98. Modeling Changes in MDM: Case Study of Irrigation Pipeline Project

verfasst von : Anikesh Paul, J. Uma Maheswari

Erschienen in: Design in the Era of Industry 4.0, Volume 3

Verlag: Springer Nature Singapore

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

It is a well-known fact that changes are unavoidable in any project. Also, these changes can happen anytime during the project tenure—for instance, either in the design or in the construction phase. Additionally, these changes are not identified and traced out as soon as they occur, and hence the impacts induced by these changes keeps progressing in mounds and heaps that it becomes NP-hard to bring the project back to as-planned state in due course of time. Change management is not a new topic and several researchers in the past had investigated and applied promising concepts in the construction industry. In this study, an attempt is made to model the project under multiple dimensions using a matrix-based methodology so that the incompleteness of the project data can be identified with minimal errors, and thereby enable a more realistic estimate of change prediction and impact assessment. Henceforth, the objective of this research study is to realistically capture the information flows in a project using the archived/documented sources and subsequently model the changes using a matrix approach. Here, Multiple Domain Matrix (MDM)-methodology has been chosen for modeling the project and for measuring the impact of the changes that is estimated along the schedule. This concept is demonstrated using the irrigation projects, and the results of this study were well received by the project experts.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literatur
1.
Zurück zum Zitat Chan, D.W.M., Kumaraswamy, M.M.: A comparative study of causes of time overruns in Hong Kong construction projects. Int. J. Proj. Manag. 15(1), 55–63 (1997)CrossRef Chan, D.W.M., Kumaraswamy, M.M.: A comparative study of causes of time overruns in Hong Kong construction projects. Int. J. Proj. Manag. 15(1), 55–63 (1997)CrossRef
2.
Zurück zum Zitat Wu, C.H., Hsieh, T.Y., Cheng, W.L., Lu, S.T.: Grey relation analysis of causes for change orders in highway construction. Constr. Manag. Econ. 22(5), 509–520 (2004)CrossRef Wu, C.H., Hsieh, T.Y., Cheng, W.L., Lu, S.T.: Grey relation analysis of causes for change orders in highway construction. Constr. Manag. Econ. 22(5), 509–520 (2004)CrossRef
3.
Zurück zum Zitat Lindhard, S., Wandahl, S.: Exploration of the reasons for delays in construction. Int. J. Constr. Manag. 14(1), 36–44 (2014) Lindhard, S., Wandahl, S.: Exploration of the reasons for delays in construction. Int. J. Constr. Manag. 14(1), 36–44 (2014)
4.
Zurück zum Zitat Prasad, K.V., Vasugi, V., Venkatesan, R., Bhat, N.S.: Critical causes of time overrun in Indian construction projects and mitigation measures. Int. J. Constr. Educ. Res. 15(3), 216–238 (2019) Prasad, K.V., Vasugi, V., Venkatesan, R., Bhat, N.S.: Critical causes of time overrun in Indian construction projects and mitigation measures. Int. J. Constr. Educ. Res. 15(3), 216–238 (2019)
5.
Zurück zum Zitat Hwang, B.G., Thomas, S.R., Haas, C.T., Caldas, C.H.: Measuring the impact of rework on construction cost performance. J. Constr. Eng. Manag. 135(3), 187–198 (2009)CrossRef Hwang, B.G., Thomas, S.R., Haas, C.T., Caldas, C.H.: Measuring the impact of rework on construction cost performance. J. Constr. Eng. Manag. 135(3), 187–198 (2009)CrossRef
6.
Zurück zum Zitat Sun, M., Meng, X.: Taxonomy for change causes and effects in construction projects. Int. J. Proj. Manag. 27(6), 560–572 (2009)CrossRef Sun, M., Meng, X.: Taxonomy for change causes and effects in construction projects. Int. J. Proj. Manag. 27(6), 560–572 (2009)CrossRef
7.
Zurück zum Zitat Motawa, I.A., Anumba, C.J., Lee, S., Peña-Mora, F.: An integrated system for change management in construction. Autom. Constr. 16(3), 368–377 (2007) CrossRef Motawa, I.A., Anumba, C.J., Lee, S., Peña-Mora, F.: An integrated system for change management in construction. Autom. Constr. 16(3), 368–377 (2007) CrossRef
8.
Zurück zum Zitat Chua, D.K.H., Hossain, M.A.: Predicting change propagation and impact on design schedule due to external changes. IEEE Trans. Eng. Manag. 59(3), 483–493 (2012)CrossRef Chua, D.K.H., Hossain, M.A.: Predicting change propagation and impact on design schedule due to external changes. IEEE Trans. Eng. Manag. 59(3), 483–493 (2012)CrossRef
9.
Zurück zum Zitat Love, P.E.D., Li, H.: Quantifying the causes and costs of rework in construction. Constr. Manag. Econ. 18(4), 479–490 (2000)CrossRef Love, P.E.D., Li, H.: Quantifying the causes and costs of rework in construction. Constr. Manag. Econ. 18(4), 479–490 (2000)CrossRef
10.
Zurück zum Zitat Zidane, Y.J.T., Andersen, B.: The top 10 universal delay factors in construction projects. Int. J. Manag. Proj. Bus. 11(3), 650–672 (2018)CrossRef Zidane, Y.J.T., Andersen, B.: The top 10 universal delay factors in construction projects. Int. J. Manag. Proj. Bus. 11(3), 650–672 (2018)CrossRef
11.
