2017 | OriginalPaper | Chapter

Project Scheduling with Dynamic Resource Allocation in a Multi-project Environment. Case: Bogotá Electricity Distributor

Authors : Feizar Javier Rueda-Velasco, Carlos Efraín Cubaque, Juan Martin Ibañez Latorre

Published in: Applied Computer Sciences in Engineering

Publisher: Springer International Publishing

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Into the engineering projects is usual to see significant deviations from the planning global duration time to the real achieved. This situation presents some questions about the schedule planning activities effectiveness or control during the execution. The present work develops an algorithm for multi-project scheduling with dynamic resource allocation. The algorithm uses variable total resource availability and priority rules in order to schedule activities and renewable resources, like the manpower or the equipment. System performance has been measured on overall project makespan. The model has been proved using activity networks modeled on dynamic systems software for a case of study in a Bogotá- Colombia electricity distributor. The results have shown a time reduction on the global projects duration time.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literature
1.
go back to reference Project Management Institute: Guía de los fundamentos para la dirección de proyectos, vol. 87, no. 11 (2013) Project Management Institute: Guía de los fundamentos para la dirección de proyectos, vol. 87, no. 11 (2013)
2.
go back to reference Hartmann, S., Briskorn, D.: A survey of variants and extensions of the resource- constrained project scheduling problem. Eur. J. Oper. Res. 207, 1–14 (2010)MathSciNetCrossRefMATH Hartmann, S., Briskorn, D.: A survey of variants and extensions of the resource- constrained project scheduling problem. Eur. J. Oper. Res. 207, 1–14 (2010)MathSciNetCrossRefMATH
3.
go back to reference Canonico, P., Söderlund, J.: Getting control of multi-project organizations: combining contingent control mechanisms. Int. J. Proj. Manag. 28(8), 796–806 (2010)CrossRef Canonico, P., Söderlund, J.: Getting control of multi-project organizations: combining contingent control mechanisms. Int. J. Proj. Manag. 28(8), 796–806 (2010)CrossRef
4.
go back to reference Chavez Guillén, R.M.: Dinamica de sistemas. Diagramas causales, pp. 1–49 (2010) Chavez Guillén, R.M.: Dinamica de sistemas. Diagramas causales, pp. 1–49 (2010)
5.
go back to reference Ballestín González, F., Verdejo, V.: Nuevos métodos de resolución del problema de secuenciación de proyectos con recursos limitados. Tesis doctorals. Universitat de València, Servei de Publicacions, València, p. 1 disc òptic (CD-ROM) (2002) Ballestín González, F., Verdejo, V.: Nuevos métodos de resolución del problema de secuenciación de proyectos con recursos limitados. Tesis doctorals. Universitat de València, Servei de Publicacions, València, p. 1 disc òptic (CD-ROM) (2002)
6.
go back to reference Kolisch, R., Padman, R.: An integrated survey of deterministic project scheduling. Omega 29(3), 249–272 (2001)CrossRef Kolisch, R., Padman, R.: An integrated survey of deterministic project scheduling. Omega 29(3), 249–272 (2001)CrossRef
7.
go back to reference Bey, R.B., Doersh, R.H., Patterson, J.H.: The net present value criterion: its impact on project scheduling. Proj. Manag. Q. 12(2), 35–45 (1981) Bey, R.B., Doersh, R.H., Patterson, J.H.: The net present value criterion: its impact on project scheduling. Proj. Manag. Q. 12(2), 35–45 (1981)
8.
go back to reference Icmeli, T., Rom, W.: Ensuring quality in resource constrained project scheduling. Eur. J. Oper. Res. 103, 483–496 (1997)CrossRefMATH Icmeli, T., Rom, W.: Ensuring quality in resource constrained project scheduling. Eur. J. Oper. Res. 103, 483–496 (1997)CrossRefMATH
9.
go back to reference Elmaghraby, S.: Activity networks: project planning and control by network models, pp. 417–433. Wiley-Interscience Publication, New York (1977)MATH Elmaghraby, S.: Activity networks: project planning and control by network models, pp. 417–433. Wiley-Interscience Publication, New York (1977)MATH
