The Influence of the Construction Technology in Time-Cost Relationships of Sewerage Projects

verfasst von: Vitor Sousa, Inês Meireles

Erschienen in: Water Resources Management | Ausgabe 8/2018

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Time-cost models have been developed in various contexts to assist in forecasting the duration of different types of projects. The present research explores the influence of the construction technology on the time-cost relationship. For that purpose, the data from 21 sewerage projects using trenchless technology and from 49 sewerage projects using the traditional open-cut method was analyzed. The 70 sewerage projects analyzed were completed in Chicago, U.S., between 1994 and 2002. The influence of the construction technology in the time-cost relationship was found to be statistically significant and time-relationships were determined for sewerage projects using trenchless technology and the traditional open-cut method. Furthermore, along with the Bromilow type models an alternative approach was tested using the time normalized by the project cost as dependent variable, allowing additional insight into the time performance of the open-cut and lining technology used (cured in place).

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Alfred LE (1988) Construction productivity – on site measurement and management. McGraw-Hill, Sydney Alfred LE (1988) Construction productivity – on site measurement and management. McGraw-Hill, Sydney
Zurück zum Zitat Bromilow FJ (1969) Contract time performance—expectation and the reality. Build Forum 1(3):70–80 Bromilow FJ (1969) Contract time performance—expectation and the reality. Build Forum 1(3):70–80
Zurück zum Zitat Chan APC (2001) Time-cost relationship of public sector projects in Malaysia. Int J Proj Manag 19:223–229CrossRef Chan APC (2001) Time-cost relationship of public sector projects in Malaysia. Int J Proj Manag 19:223–229CrossRef
Zurück zum Zitat Chan APC, Chan DWM (2004) Developing a benchmark model for project construction time performance in Hong Kong. Build Environ 39(3):339–349CrossRef Chan APC, Chan DWM (2004) Developing a benchmark model for project construction time performance in Hong Kong. Build Environ 39(3):339–349CrossRef
Zurück zum Zitat Chan DWM, Kumaraswamy MM (1999) Forecasting construction durations for public housing projects: a Hong Kong perspective. Build Environ 34(5):633–646CrossRef Chan DWM, Kumaraswamy MM (1999) Forecasting construction durations for public housing projects: a Hong Kong perspective. Build Environ 34(5):633–646CrossRef
Zurück zum Zitat Chen WT, Huang Y-H (2006) Approximately predicting the cost and duration of school reconstruction projects in Taiwan. Constr Manag Econ 24(12):1231–1239CrossRef Chen WT, Huang Y-H (2006) Approximately predicting the cost and duration of school reconstruction projects in Taiwan. Constr Manag Econ 24(12):1231–1239CrossRef
Zurück zum Zitat Chitkara K (2001) Construction project management techniques and practice. Tata McGraw-Hill, New Deli Chitkara K (2001) Construction project management techniques and practice. Tata McGraw-Hill, New Deli
Zurück zum Zitat Choudhury I, Rajan SS (2003) Time-cost relationship for residential construction in Texas. Constr Inf Digit Libr w78-2003-73 Choudhury I, Rajan SS (2003) Time-cost relationship for residential construction in Texas. Constr Inf Digit Libr w78-2003-73
Zurück zum Zitat CIDA (1993) Project performance update – a report on the cost and time performance of Australian building projects completed 1988–1993. Construction Industry Development Agency, Australia CIDA (1993) Project performance update – a report on the cost and time performance of Australian building projects completed 1988–1993. Construction Industry Development Agency, Australia
Zurück zum Zitat EPA (2006) Emerging technologies for conveyance systems - new installations and rehabilitation methods. Handbook, EPA 832-R-06-004, United States Environmental Protection Agency (EPA), Office of Wastewater Management, Washington, D.C., USA EPA (2006) Emerging technologies for conveyance systems - new installations and rehabilitation methods. Handbook, EPA 832-R-06-004, United States Environmental Protection Agency (EPA), Office of Wastewater Management, Washington, D.C., USA
Zurück zum Zitat Hoffman GJ, Thal AE Jr, Webb TS, Weir JD (2007) Estimating performance time for construction projects. J Manag Eng 23(4):193–199CrossRef Hoffman GJ, Thal AE Jr, Webb TS, Weir JD (2007) Estimating performance time for construction projects. J Manag Eng 23(4):193–199CrossRef
