Capital and maintenance costs
The cost of each check dam was taken from government department records and varied from 150,000 to 500,000 Indian Rupees (INR) in their year of construction, which ranged from 1995 to 2005 (Table
6). The benefit cost evaluation here is done in Indian Rupees (INR) in the year 2014. In that year the average exchange rate with the US dollar was 60 INR per US$ (max 63.69, min 58.43).
Table 6
Capital costs and dimensions of check dams and present value of capital costs in 2014 (primary data supplied by Rajasthan Watershed Department and Irrigation Department)
Badgaon | 2001 | 42,000 | 12.7 | 1.57 | 150,000 | 407,900 | 36,200 | 9.7 |
Dharta | 2005 | 140,000 | 66.0 | 1.82 | 500,000 | 999,500 | 88,800 | 7.1 |
Hinta | 2000 | 223,000 | 45.1 | 2.62 | 450,000 | 1,321,700 | 117,000 | 5.9 |
Sunderpura | 1995 | 64,400 | 30.0 | 2.05 | 225,000 | 971,000 | 86,200 | 15.1 |
Total | – | 469,400 | – | – | – | 3,700,000 | 328,200 | 7.9 |
The maintenance costs of each check dam (primarily scraping for silt removal and occasional repairs to concrete structures) were estimated for manual and mechanical scraping (Table
7). No maintenance costs were recorded for the four check dams from their establishment until after 2014, and for Sunderpura check dam there has been no maintenance for 22 years. The check dams had quite different mean annual maintenance costs, which discounted to year 2014 INR, ranged from 0 to 7.3%/year of the capital costs with a mean of 2.9%/year.
Table 7
Record of maintenance of each check dam, showing year, method and cost for each check dam (primary data supplied by Watershed Department, Block Bhindar, Rajasthan)
Badgaon | 2015 | Manual desilting | 2,408 | 150,000 | 139,000 | 10,700 |
Dharta | 2015 | Mechanical desilting | 2,981 | 184,500 | 171,000 | 73,400 |
2016 | Mechanical desilting and repair side walls of weir | 2,676 | 400,000 | 343,000 |
Hinta | 2016 | Mechanical desilting and repair side walls of weir | 936 | 400,000 | 343,000 | 24,500 |
Sunderpura | None | None | 0 | 0 | 0 | 0 |
Total | – | – | 9,000 | 1,134,500 | 995,600 | 108,600 |
Mean | – | – | 2,250 | 284,000 | 248,900 | 27,144c |
Table
8 summarizes the annualized costs expressed in terms of the present value in 2014 INR, for capital, and applied to all check dams with the assumed maintenance cost, taken as the mean from Table
7. It also shows the average annual recharge over the 3 years of record, 2014–2016. Using the approximation that the mean annual recharge in these 3 years represents the mean annual recharge over a 30-year life of these check dams, given this level of maintenance, the average unit cost of annual recharge (CR) is obtained (Eq.
5).
Table 8
Discounted annualized present value costs (INR 2014) for capital and maintenance for each check dam, average annual recharge for 2014–2016, and the resultant unit cost of recharge for each of the four check dams
Badgaon | 36,200 | 27,144 | 63,344 | 104,000 | 0.61 |
Dharta | 88,800 | 27,144 | 115,944 | 212,000 | 0.55 |
Hinta | 117,000 | 27,144 | 144,144 | 397,333 | 0.36 |
Sunderpura | 86,200 | 27,144 | 113,344 | 65,333 | 1.73 |
Total | 328,200 | 108,575 | 436,775 | 778,667 | 0.56 |
Benefits
Benefits were calculated using data provided by the Irrigation Depatment, Rajasthan Department of Agriculture (
2017) and ICAR (
2009) and Eqs. (
6)–(
9). Major rabi season crops are wheat and mustard having on average 44 and 36% of the total cropped area, respectively. Water uses for these two dominant crops were measured in farmers’ fields by installing a water meter near the well head. For the remaining mix of crops, the water use was referred from sources as listed in the footnote of Table
9. The area fraction of opium (0.7%) is very small compared to major crops in Dharta watershed, but to eliminate any possible impression that this crop may be responsible for elevating the determined benefit cost ratios, the net profit and water use of wheat were substituted for opium. This marginally reduced the area-weighted profit per unit volume of water from 2.42 to 2.36 INR/m
3 (in INR 2014) for Dharta watershed using groundwater. This lower value was used in the benefit:cost analysis.
