project selection. J Mult Valued Logic Soft Comput 24(5):1–15MathSciNet
57.
go back to reference Pate-Cornell ME, Tagaras G, Eisenhardt KM (1990) Dynamic optimization of cash flow management decisions: a stochastic model. IEEE Trans Eng Manag 37(3):203–212 Pate-Cornell ME, Tagaras G, Eisenhardt KM (1990) Dynamic optimization of cash flow management decisions: a stochastic model. IEEE Trans Eng Manag 37(3):203–212
58.
go back to reference Purnus A, Bodea CN (2015) Financial management of the construction projects: a proposed cash flow analysis model at project portfolio level. Organ Technol Manag Constr Int J 7(1):1217–1227 Purnus A, Bodea CN (2015) Financial management of the construction projects: a proposed cash flow analysis model at project portfolio level. Organ Technol Manag Constr Int J 7(1):1217–1227
60.
go back to reference Şengül Ü, Eren M, Shiraz SE, Gezder V, Şengül AB (2015) Fuzzy TOPSIS method for ranking renewable energy supply systems in Turkey. Renew Energy 75:617–625 Şengül Ü, Eren M, Shiraz SE, Gezder V, Şengül AB (2015) Fuzzy TOPSIS method for ranking renewable energy supply systems in Turkey. Renew Energy 75:617–625
61.
go back to reference Shash AA, Qarra AA (2018) Cash flow management of construction projects in Saudi Arabia. Project Manag J 49(5):48–63 Shash AA, Qarra AA (2018) Cash flow management of construction projects in Saudi Arabia. Project Manag J 49(5):48–63
62.
go back to reference Simister SJ (1994) Usage and benefits of project risk analysis and management. Int J Project Manag 12(1):5–10 Simister SJ (1994) Usage and benefits of project risk analysis and management. Int J Project Manag 12(1):5–10
63.
go back to reference Su Y, Lucko G, Thompson RC (2016) Evaluating performance of critical chain project management to mitigate delays based on different schedule network complexities. In: IEEE 2016 winter simulation conference (WSC), pp 3314–3324 Su Y, Lucko G, Thompson RC (2016) Evaluating performance of critical chain project management to mitigate delays based on different schedule network complexities. In: IEEE 2016 winter simulation conference (WSC), pp 3314–3324
64.
go back to reference Tabei SMA, Bagherpour M, Mahmoudi A (2019) Application of fuzzy modelling to predict construction projects cash flow. Period Polytech Civ Eng 63(2):647–659 Tabei SMA, Bagherpour M, Mahmoudi A (2019) Application of fuzzy modelling to predict construction projects cash flow. Period Polytech Civ Eng 63(2):647–659
65.
go back to reference Turner R (2016) Gower handbook of project management. Routledge, London Turner R (2016) Gower handbook of project management. Routledge, London
66.
go back to reference Wei G, Alsaadi FE, Hayat T, Alsaedi A (2017) A linear assignment method for multiple criteria decision analysis with hesitant fuzzy sets based on fuzzy measure. Int J Fuzzy Syst 19(3):607–614MathSciNet Wei G, Alsaadi FE, Hayat T, Alsaedi A (2017) A linear assignment method for multiple criteria decision analysis with hesitant fuzzy sets based on fuzzy measure. Int J Fuzzy Syst 19(3):607–614MathSciNet
67.
go back to reference Wu D, Mendel JM (2007) Aggregation using the linguistic weighted average and interval type-2 fuzzy sets. IEEE Trans Fuzzy Syst 15(6):1145–1161 Wu D, Mendel JM (2007) Aggregation using the linguistic weighted average and interval type-2 fuzzy sets. IEEE Trans Fuzzy Syst 15(6):1145–1161
68.
go back to reference Yu MC, Dang VL, Yeh HC (2017) Measuring cash flow and overdraft for fuzzy project networks with overlapping activities. J Civ Eng Manag 23(4):487–498 Yu MC, Dang VL, Yeh HC (2017) Measuring cash flow and overdraft for fuzzy project networks with overlapping activities. J Civ Eng Manag 23(4):487–498
69.
go back to reference Zadeh LA (1974) Fuzzy logic and its application to approximate reasoning. In: IFIP congress, vol 591 Zadeh LA (1974) Fuzzy logic and its application to approximate reasoning. In: IFIP congress, vol 591
70.
go back to reference Zadeh LA (1975) The concept of a linguistic variable and its application to approximate reasoning—I. Inf Sci 8(3):199–249MathSciNetMATH Zadeh LA (1975) The concept of a linguistic variable and its application to approximate reasoning—I. Inf Sci 8(3):199–249MathSciNetMATH
71.
go back to reference Zarandi MH, Yazdi EH (2008) A type-2 fuzzy rule-based expert system model for portfolio selection. In: 11th joint international conference on information sciences. Atlantis Press Zarandi MH, Yazdi EH (2008) A type-2 fuzzy rule-based expert system model for portfolio selection. In: 11th joint international conference on information sciences. Atlantis Press
72.
go back to reference Zayed T, Amer M, Pan J (2008) Assessing risk and uncertainty inherent in Chinese highway projects using AHP. Int J Project Manag 26(4):408–419 Zayed T, Amer M, Pan J (2008) Assessing risk and uncertainty inherent in Chinese highway projects using AHP. Int J Project Manag 26(4):408–419
73.
go back to reference Zhang J, Elmaghraby SE (2014) The relevance of the “alphorn of uncertainty” to the financial management of projects under uncertainty. Eur J Oper Res 238(1):65–76 Zhang J, Elmaghraby SE (2014) The relevance of the “alphorn of uncertainty” to the financial management of projects under uncertainty. Eur J Oper Res 238(1):65–76
74.
go back to reference Zhang Z, Zhang S (2013) A novel approach to multi attribute group decision making based on trapezoidal interval type-2 fuzzy soft sets. Appl Math Model 37(7):4948–4971MathSciNetMATH Zhang Z, Zhang S (2013) A novel approach to multi attribute group decision making based on trapezoidal interval type-2 fuzzy soft sets. Appl Math Model 37(7):4948–4971MathSciNetMATH
75.
go back to reference Zolfaghari S, Mousavi SM (2018) Construction-project risk assessment by a new decision model based on De-Novo multi-approaches analysis and hesitant fuzzy sets under uncertainty. J Intell Fuzzy Syst 35(1):639–649 Zolfaghari S, Mousavi SM (2018) Construction-project risk assessment by a new decision model based on De-Novo multi-approaches analysis and hesitant fuzzy sets under uncertainty. J Intell Fuzzy Syst 35(1):639–649
Metadata
Title
An innovative interval type-2 fuzzy approach for multi-scenario multi-project cash flow evaluation considering TODIM and critical chain with an application to energy sector
Authors
Seyed Ali Mirnezami
Seyed Meysam Mousavi
Vahid Mohagheghi
Publication date
29-06-2020
Publisher
Springer London
Published in
Neural Computing and Applications / Issue 7/2021
Print ISSN: 0941-0643
Electronic ISSN: 1433-3058
DOI
https://doi.org/10.1007/s00521-020-05095-z

Other articles of this Issue 7/2021

Neural Computing and Applications 7/2021 Go to the issue

Premium Partner