Zurück zum Zitat Kaka A, Price ADF (1991) Relationship between value and duration of construction projects. Constr Manag Econ 9(4):383–400CrossRef Kaka A, Price ADF (1991) Relationship between value and duration of construction projects. Constr Manag Econ 9(4):383–400CrossRef
Zurück zum Zitat Kenley R (2001) The predictive ability of Bromilow's time-cost model: comment. Constr Manag Econ 19(8):759–764CrossRef Kenley R (2001) The predictive ability of Bromilow's time-cost model: comment. Constr Manag Econ 19(8):759–764CrossRef
Zurück zum Zitat Khosrowshahi F, Kaka AP (1996) Estimation of project total cost and duration for housing projects in the U.K. Build Environ 31(4):373–383CrossRef Khosrowshahi F, Kaka AP (1996) Estimation of project total cost and duration for housing projects in the U.K. Build Environ 31(4):373–383CrossRef
Zurück zum Zitat Kumaraswamy MM, Chan DWM (1995) Determinants of construction duration. Constr Manag Econ 13:209–217CrossRef Kumaraswamy MM, Chan DWM (1995) Determinants of construction duration. Constr Manag Econ 13:209–217CrossRef
Zurück zum Zitat Love PED, Tse RYC, Edwards DJ (2005) Time–cost relationships in Australian building construction projects. J Constr Eng Manag 131(2):187–194CrossRef Love PED, Tse RYC, Edwards DJ (2005) Time–cost relationships in Australian building construction projects. J Constr Eng Manag 131(2):187–194CrossRef
Zurück zum Zitat Martin J, Burrows T, Pegg I (2006) Predicting construction duration of building projects. Shaping the Change, XXIII FIG Congress, Munich, Germany, October 8-13 Martin J, Burrows T, Pegg I (2006) Predicting construction duration of building projects. Shaping the Change, XXIII FIG Congress, Munich, Germany, October 8-13
Zurück zum Zitat NEDO (1988) Faster building for commerce. National Economic Development Office (NEDO). Millbank, UK NEDO (1988) Faster building for commerce. National Economic Development Office (NEDO). Millbank, UK
Zurück zum Zitat Skitmore RM, Ng ST (2003) Forecast models for actual construction time and cost. Build Environ 8(8):1075–1083CrossRef Skitmore RM, Ng ST (2003) Forecast models for actual construction time and cost. Build Environ 8(8):1075–1083CrossRef
Zurück zum Zitat Sousa V (2012) Risk management in construction: application to urban drainage projects. Ph.D. Thesis, IST – Universidade de Lisboa, Lisbon, Portugal. (in Portuguese) Sousa V (2012) Risk management in construction: application to urban drainage projects. Ph.D. Thesis, IST – Universidade de Lisboa, Lisbon, Portugal. (in Portuguese)
Zurück zum Zitat Sousa V, Almeida N, Dias L, Branco F (2014a) Risk-informed time-cost relationship models for sanitation projects. J Constr Eng Manag 140(5):06014002CrossRef Sousa V, Almeida N, Dias L, Branco F (2014a) Risk-informed time-cost relationship models for sanitation projects. J Constr Eng Manag 140(5):06014002CrossRef
Zurück zum Zitat Sousa V, Almeida N, Dias L (2014b) Role of statistics and engineering judgment in developing optimized time-cost relationship models. J Constr Eng Manag 140(8):04014034CrossRef Sousa V, Almeida N, Dias L (2014b) Role of statistics and engineering judgment in developing optimized time-cost relationship models. J Constr Eng Manag 140(8):04014034CrossRef
Zurück zum Zitat Walker DHT (1994) An investigation into factors that determine building construction time performance. PhD thesis, Royal Melbourne Institute of Technology, Australia Walker DHT (1994) An investigation into factors that determine building construction time performance. PhD thesis, Royal Melbourne Institute of Technology, Australia
Zurück zum Zitat Yousef G, Baccarini D (2001) Developing a cost–time model for estimating construction durations of sewerage projects in Perth, Western Australia. J Constr Res 2(2):213–220 Yousef G, Baccarini D (2001) Developing a cost–time model for estimating construction durations of sewerage projects in Perth, Western Australia. J Constr Res 2(2):213–220
Metadaten
Titel
The Influence of the Construction Technology in Time-Cost Relationships of Sewerage Projects
verfasst von
Vitor Sousa
Inês Meireles
Publikationsdatum
13.03.2018
Verlag
Springer Netherlands
Erschienen in
Water Resources Management / Ausgabe 8/2018
Print ISSN: 0920-4741
Elektronische ISSN: 1573-1650
DOI
https://doi.org/10.1007/s11269-018-1956-y

Weitere Artikel der Ausgabe 8/2018

Water Resources Management 8/2018 Zur Ausgabe