First Engineering Commissioning of EAST Tokamak

, , and

Published under licence by IOP Publishing Ltd
, , Citation Wan Yuanxi et al 2006 Plasma Sci. Technol. 8 253 DOI 10.1088/1009-0630/8/3/01

1009-0630/8/3/253

Abstract

Experimental Advanced Superconducting Tokamak (EAST) is the first fully superconducting tokamak. The first commissioning started on Feb. 1st of 2006 and finished on March 30th of 2006 at the Institute of Plasma Physics, Chinese Academy of Sciences. It consists of leakage testing at both room temperature and low temperature, pumping down, cooling down all coils, current leads, bus bar and the thermal shielding, exciting all the coils, measuring magnetic configuration and warming up the magnets. The electromagnetic, thermal hydraulic and mechanical performance of EAST Toroidal Field (TF) and Poloidal Field (PF) magnets have also been tested. All sub-systems, including pumping system, cryogenic system, PF& TF power supply systems, magnet instrumentation system, quench detection and protection system, water cooling system, data acquisition system, main control system, plasma control system (PCS), interlock and safety system have been successfully tested.

Export citation and abstract BibTeX RIS

10.1088/1009-0630/8/3/01