Perception of Consultants and Contractors to Performance Factors of Construction Projects

Authors : Ayodeji E. Oke, Clinton O. Aigbavboa, Khosi Mohapeloa

Published in: Project Management and BIM for Sustainable Modern Cities

Publisher: Springer International Publishing

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Due to various problems and challenges of construction industry especially in the production and delivery of sustainable infrastructure, performance of construction projects has become an issue of concern not only to contractors and professionals but other stakeholders including clients, project sponsors and end-users. This is due to complexity of construction process, innovation in the use of raw materials and machinery, new construction management techniques and more importantly, change in the demand of clients. Thus, this research evaluates performance indicators for construction projects from the perspective of consultants and contractors. This is to improve construction project performance with a view to enhancing the quest of construction industry of contributing positively to the economy and overall growth of the nation. Using quantitative approach, data were collected through close-ended questionnaires administered on a group of learned consultants and contractors with sufficient knowledge and experience of the construction industry. From the analysed data, there is a significant difference in the perceptions of consultants and contractors regarding factors affecting performance of construction projects. To consultants, general time factors and conformance to specification are the most important performance indicator for project success while from contractors’ view, cost factors including delay in payment from owner to contractor is a major critical success factor. The two groups unilaterally agreed that bringing about the best planning and scheduling technique before and during construction would assist in improving performance of construction projects in the country.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literature
go back to reference Akanni, P.O., Oke, A.E., Akpomiemie, O.A.: Impact of environmental factors on building project performance in Delta State, Nigeria. Hous. Build. Natl. Res. Cent. J. 11(1), 91–97 (2015) Akanni, P.O., Oke, A.E., Akpomiemie, O.A.: Impact of environmental factors on building project performance in Delta State, Nigeria. Hous. Build. Natl. Res. Cent. J. 11(1), 91–97 (2015)
go back to reference Akogbei, R.T., Feng, X., Zhou, J.: Project performance evaluation based on time-cost-design capacity and plant utilization. J. Archit. Civ. Eng. 2(2), 1–9 (2015) Akogbei, R.T., Feng, X., Zhou, J.: Project performance evaluation based on time-cost-design capacity and plant utilization. J. Archit. Civ. Eng. 2(2), 1–9 (2015)
go back to reference Alsakini, W., Wikstrum, K., Kiiras, J.: Proactive schedule management of industrial Turnkey projects in developing countries. Int. J. Project Manag. 22(1), 75–85 (2004)CrossRef Alsakini, W., Wikstrum, K., Kiiras, J.: Proactive schedule management of industrial Turnkey projects in developing countries. Int. J. Project Manag. 22(1), 75–85 (2004)CrossRef
go back to reference Auma, E.: Factors affecting the performance of construction projects in Kenya: a survey of low-rise buildings in Nairobi Central Business District. Int. J. Bus. Manag. 2(10), 115–140 (2014) Auma, E.: Factors affecting the performance of construction projects in Kenya: a survey of low-rise buildings in Nairobi Central Business District. Int. J. Bus. Manag. 2(10), 115–140 (2014)
go back to reference Brown, D., Armstrong, M.: Paying for contribution: real performance-related pay strategies. Kogan, London (1999) Brown, D., Armstrong, M.: Paying for contribution: real performance-related pay strategies. Kogan, London (1999)
go back to reference Chan, D.W.M., Kumaraswamy, M.: Compressing construction durations: lessons learned from Hong Kong building projects. Int. J. Project Manag. 20(1), 23–35 (2002)CrossRef Chan, D.W.M., Kumaraswamy, M.: Compressing construction durations: lessons learned from Hong Kong building projects. Int. J. Project Manag. 20(1), 23–35 (2002)CrossRef