Table 9
Benefits from rabi season crops per unit volume of water use for the existing crop mix
Wheat | 896 | 900 | 1301 | 1032 | 0.443 | 3,408 | 16.1 | 54,869 | 47,029 | 7,840 |
410
d
| 1.91 |
Sorghum | 80 | 80 | 0 | 53 | 0.023 | 1,276 | 12.5 | 15,950 | 23,515 | 4,435 | 500 | 0.89 |
Mustard | 749 | 773 | 982 | 835 | 0.358 | 1,260 | 30.5 | 38,430 | 30,020 | 8,410 |
308
d
| 2.73 |
Isabgol | 75 | 300 | 350 | 242 | 0.104 | 562 | 67.7 | 38,042 | 24,024 | 14,018 | 540 | 2.60 |
Opiumb | 15 | 13 | 20 | 16 | 0.007 | 3,408 | 16.1 | 54,869 | 47,029 | 7,840 | 410 | 1.91 |
Onion | 3 | 6 | 7 | 5 | 0.002 | 9,285 | 12.6 | 117,177 | 77,850 | 39,327 | 640 | 6.14 |
Berseem/ Fodder | 44 | 48 | 53 | 48 | 0.021 | 76,600 | 0.8 | 57,450 | 25,015 | 32,435 | 750 | 4.32 |
Fenugreek | 4 | 0 | 9 | 4 | 0.002 | 1,155 | 42.4 | 48,949 | 30,020 | 18,929 | 240 | 7.89 |
Barley | 0 | 0 | 120 | 40 | 0.017 | 2,700 | 13.5 | 36,396 | 32,019 | 4,377 | 240 | 1.82 |
Gram | 0 | 0 | 28 | 9 | 0.004 | 830 | 44.5 | 36,935 | 27,017 | 9,918 | 300 | 3.31 |
Cumin | 0 | 0 | 131 | 44 | 0.019 | 394 | 170.1 | 67,000 | 42,027 | 24,973 | 724 | 3.45 |
Ajwain | 0 | 0 | 7 | 2 | 0.001 | 637 | 99.5 | 63,401 | 45,030 | 18,371 | 720 | 2.55 |
Total | 1,866 | 2,120 | 3,008 | 2,331 | 1.000 | – | – | – | – | – | – | – |
Meanc | – | – | – | | – | – | – |
46,965
c
|
37,255
c
|
9,984
c
|
400
c
|
2.36
c
|
This paper has addressed only one aspect of the benefits of recharge enhancement, being the main motivation to secure and expand rabi season irrigation supplies. Beernaerts (
2006) proposed an evaluation framework for groundwater recharge enhancement systems for improved irrigated agriculture with economic, social and environmental indicators. In addition to the economic evaluation of the current study, Beernaerts (
2006) proposed evaluating: economic impacts on improved soil fertility using silt removed from check dams; the potential for increase or decrease in fluoride or arsenic concentration in the aquifer and for pollution by faecal pathogens, taking account of water quality improvements (e.g., as reported by Patel
2002 with localized lowering of salinity); the rise in water table with consequent reduction in energy required for pumping, improved conditions for survival of riparian trees and control of saline intrusion in coastal areas; the current externalities faced by downstream communities of reduced water availability for irrigation or city water supply dams and reduced incidences and severity of flooding and erosion. Beernaerts (
2006) also considered a range of financial indicators for evaluating economic impacts of recharge enhancement and suggested that those measures that brought supply side and demand-side (such as water use efficiency) into perspective would have advantage to communities for decision making on water management.
Gale et al. (
2006) reported the results of a project to determine impacts of recharge structures on livelihoods in village communities. Their study showed the reasons why this is difficult. They found that a lack of baseline data on the ‘before’ recharge situation hampered longitudinal comparisons of ‘before’ and ‘after’ income. MAR typically forms one of a number of watershed activities and agricultural reforms aimed at improving resource productivity, generating employment and supporting livelihoods. Hence it would generally not be straight forward to isolate the effects of recharge structures from the other effects. Gale et al. (
2006) proposed that comparisons between ‘with’ and ‘without’ recharge structures also require a control group with a similar environmental and socio-economic profile to the ‘with’ group. This would enable confounding effects of rainfall variations between years and other factors affecting productivity to be removed. Finally, changes in economic conditions, access to infrastructure and other external factors may also impact on agricultural production. Gale et al. (
2006) concluded that “attributing changes in livelihood strategies and outcomes to watershed development, and to MAR specifically, is therefore difficult to do with confidence”. However, surveys of farmers for their records and perceptions did reveal an association between increased livelihoods and streambed recharge structures. The approach used in this current study using recharge volumes from check dams determined from daily water balances, assuming a proportion of this (here 100%) contributes to crop production, and using crop area weighted mix of net profit per cubic meter to value the benefit, is a more rational approach than the ‘before and after’ method, but is not without limitations, as discussed earlier.
