Skip to main content
Erschienen in: Bulletin of Engineering Geology and the Environment 3/2010

01.08.2010 | Original Paper

Jinping hydropower project: main technical issues on engineering geology and rock mechanics

verfasst von: Wu Shiyong, Shen Manbin, Wang Jian

Erschienen in: Bulletin of Engineering Geology and the Environment | Ausgabe 3/2010

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

In 1978, the Jinping Project was designed as an integrated hydroelectric power scheme on the Yalong River in Southwest China. Jinping I involves a 305 m high arch dam on the upstream side of the Great Jinping River Bend. Water is directed through the mountains in four 16.7 km long, c. 13 m diameter tunnels, beneath up to 2,525 m of overburden, to the Jinping II underground powerhouse where the head is 310 m. The combined schemes will produce 8,400 MW and an annual power generation of 40.8 TW.h.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Chengdu Hydropower Investigation & Design and Research Institute (2003) The feasibility Report of Jinping I Hydropower Project, Chengdu, China Chengdu Hydropower Investigation & Design and Research Institute (2003) The feasibility Report of Jinping I Hydropower Project, Chengdu, China
Zurück zum Zitat East China Hydropower Investigation & Design and Research Institute (2005) The feasibility Report of Jinping II Hydropower Project, Hangzhou, China East China Hydropower Investigation & Design and Research Institute (2005) The feasibility Report of Jinping II Hydropower Project, Hangzhou, China
Zurück zum Zitat Gong M, Qi S, Liu J (2009) Engineering geological problems related to high geo-stresses at the Jinping I Hydropower Station, Southwest China. Bull Eng Geol Environ (submitted) Gong M, Qi S, Liu J (2009) Engineering geological problems related to high geo-stresses at the Jinping I Hydropower Station, Southwest China. Bull Eng Geol Environ (submitted)
Zurück zum Zitat Huang R, Lin F, Yan M (2009) Deformation mechanism and stability evaluation for the left abutment slope of Jinping I Hydropower Station. Bull Eng Geol Environ (submitted) Huang R, Lin F, Yan M (2009) Deformation mechanism and stability evaluation for the left abutment slope of Jinping I Hydropower Station. Bull Eng Geol Environ (submitted)
Zurück zum Zitat Jiang Q, Feng X, Xiang T (2009) Rockburst characteristics and numerical simulation based on a new energy index: a case study of a tunnel at 2500 m depth. Bull Eng Geol Environ (submitted) Jiang Q, Feng X, Xiang T (2009) Rockburst characteristics and numerical simulation based on a new energy index: a case study of a tunnel at 2500 m depth. Bull Eng Geol Environ (submitted)
Zurück zum Zitat Qi S, Wu F, Yan F, Lan H (2004) Mechanism of deep cracks in the left bank slope of Jinping first stage hydropower station. Eng Geol 73(1–2):129–144CrossRef Qi S, Wu F, Yan F, Lan H (2004) Mechanism of deep cracks in the left bank slope of Jinping first stage hydropower station. Eng Geol 73(1–2):129–144CrossRef
Zurück zum Zitat Qi S, Wu F, Zhou Y, Song Y, Gong M (2009) Influence of deep seated discontinuities on the left slope of Jinping I Hydropower Station and its stability analysis. Bull Eng Geol Environ (submitted) Qi S, Wu F, Zhou Y, Song Y, Gong M (2009) Influence of deep seated discontinuities on the left slope of Jinping I Hydropower Station and its stability analysis. Bull Eng Geol Environ (submitted)
Zurück zum Zitat Shan Z (2009) High in situ stress break and controlling during excavation of deep-lying tunnel in Jinping II Hydropower Station. Bull Eng Geol Environ (submitted) Shan Z (2009) High in situ stress break and controlling during excavation of deep-lying tunnel in Jinping II Hydropower Station. Bull Eng Geol Environ (submitted)
Zurück zum Zitat Wu F, Hu X, Gong M, Liu J, Ren A (2009) Unloading deformation during layered excavation for the underground powerhouse of Jinping I Hydropower Station, southwest China. Bull Eng Geol Environ (submitted) Wu F, Hu X, Gong M, Liu J, Ren A (2009) Unloading deformation during layered excavation for the underground powerhouse of Jinping I Hydropower Station, southwest China. Bull Eng Geol Environ (submitted)
Metadaten
Titel
Jinping hydropower project: main technical issues on engineering geology and rock mechanics
verfasst von
Wu Shiyong
Shen Manbin
Wang Jian
Publikationsdatum
01.08.2010
Verlag
Springer-Verlag
Erschienen in
Bulletin of Engineering Geology and the Environment / Ausgabe 3/2010
Print ISSN: 1435-9529
Elektronische ISSN: 1435-9537
DOI
https://doi.org/10.1007/s10064-010-0272-4

Weitere Artikel der Ausgabe 3/2010

Bulletin of Engineering Geology and the Environment 3/2010 Zur Ausgabe