10.
go back to reference Deckro, R., Herbert, F.: Resource constrained project crashing. Int. J. Manag. Sci. 17, 69–79 (1989) Deckro, R., Herbert, F.: Resource constrained project crashing. Int. J. Manag. Sci. 17, 69–79 (1989)
11.
go back to reference Deckro, R.F., Hebert, J.E., Verdini, W.A.: A decomposition approach to multi-project scheduling. Eur. J. Oper. Res. 51, 110–118 (1990)CrossRefMATH Deckro, R.F., Hebert, J.E., Verdini, W.A.: A decomposition approach to multi-project scheduling. Eur. J. Oper. Res. 51, 110–118 (1990)CrossRefMATH
12.
go back to reference Bandelloni, M., Tucci, M., Rinaldi, R.: Optimal resource leveling using non-serial dyanamic programming. Eur. J. Oper. Res. 78(2), 162–177 (1994)CrossRefMATH Bandelloni, M., Tucci, M., Rinaldi, R.: Optimal resource leveling using non-serial dyanamic programming. Eur. J. Oper. Res. 78(2), 162–177 (1994)CrossRefMATH
13.
go back to reference Vanhoucke, M., Debels, D.: The impact of various activity assumptions on the lead time and resource utilization of resource-constrained projects. Comput. Ind. Eng. 54(1), 140–154 (2008)CrossRef Vanhoucke, M., Debels, D.: The impact of various activity assumptions on the lead time and resource utilization of resource-constrained projects. Comput. Ind. Eng. 54(1), 140–154 (2008)CrossRef
14.
go back to reference Schilling, M.A., Vidal, P., Ployhart, R.E., Marangoni, A.: Learning by doing something else: variation, relatedness, and the learning curve. Manage. Sci. 49(1), 39–56 (2003)CrossRef Schilling, M.A., Vidal, P., Ployhart, R.E., Marangoni, A.: Learning by doing something else: variation, relatedness, and the learning curve. Manage. Sci. 49(1), 39–56 (2003)CrossRef
15.
go back to reference Naber, A.: Resource-constrained project scheduling with flexible resource profiles in continuous time. Comput. Oper. Res. 84, 33–45 (2017)MathSciNetCrossRef Naber, A.: Resource-constrained project scheduling with flexible resource profiles in continuous time. Comput. Oper. Res. 84, 33–45 (2017)MathSciNetCrossRef
16.
go back to reference Tritschler, M., Naber, A., Kolisch, R.: A hybrid metaheuristic for resource-constrained project scheduling with flexible resource profiles. Eur. J. Oper. Res. 262(1), 262–273 (2017)MathSciNetCrossRef Tritschler, M., Naber, A., Kolisch, R.: A hybrid metaheuristic for resource-constrained project scheduling with flexible resource profiles. Eur. J. Oper. Res. 262(1), 262–273 (2017)MathSciNetCrossRef
17.
go back to reference Rueda, F., Gonzalez, L.: Modelo para la Medición del impacto de la Variabilidad en Recursos Renovables para la Gestión de Proyectos, Memorias del 7º Congreso Latinoamericano de Dinámica de Sistemas (2009) Rueda, F., Gonzalez, L.: Modelo para la Medición del impacto de la Variabilidad en Recursos Renovables para la Gestión de Proyectos, Memorias del 7º Congreso Latinoamericano de Dinámica de Sistemas (2009)
18.
19.
go back to reference Browning, T.R., Yassine, A.A.: Resource-constrained multi-project scheduling: priority rule performance revisited. Int. J. Prod. Econ. 126(2), 212–228 (2010)CrossRef Browning, T.R., Yassine, A.A.: Resource-constrained multi-project scheduling: priority rule performance revisited. Int. J. Prod. Econ. 126(2), 212–228 (2010)CrossRef
20.
go back to reference Krüger, D., Scholl, A.: A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times. Eur. J. Oper. Res. 197(2), 492–508 (2009)CrossRefMATH Krüger, D., Scholl, A.: A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times. Eur. J. Oper. Res. 197(2), 492–508 (2009)CrossRefMATH
Metadata
Title
Project Scheduling with Dynamic Resource Allocation in a Multi-project Environment. Case: Bogotá Electricity Distributor
Authors
Feizar Javier Rueda-Velasco
Carlos Efraín Cubaque
Juan Martin Ibañez Latorre
Copyright Year
2017
DOI
https://doi.org/10.1007/978-3-319-66963-2_52

Premium Partner