A comparable analysis for agricultural value of water use using surface-water irrigation was undertaken by Garg et al. (
2012) in the Upper Bhima sub-basin of Maharashtra. The gross income was calculated using crop yields and support prices of crops for 2003–2004 for a known volume of dam water released and cropped area. Then deducting the cost of cultivation gave net income and water productivity was calculated to range between US$0.02/m
3 and US$0.03/m
3. Other researchers, Hussain et al. (
2007), compiled more recent estimates of the average value of agricultural water in several countries that varied among countries. For Indian irrigated areas, the average value of agricultural water use was estimated as US$0.09/m
3. After accounting for inflation, the higher value of water benefits obtained for the current study (Table
9) is attributed to higher efficiency in the use of groundwater over surface water, as has been observed by Burke and Moench (
2000).
Benefit cost ratio (BCR)
Benefit cost analysis is presented for the four studied check dams of Dharta watershed in Table
10. The unit cost of recharge, CR (Eq.
5), varies from 0.36 to 1.73 INR/m
3 (from Table
8). The unit benefit of recharge, BR (Eq.
8), was found to be 2.36 INR/m
3 (from Table
9) and is assumed constant for all check dams in this area. These unit values attributable to benefits and costs were used to calculate benefit:cost ratio (BCR) which ranged from 1.3 at Sunderpura check dam to 6.4 at Hinta check dam with a mean of 4.1 (Table
10). The Hinta check dam had the highest recharge (about half of the aggregate recharge of the four check dams), the lowest unit costs of recharge, and contributed 57% of aggregate net benefits from all four check dams. This suggests that the siting and design features were well matched for this check dam.
Table 10
Benefits and costs and benefit:cost ratio attributable to recharge from four check dams
Badgaon | 104,000 | 0.61 | 2.36 | 3.9 | 178,000 |
Dharta | 212,000 | 0.55 | 2.36 | 4.3 | 375,000 |
Hinta | 397,333 | 0.36 | 2.36 | 6.6 | 779,000 |
Sunderpura | 65,333 | 1.73 | 2.36 | 1.4 | 39,000 |
Total | 778,667 | – | – | – | 1,371,000 |
Mean
|
–
|
0.56
|
2.36
|
4.1
| – |
The earliest BCR found for Indian streambed recharge structures was for Baramati Taluka of Pune District, Maharashtra, which was declared in 1963 to be an area of “precarious scarcity” with total or near total crop failure occurring in 1 year in 3, due to drought. In response, a combined effort of government and NGOs constructed the first percolation tank in 1968, and by the end of 1978 more than 149 had been built with a combined capacity of 15 Mm
3 (Dillon
1983). Percolation tanks are similar to check dams except that they have an earthen embankment and a separate concrete spillway, rather than just a weir on a stream. At 1980 the feasibility criterion for construction of percolation tanks was for cost to be less than 1.9 INR/m
3 detention capacity and the average value was 0.92INR/m
3 capacity (Dillon
1983). (In the current study this was 7.9 INR/m
3 in 2014 Indian Rupees, approximately, half the cost from 1978 inflated at 8% pa rate to 14.7 INR/m
3.) There were no measurements to enable recharge to be estimated, although Dillon (
1983) recommended installation of gaugeboards and monitoring water levels in streambed structures and wells. The current study demonstrates the value of having such data.
Based on Maharashtra Irrigation Department records, the mean capacity of these first 149 percolation tanks was 98,700 m
3, and the average area benefitted by each tank was estimated to be 36.2 ha. The crop mix in this area was jowar (millet) (45%), wheat (30%), sugar cane (10%), and vegetables, onions and gram (each 5%). The Irrigation Department’s estimated average annual increase in income per tank was 56,000 INR and net costs of production were not reported. The capacity of a tank divided by the estimated benefitted area is 272 mm. This is not inconsistent with water use results for the current study considering crop types and the likelihood of annual recharge to exceed detention capacity. The resulting benefit:cost ratio (BCR) derived by Dillon (
1983) based on a discount rate of 10% was >6. Using a 30-year life and 8% discount rate, as per the current study, BCR would have been 7.0; however, for comparison with current data from Rajasthan (where profit is 28% of the increase in income), and allowing 3% capital costs for annual maintenance, and a 30-year life and 8% discount rate, a BCR of 1.5 is achieved. In the Baramati area the Irrigation Department also estimated a silt loading to percolation tanks of 1.7 m
3/year/ha of catchment area. It would be very informative to record the current status, maintenance history and also the DWIR on these percolation tanks 40–50 years since construction.
