Comparison between Critical Path Method (CPM) and Last Planners System (LPS) for Planning and Scheduling METRO Rail Project of Ahmedabad

Authors : Viraj Parekh, Karan Asnani, Yashraj Bhatt, Rahul Mulchandani

Published in: CIGOS 2019, Innovation for Sustainable Infrastructure

Publisher: Springer Singapore

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

The purpose of this paper is to compare Critical Path Method (CPM) and Last Planner System (LPS) with respect to Planning and Scheduling of METRO Rail Project, Ahmedabad, Gujarat. Critical Path Method emphasises on updating the network for tracking the progress as well as to identify the delays. Last Planner System works on the weekly schedules prepared from the Master Plan and Look-ahead schedules to avoid the delays. One of the stretch from North-South Corridor was selected for the study from Vijaynagar to Usmanpura. The data such as activities, duration of activities, sequence and inter-relation of activities etc. were collected to prepare the network as well as weekly schedules. The network was updated and original network was compared with the updated one and the delays were spotted for the stretch selected. Weekly plans were also prepared for the selected stretch from the look-ahead schedule and Master Plan. PPC (Percent Plan Complete) were calculated to track the progress as per planned schedule. The data were collected by conducting interviews of various personnel and visual observations. Both the approaches (CPM and LPS) have been applied on the selected stretch by action research process. The delays were calculated and studied for both the methods and it was observed that Last Planner System is more appropriate to use for big infrastructure projects like this to avoid time-overrun and consecutive cost over-run. Resources can be well utilized with the Last Planner System, too. The type of this paper is a Case Study.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Metadata
Title
Comparison between Critical Path Method (CPM) and Last Planners System (LPS) for Planning and Scheduling METRO Rail Project of Ahmedabad
Authors
Viraj Parekh
Karan Asnani
Yashraj Bhatt
Rahul Mulchandani
Copyright Year
2020
Publisher
Springer Singapore
DOI
https://doi.org/10.1007/978-981-15-0802-8_81