go back to reference Chan, A.P., Scott, D., Chan, A.P.: Factors affecting the success of a construction project. J. Constr. Eng. Manag. 130(1), 153–155 (2004)CrossRef Chan, A.P., Scott, D., Chan, A.P.: Factors affecting the success of a construction project. J. Constr. Eng. Manag. 130(1), 153–155 (2004)CrossRef
go back to reference Chitkara, K.K.: Project management: planning, scheduling and controlling. McGraw Hill, New Delhi (2005) Chitkara, K.K.: Project management: planning, scheduling and controlling. McGraw Hill, New Delhi (2005)
go back to reference Dissanayaka, S.M., Kumaraswamy, M.: Comparing contributors to time and cost performance in building projects. Build. Environ. 34(1), 31–42 (1999)CrossRef Dissanayaka, S.M., Kumaraswamy, M.: Comparing contributors to time and cost performance in building projects. Build. Environ. 34(1), 31–42 (1999)CrossRef
go back to reference El-Nagari, R., Hosny, H., Askari, H.S.: Development of a safety performance index for construction projects in Egypt. Am. J. Civ. Eng. Archit. 3(5), 182–192 (2015) El-Nagari, R., Hosny, H., Askari, H.S.: Development of a safety performance index for construction projects in Egypt. Am. J. Civ. Eng. Archit. 3(5), 182–192 (2015)
go back to reference Errasti, A.R., Roger, B., Aitor, O., Javier, S.: A process for developing partnerships with subcontractors in the construction industry: an empirical study. Int. J. Proj. Manag. 25(3), 250–256 (2007)CrossRef Errasti, A.R., Roger, B., Aitor, O., Javier, S.: A process for developing partnerships with subcontractors in the construction industry: an empirical study. Int. J. Proj. Manag. 25(3), 250–256 (2007)CrossRef
go back to reference Furnham, A.: Performance management systems. Eur. Bus. J. 16(2), 83–94 (2004) Furnham, A.: Performance management systems. Eur. Bus. J. 16(2), 83–94 (2004)
go back to reference Iyer, K.C., Jha, K.N.: Critical factors affecting quality performance in construction projects. Int. J. Project Manag. 17(9), 1155–1170 (2006) Iyer, K.C., Jha, K.N.: Critical factors affecting quality performance in construction projects. Int. J. Project Manag. 17(9), 1155–1170 (2006)
go back to reference Jouini, S., Mahmoud, B., Christophe, M., Gilles, G.: Time-to-market vs. time-to-delivery; managing speed in engineering, procurement and construction projects. Int. J. Project Manag. 22(5), 359–367 (2004)CrossRef Jouini, S., Mahmoud, B., Christophe, M., Gilles, G.: Time-to-market vs. time-to-delivery; managing speed in engineering, procurement and construction projects. Int. J. Project Manag. 22(5), 359–367 (2004)CrossRef
go back to reference Koushki, P.A., Kartam, N.: Impact of construction materials on project time and cost in Kuwait. Eng. Constr. Manag. Econ. J. 11(2), 126–132 (2004) Koushki, P.A., Kartam, N.: Impact of construction materials on project time and cost in Kuwait. Eng. Constr. Manag. Econ. J. 11(2), 126–132 (2004)
go back to reference Ling, F.Y.Y., Low, S.P., Wang, S.Q., Lim, H.H.: Key project management practices affecting Singaporean firms: project performance in China. Int. J. Project Manag. 27(1), 59–71 (2009)CrossRef Ling, F.Y.Y., Low, S.P., Wang, S.Q., Lim, H.H.: Key project management practices affecting Singaporean firms: project performance in China. Int. J. Project Manag. 27(1), 59–71 (2009)CrossRef
go back to reference Masilamani, M.: Key Performance Indicators: Paper Presented at National Conference on Key Performance Indicators (KPis), 19–22 September, Crown Princess Hotel, Kuala Lumpur (2005) Masilamani, M.: Key Performance Indicators: Paper Presented at National Conference on Key Performance Indicators (KPis), 19–22 September, Crown Princess Hotel, Kuala Lumpur (2005)
go back to reference Mbamali, I., Aiyetan, A.O., Kehinde, J.O.: Building design for buildability: an investigation into the current practice in Nigeria. Build. Environ. 40(9), 1267–1274 (2005)CrossRef Mbamali, I., Aiyetan, A.O., Kehinde, J.O.: Building design for buildability: an investigation into the current practice in Nigeria. Build. Environ. 40(9), 1267–1274 (2005)CrossRef
go back to reference Navon, R.: Automated project performance control of construction projects. Autom. Constr. 14(4), 467–476 (2005)CrossRef Navon, R.: Automated project performance control of construction projects. Autom. Constr. 14(4), 467–476 (2005)CrossRef