The CGWB (
2000)
Guide on Artificial Recharge to Ground Water gives a brief summary of the procedure for undertaking an analysis to determine the benefit:cost ratio (BCR) of a recharge project, and gives the computed BCR for a number of recharge structures in Amravati District, Maharashtra. For three percolation tanks, BCR is 1.3–2.0, increasing with impoundment size (from 49,000 to 132,000 m
3), and with an aggregate mean BCR of 1.76. Cement plugs are smaller, with a typical detention volume of 4,000–10,000m
3, and for ten such structures the estimated BCR ranged from 0.88 to 5.80 with a mean of 1.88. The method of recharge benefit calculation assumed that the difference in recharge, and hence area that can be irrigated resulting in increased crop income, is attributable entirely to the check dam. However, in the current study there are significant variations in recharge and crop production between years due to the amount and pattern of rainfall within the monsoon. This and other agronomic factors would confound estimates of benefits attributable to check dams. A series of years before and after check dam construction would need to be compared to give confidence to these benefit estimates. Another advantage of the method used in this paper is that it can be applied even in the absence of information before the check dam was constructed. As presented in Table
9 for the area-weighted crop mix, the benefits can be calculated from per unit volume of recharged water even in a study period of 3 years. The benefit calculation depends on average crop mix in an area; thus, it can be applied for any check dam within the catchment.
Machiwal et al. (
2004) used the contrast between expected production before and after check dam construction for a hypothetical example consistent with the authors’ perceptions, to estimate benefits of small-water-harvesting structures suitable for catchments smaller than 30 ha in southern Rajasthan. Their analysis used a lifetime of 10 years and a 10% discount rate; the analysis took into account capital costs based on design of the structure and presumed an annual maintenance cost of 10% of capital costs for masonry structures and 25%/year for earthen structures. The net profits per ha of wheat and mustard crops were slightly higher than those used in this current study after taking into account inflation. Importantly, they also considered benefits to occur during the kharif season, with one third of the benefits attributed to extra cropping in the kharif in their lower rainfall (541 mm) study area. In the current study, it was not possible to quantify benefits attributable to check dams of “life-saving” irrigation during dry spells in the monsoon. These benefits were ignored on the conservative presumption that the residual groundwater available for rabi irrigation may be reduced by irrigation in the kharif. Hypothetical benefit:cost ratios calculated by Machiwal et al. (
2004) ranged from 5 for earthen structures to 3.5 and 1.9 for dry stone masonry of simple and more complex design, respectively. They concluded that concrete weirs, which cost considerably more, were not cost-effective in catchments of less than 30 ha.
By 2007 the Central Ground Water Board had revised and expanded its
Manual on Artificial Recharge of Ground Water (CGWB
2007). In this, a chapter is devoted to economic evaluation of recharge schemes. The volume of recharge is estimated from the product of seepage rate, average area of water spread and the duration of storage. This implies monitoring of water levels in the check dam; however, the degree of adherence to this is unknown. Benefits can include income from additional agricultural production, and savings in pumping energy, as well as savings from constructing new tube wells and installing new pumps that would otherwise be done. The CGWB (
2007) template for cost benefit analysis adopts the income from increased production rather than the net income after costs (28% of income in the current study), and the default value suggests crop irrigation requirement is 670–1,000 mm/ year, which is somewhat larger than the 413 mm/year for the cropping mix in the current study. Hence, on balance, the default values in CGWB (
2007) likely overestimate the benefits in comparison with the current study. However conservative default values for annual costs are likely to at least partially compensate, by including an annual interest expenditure of 10% of the capital cost, maintenance and repairs charges of 2.5%, depreciation of civil works 5% and miscellaneous expenditure of 1%. An example of percolation tanks in Baramati Taluka of Pune District, Maharashtra, is given that used a life time of 15 years and very high discount rate of 15% at an undeclared date, with an interest rate on loans of 11.5%. The capital cost of 9 INR/m
3 capacity, pre-2007, would considerably exceed the average capital costs for the current study at 7.9INR (in 2014) /m
3 capacity. The size of the tank evaluated was 130,000m
3, very similar to that of the Dharta check dam. For that example, the present value of costs exceeded the present value of benefits unless a 75% subsidy was applied to the capital cost. It is unclear whether capital costs as well as interest on capital are accounted for in this analysis, but it seems at odds with the BCR of 1.5 re-evaluated for the average of 149 check dams in the Baramati area, as shown in the preceding text.
Malik et al. (
2014) followed a different approach, by interviewing 120 farmers with and without small private rainwater harvesting structures on their land in western Madhya Pradesh and recording the changes in reported crops and livestock. There was negligible change in kharif cropped area and livestock numbers, but a very substantial increase in cropped area in the rabi season followed construction of structures. In this area, of ~800-mm annual rainfall, irrigation water was drawn directly from farm water storages rather than by recharge to the aquifer and then extracting. Benefit cost ratios of 1.9 and 1.5 were found for alluvial and hard-rock areas respectively without a government subsidy. In hard-rock areas, the depth of excavation and hence impoundment depth was constrained. These structures occupied between 6 and 10% of a farmer’s land area, and so it is not surprising that with evaporation losses and low use of water for irrigation in the kharif season, the available irrigation water would be less than detention capacity, so the benefit:cost ratio would be expected to be lower than that found for groundwater recharge structures in wadis found in the current study, where average recharge was 1.66 times detention capacity.