The Use of Type-2 Fuzzy Sets to Assess Delays in the Implementation of the Daily Operation Plan for the Operating Theatre

verfasst von : Barbara Gładysz, Anna Skowrońska-Szmer, Wojciech Nowak

Erschienen in: Computational Science – ICCS 2021

Verlag: Springer International Publishing

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

In the paper we present a critical time analysis of the project, in which there is a risk of delay in commencing project activities. We assume that activity times are type-2 fuzzy numbers. When experts estimate shapes of membership functions of times of activities, they take into account both situations when particular activities of the project start on time and situations when they start with a delay. We also suggest a method of a sensitivity analysis of these delays to meeting the project deadline. We present a case study in which the critical tome analysis was used to analyse processes implemented in the operating ward of a selected hospital in the South of Poland. Data for the empirical study was collected in the operating theatre of this hospital. This made it possible to identify non-procedural activities at the operating ward that have a significant impact on the duration of the entire operating process. In the hospital selected for testing implementation of the daily plan of surgeries was at risk every day. The research shows that the expected delay in performing the typical daily plan - two surgeries in one operating room – could be about 1 h. That may result in significant costs of overtime. Additionally, the consequence may also include extension of the queue of patients waiting for their surgeries. We show that elimination of occurrence of surgery activity delays allows for execution of the typical daily plan of surgeries within a working day in the studied hospital.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Fußnoten
1
In order to find the sum and the maximum of interval fuzzy numbers one may apply the rule of dividing a part [0, 1] of the value of membership functions into intervals and to find approximate value of the maximum, applying interval arithmetic for those intervals.
 