go back to reference Ng, S.T., Palaneeswaran, E., Kumaraswamy, M.: A dynamic e-reporting system for contractor’s performance appraisal. Adv. Eng. Softw. 33(6), 339–349 (2002)CrossRef Ng, S.T., Palaneeswaran, E., Kumaraswamy, M.: A dynamic e-reporting system for contractor’s performance appraisal. Adv. Eng. Softw. 33(6), 339–349 (2002)CrossRef
go back to reference Oladinrin, T.O., Oke, A.E., Abidoye, R.B, Koleowo, N.A.: Assessment of the critical success factors for healthcare project delivery in Ondo state, Nigeria. In: Ebohon, O.J., Ayeni, D.A., Egbu, C.O., Omole, F.K. (eds.) Proceeding of Joint International Conference on 21st Century Human Habitat: Issues, Sustainability and Development, 21–24 March, Federal University of Technology, Akure, Nigeria, pp. 311–318 (2016) Oladinrin, T.O., Oke, A.E., Abidoye, R.B, Koleowo, N.A.: Assessment of the critical success factors for healthcare project delivery in Ondo state, Nigeria. In: Ebohon, O.J., Ayeni, D.A., Egbu, C.O., Omole, F.K. (eds.) Proceeding of Joint International Conference on 21st Century Human Habitat: Issues, Sustainability and Development, 21–24 March, Federal University of Technology, Akure, Nigeria, pp. 311–318 (2016)
go back to reference Olatunji, S.O., Oke, A.E., Aghimien, D.O., Saidu, S.A.: Effect of construction project performance on economic development of Nigeria. J. Econo. Sustain. Dev. 7(12), 142–149 (2016) Olatunji, S.O., Oke, A.E., Aghimien, D.O., Saidu, S.A.: Effect of construction project performance on economic development of Nigeria. J. Econo. Sustain. Dev. 7(12), 142–149 (2016)
go back to reference Parmenter, D.: Key Performance Indicators, Developing, Implementing and Using Winning KPIs. Wiley, Canada (2010) Parmenter, D.: Key Performance Indicators, Developing, Implementing and Using Winning KPIs. Wiley, Canada (2010)
go back to reference Reichelt, K.L.J.: The dynamic of project performance benchmarking the drivers of cost and schedule overrun. Eur. Manag. J. 17(2), 135–150 (1999)CrossRef Reichelt, K.L.J.: The dynamic of project performance benchmarking the drivers of cost and schedule overrun. Eur. Manag. J. 17(2), 135–150 (1999)CrossRef
go back to reference Shaban, S.A.: Factors Affecting the Performance of Construction Projects in the Gaza Strip. The Islamic University of Gaza, Palestine (2008) Shaban, S.A.: Factors Affecting the Performance of Construction Projects in the Gaza Strip. The Islamic University of Gaza, Palestine (2008)
go back to reference Sweis, R.J., Bisharat, S.M., Bisharat, L., Sweis, G.: Factors affecting contractor performance on public construction projects. Life Sci. J. 11(4), 28–39 (2014) Sweis, R.J., Bisharat, S.M., Bisharat, L., Sweis, G.: Factors affecting contractor performance on public construction projects. Life Sci. J. 11(4), 28–39 (2014)
go back to reference Thomas, S., Wentao, L.: A parallel bargaining protocol for automated sourcing of construction suppliers. Autom. Constr. 15(5), 365–373 (2006) Thomas, S., Wentao, L.: A parallel bargaining protocol for automated sourcing of construction suppliers. Autom. Constr. 15(5), 365–373 (2006)
go back to reference Toor, S.R., Oguniana, S.O.: Problems causing delays in major construction projects in Thailand. Constr. Manag. Econ. 26(4), 395–408 (2008)CrossRef Toor, S.R., Oguniana, S.O.: Problems causing delays in major construction projects in Thailand. Constr. Manag. Econ. 26(4), 395–408 (2008)CrossRef
go back to reference Ugwu, O.O., Haupt, T.C.: Key performance indicators and assessment methods for infrastructure sustainability: a South African construction industry perspective. Build. Environ. 42(6), 665–680 (2007)CrossRef Ugwu, O.O., Haupt, T.C.: Key performance indicators and assessment methods for infrastructure sustainability: a South African construction industry perspective. Build. Environ. 42(6), 665–680 (2007)CrossRef
go back to reference Yakubu, O., Sun, M.: Cost and time control of construction projects: a survey of contractors and consultants in the UK. Constr. Inf. Q. 11(2), 53–59 (2009) Yakubu, O., Sun, M.: Cost and time control of construction projects: a survey of contractors and consultants in the UK. Constr. Inf. Q. 11(2), 53–59 (2009)
Metadata
Title
Perception of Consultants and Contractors to Performance Factors of Construction Projects
Authors
Ayodeji E. Oke
Clinton O. Aigbavboa
Khosi Mohapeloa
Copyright Year
2019
DOI
https://doi.org/10.1007/978-3-030-01905-1_9