Zurück zum Zitat Padala, S.S., Maheswari, J.U., Hirani, H.: Identification and classification of change causes and effects in construction projects. Int. J. Constr. Manag. 1–20 (2020) Padala, S.S., Maheswari, J.U., Hirani, H.: Identification and classification of change causes and effects in construction projects. Int. J. Constr. Manag. 1–20 (2020)
12.
Zurück zum Zitat Lee, S., Peña-Mora, F., Park, M.: Quality and change management model for large scale concurrent design and construction projects. J. Constr. Eng. Manag. 131(8), 890–902 (2005)CrossRef Lee, S., Peña-Mora, F., Park, M.: Quality and change management model for large scale concurrent design and construction projects. J. Constr. Eng. Manag. 131(8), 890–902 (2005)CrossRef
13.
Zurück zum Zitat Sun, M., Fleming, A., Senaratne, S., Motawa, I., Yeoh, M.L.: A change management toolkit for construction projects. Arch. Eng. Des. Manag. 2(4), 261–271 (2006) Sun, M., Fleming, A., Senaratne, S., Motawa, I., Yeoh, M.L.: A change management toolkit for construction projects. Arch. Eng. Des. Manag. 2(4), 261–271 (2006)
14.
Zurück zum Zitat Al-Kofahi, Z.G., Mahdavian, A., Oloufa, A.: System dynamics modeling approach to quantify change orders impact on labor productivity 1: Principles and model development comparative study. Int. J. Constr. Manag. 1–12 (2020) Al-Kofahi, Z.G., Mahdavian, A., Oloufa, A.: System dynamics modeling approach to quantify change orders impact on labor productivity 1: Principles and model development comparative study. Int. J. Constr. Manag. 1–12 (2020)
15.
Zurück zum Zitat Eckert, C., Clarkson, P.J., Zanker, W.: Change and customization in complex engineering domains. Res. Eng. Des. 15(1), 1–21 (2004)CrossRef Eckert, C., Clarkson, P.J., Zanker, W.: Change and customization in complex engineering domains. Res. Eng. Des. 15(1), 1–21 (2004)CrossRef
16.
Zurück zum Zitat Pasqual, M.C., De Weck, O.L.: Multilayer network model for analysis and management of change propagation. Res. Eng. Des. 23(4), 305–328 (2012)CrossRef Pasqual, M.C., De Weck, O.L.: Multilayer network model for analysis and management of change propagation. Res. Eng. Des. 23(4), 305–328 (2012)CrossRef
17.
Zurück zum Zitat Danilovic, M., Sandkull, B.: The use of dependence structure matrix and domain mapping matrix in managing uncertainty in multiple project situations. Int. J. Proj. Manag. 23(3), 193–203 (2005)CrossRef Danilovic, M., Sandkull, B.: The use of dependence structure matrix and domain mapping matrix in managing uncertainty in multiple project situations. Int. J. Proj. Manag. 23(3), 193–203 (2005)CrossRef
18.
Zurück zum Zitat Padala, S.S.: Application of axiomatic design and design structure matrix for early identification of changes in construction projects. J. Inst. Eng. (India) Ser. A 103(2), 647–661 (2022) Padala, S.S.: Application of axiomatic design and design structure matrix for early identification of changes in construction projects. J. Inst. Eng. (India) Ser. A 103(2), 647–661 (2022)
19.
Zurück zum Zitat Maurer, M., Lindemann, U.: The application of the multiple-domain matrix: considering multiple domains and dependency types in complex product design. In: IEEE International Conference on Systems, Man and Cybernetics, pp. 2487–2493 (2008) Maurer, M., Lindemann, U.: The application of the multiple-domain matrix: considering multiple domains and dependency types in complex product design. In: IEEE International Conference on Systems, Man and Cybernetics, pp. 2487–2493 (2008)
20.
Zurück zum Zitat Padala, S.S., Maheswari, J.U.: Modeling a construction project in a matrix-based framework for managing requirement changes. Int. J. Constr. Manag. 1–22 (2022) Padala, S.S., Maheswari, J.U.: Modeling a construction project in a matrix-based framework for managing requirement changes. Int. J. Constr. Manag. 1–22 (2022)
21.
Zurück zum Zitat Mujumdar, P., Muraleedharan, P., Maheswari, J.U.: Structured methodology for applying multiple domain matrices (MDM) to construction projects. In: Proceedings of the 16th International DSM Conference, pp. 299–308 (2014) Mujumdar, P., Muraleedharan, P., Maheswari, J.U.: Structured methodology for applying multiple domain matrices (MDM) to construction projects. In: Proceedings of the 16th International DSM Conference, pp. 299–308 (2014)
22.
Zurück zum Zitat Maheswari, J.U., Padala, S.S., Sharma, S., Sariyal, S.: Application of MDM for scheduling iteration in construction projects. In: Proceedings of 7th International Conference on Research into Design (ICoRD), pp. 175–184 (2019) Maheswari, J.U., Padala, S.S., Sharma, S., Sariyal, S.: Application of MDM for scheduling iteration in construction projects. In: Proceedings of 7th International Conference on Research into Design (ICoRD), pp. 175–184 (2019)
Metadaten
Titel
Modeling Changes in MDM: Case Study of Irrigation Pipeline Project
verfasst von
Anikesh Paul
J. Uma Maheswari
Copyright-Jahr
2023
Verlag
Springer Nature Singapore
DOI
https://doi.org/10.1007/978-981-99-0428-0_98

    Marktübersichten

    Die im Laufe eines Jahres in der „adhäsion“ veröffentlichten Marktübersichten helfen Anwendern verschiedenster Branchen, sich einen gezielten Überblick über Lieferantenangebote zu verschaffen.