Literatur
1.
Zurück zum Zitat Gṻr, S., Eren, T.: Application of operational research techniques in operating room scheduling problems: Literature Overview. J. Healthcare Eng. 2018(5341394), 15 (2018) Gṻr, S., Eren, T.: Application of operational research techniques in operating room scheduling problems: Literature Overview. J. Healthcare Eng. 2018(5341394), 15 (2018)
2.
Zurück zum Zitat Al-Refaie, A., Judeh, M., Li, M.-H.: Optimal fuzzy scheduling and sequencing of multiple-period operating room. Artif. Intell. Eng. Des. Anal. Manuf. 32(1), 108–121 (2018)CrossRef Al-Refaie, A., Judeh, M., Li, M.-H.: Optimal fuzzy scheduling and sequencing of multiple-period operating room. Artif. Intell. Eng. Des. Anal. Manuf. 32(1), 108–121 (2018)CrossRef
3.
Zurück zum Zitat Dexter, F., Macario, A., Traub, R.D.: Which algorithm for scheduling add-on elective cases maximizes operating room utilization? Use of bin packing algorithms and fuzzy constraints in operating room management. Anesthesiolog 91(5), 1491–2150 (1999)CrossRef Dexter, F., Macario, A., Traub, R.D.: Which algorithm for scheduling add-on elective cases maximizes operating room utilization? Use of bin packing algorithms and fuzzy constraints in operating room management. Anesthesiolog 91(5), 1491–2150 (1999)CrossRef
5.
Zurück zum Zitat Rachuba, S., Werners, B.: A Fuzzy multi-criteria approach for robust operating room schedules. Ann. Oper. Res. 251(1–2), 325–351 (2017)MathSciNetCrossRef Rachuba, S., Werners, B.: A Fuzzy multi-criteria approach for robust operating room schedules. Ann. Oper. Res. 251(1–2), 325–351 (2017)MathSciNetCrossRef
6.
Zurück zum Zitat Gṻl, M., Gṻneri, A.F., Gṻnes, G.: Project management in healthcare: a case study for patient flow evaluation in an emergency room using fuzzy CPM and fuzzy PERT. Sigma J. Eng. Natiral Sci. 8(1), 41–51 (2017) Gṻl, M., Gṻneri, A.F., Gṻnes, G.: Project management in healthcare: a case study for patient flow evaluation in an emergency room using fuzzy CPM and fuzzy PERT. Sigma J. Eng. Natiral Sci. 8(1), 41–51 (2017)
7.
Zurück zum Zitat Nazif, H., Makis, V.: Operating room surgery scheduling with fuzzy surgery durations using a metaheuristic approach. Adv. Oper. Res. 2018(8637598), 8 (2018) Nazif, H., Makis, V.: Operating room surgery scheduling with fuzzy surgery durations using a metaheuristic approach. Adv. Oper. Res. 2018(8637598), 8 (2018)
8.
Zurück zum Zitat Lahijanian, B., Zarandi, M.F., Farahani, F.V.: Proposing a model for operating” room scheduling based on fuzzy surgical duration. In: Annual Conference of the North American Fuzzy Information Processing Society (NAFIPS), IEEE, El Paso, TX, USA (2016) Lahijanian, B., Zarandi, M.F., Farahani, F.V.: Proposing a model for operating” room scheduling based on fuzzy surgical duration. In: Annual Conference of the North American Fuzzy Information Processing Society (NAFIPS), IEEE, El Paso, TX, USA (2016)
9.
Zurück zum Zitat Wang, D., Xu, J.: A fuzzy multi-objective optimizing scheduling for operation room in hospital. In: IEEE International Conference on Industrial Engineering and Engineering Management, pp. 614–618 (2008) Wang, D., Xu, J.: A fuzzy multi-objective optimizing scheduling for operation room in hospital. In: IEEE International Conference on Industrial Engineering and Engineering Management, pp. 614–618 (2008)
10.
Zurück zum Zitat Behmanesh, R., Zendieh, M., Hadji Molana, S.M.: The surgical case scheduling problem with fuzzy duration time: an ant system algorithm. Scientia Iranica E 26(3), 1824–1841 (2018) Behmanesh, R., Zendieh, M., Hadji Molana, S.M.: The surgical case scheduling problem with fuzzy duration time: an ant system algorithm. Scientia Iranica E 26(3), 1824–1841 (2018)
11.
Zurück zum Zitat Behmanesh, R., Zendieh, M.: Surgical case scheduling problem with fuzzy surgery time: an advances bi-objective ant system approach. Knowl.-Based Syst. 186, 104913 (2019)CrossRef Behmanesh, R., Zendieh, M.: Surgical case scheduling problem with fuzzy surgery time: an advances bi-objective ant system approach. Knowl.-Based Syst. 186, 104913 (2019)CrossRef
12.
Zurück zum Zitat Moore, R.E.: Interval Analysis. Prentice-Hall, Englewood Cliff (1966)MATH Moore, R.E.: Interval Analysis. Prentice-Hall, Englewood Cliff (1966)MATH
13.
17.
Zurück zum Zitat Mendel, J., Wu, D.: Linguistic summarization using IF–THEN rules and interval type-2 fuzzy sets. IEEE Trans. Fuzzy Syst. 19(1), 136–151 (2010) Mendel, J., Wu, D.: Linguistic summarization using IF–THEN rules and interval type-2 fuzzy sets. IEEE Trans. Fuzzy Syst. 19(1), 136–151 (2010)
18.
Zurück zum Zitat Dinagar, D.S.; Anabalagan, A.A.: New type -2 fuzzy number arithmetic using extension principle. In: IEEE- International Conference on Advances in Engineering, Science and Management (ICAEMS-2012), pp. 30–31 (2012) Dinagar, D.S.; Anabalagan, A.A.: New type -2 fuzzy number arithmetic using extension principle. In: IEEE- International Conference on Advances in Engineering, Science and Management (ICAEMS-2012), pp. 30–31 (2012)
19.
Zurück zum Zitat Gładysz, B.: Type-2 fuzzy numbers in models of the duration of a project affected by risk. J. Decis. Syst. p. 8 (2020) Gładysz, B.: Type-2 fuzzy numbers in models of the duration of a project affected by risk. J. Decis. Syst. p. 8 (2020)
20.
Zurück zum Zitat Hu, J., Zhang, Y., Chen, X., Liu, Y.: Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl.-Based Syst. 43, 21–29 (2013)CrossRef Hu, J., Zhang, Y., Chen, X., Liu, Y.: Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl.-Based Syst. 43, 21–29 (2013)CrossRef
21.
Zurück zum Zitat Malcolm, D.G., Roseboom, J.H., Clark, C.E., Fazar, W.: Application of a technique for research and development program evaluation. Oper. Res. 7, 646–669 (1959)CrossRef Malcolm, D.G., Roseboom, J.H., Clark, C.E., Fazar, W.: Application of a technique for research and development program evaluation. Oper. Res. 7, 646–669 (1959)CrossRef
22.
Zurück zum Zitat Carlsson, C., Fullér, R.: On possibilistic mean value and variance of fuzzy numbers. Fuzzy Sets Syst. 122, 315–326 (2001)MathSciNetCrossRef Carlsson, C., Fullér, R.: On possibilistic mean value and variance of fuzzy numbers. Fuzzy Sets Syst. 122, 315–326 (2001)MathSciNetCrossRef
23.
Zurück zum Zitat Santibáñez, P.S., Chow, V.S., French, J., Puterman, M.L., Tyldesley, S.: Reducing patient wait times and improving resource utilization at British Columbia cancer agency’s ambulatory care unit through simulation. Health Care Manag. Sci. 12, 392–407 (2009)CrossRef Santibáñez, P.S., Chow, V.S., French, J., Puterman, M.L., Tyldesley, S.: Reducing patient wait times and improving resource utilization at British Columbia cancer agency’s ambulatory care unit through simulation. Health Care Manag. Sci. 12, 392–407 (2009)CrossRef
Metadaten
Titel
The Use of Type-2 Fuzzy Sets to Assess Delays in the Implementation of the Daily Operation Plan for the Operating Theatre
verfasst von
Barbara Gładysz
Anna Skowrońska-Szmer
Wojciech Nowak
Copyright-Jahr
2021
DOI
https://doi.org/10.1007/978-3-030-77980-1_37