2019 | OriginalPaper | Chapter

Causes of Delay and Cost Overrun in Malaysian Construction Industry

Authors : Muhammad Muhammad Tahir, Nuzul Azam Haron, Aidi Hizami Alias, Ikechukwu A. Diugwu

Published in: GCEC 2017

Publisher: Springer Singapore

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

The construction industry in Malaysia drives the economic growth and development of the country. However, the industry is plagued with delays and cost overrun which transforms what should have been successful projects to projects incurring additional costs, disagreements, litigation and in some cases abandonment of projects. This research studied the causes of delays and cost overrun in the industry and ranked them according to their perceived importance to the contractors, with a view to establishing those to be addressed by the contractors. Online questionnaires were used for data collection for this research. A total of 69 responses were analysed using principal component analysis (PCA) (factor analysis) to identify the main causes. The result of the analysis showed that delay in preparation of design document, poor schedule and control of time, delay in delivery of material to site, lack of knowledge about the different defined execution methods, shortage of labour and material in market, and changes in scope of work were the main causes of delay and cost overrun. The identified causes if properly addressed would reduce the rate of delays and cost overrun in construction projects, thus enhancing the economic growth and development of the country.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literature
1.
go back to reference Department of Statistics (DOSM): National Accounts: Quarterly Gross Domestic Product (Fourth Quarter 2016). Department of Statistics, Editor. 2017, Department of Statistics, Malaysia: Kuala Lumpur (2017) Department of Statistics (DOSM): National Accounts: Quarterly Gross Domestic Product (Fourth Quarter 2016). Department of Statistics, Editor. 2017, Department of Statistics, Malaysia: Kuala Lumpur (2017)
2.
go back to reference Alaghbari, W.E., et al.: The significant factors causing delay of building construction projects in Malaysia. Eng. Constr. Architectural Manag. 14(2), 192–206 (2007)CrossRef Alaghbari, W.E., et al.: The significant factors causing delay of building construction projects in Malaysia. Eng. Constr. Architectural Manag. 14(2), 192–206 (2007)CrossRef
3.
go back to reference Shehu, Z., Endut, I.R., Akintoye, A.: Factors contributing to project time and hence cost overrun in the Malaysian construction industry. J. Financ. Manage. Property Constr. 19(1), 55–75 (2014)CrossRef Shehu, Z., Endut, I.R., Akintoye, A.: Factors contributing to project time and hence cost overrun in the Malaysian construction industry. J. Financ. Manage. Property Constr. 19(1), 55–75 (2014)CrossRef
4.
go back to reference Minchin Jr., R.E., et al.: Comparison of cost and time performance of design-build and design-bid-build delivery systems in Florida. J. Constr. Eng. Manage. 139(10), 04013007 (2013)CrossRef Minchin Jr., R.E., et al.: Comparison of cost and time performance of design-build and design-bid-build delivery systems in Florida. J. Constr. Eng. Manage. 139(10), 04013007 (2013)CrossRef
5.
go back to reference Forbes, L.H., Ahmed, S.M.: Modern Construction: Lean Project Delivery and Integrated Practices (2010) (CRC Press)CrossRef Forbes, L.H., Ahmed, S.M.: Modern Construction: Lean Project Delivery and Integrated Practices (2010) (CRC Press)CrossRef
6.
go back to reference Rasdorf, W.J., Abudayyeh, O.Y.: Cost-and schedule-control integration: issues and needs. J. Constr. Eng. Manage. 117(3), 486–502 (1991)CrossRef Rasdorf, W.J., Abudayyeh, O.Y.: Cost-and schedule-control integration: issues and needs. J. Constr. Eng. Manage. 117(3), 486–502 (1991)CrossRef
7.
go back to reference Flyvbjerg, B., Holm, M.S., Buhl, S.: Underestimating costs in public works projects: error or lie? J. Am. Plann. Assoc. 68(3), 279–295 (2009)CrossRef Flyvbjerg, B., Holm, M.S., Buhl, S.: Underestimating costs in public works projects: error or lie? J. Am. Plann. Assoc. 68(3), 279–295 (2009)CrossRef
8.
go back to reference Enshassi, A., Al-Najjar, J., Kumaraswamy, M.: Delays and cost overruns in the construction projects in the Gaza Strip. J. Financ. Manage. Property Constr. 14(2), 126–151 (2009)CrossRef Enshassi, A., Al-Najjar, J., Kumaraswamy, M.: Delays and cost overruns in the construction projects in the Gaza Strip. J. Financ. Manage. Property Constr. 14(2), 126–151 (2009)CrossRef
9.
go back to reference JBIM: Official publication of the national BIM standard (NBIMS) and the national institute of building science. J. Build. Inf. Model (2007) (Washington D.C.) JBIM: Official publication of the national BIM standard (NBIMS) and the national institute of building science. J. Build. Inf. Model (2007) (Washington D.C.)
10.
go back to reference Ismail, I., et al.: Comparative Study on Time Management Practices in Construction Industry Between Kedah and Kelantan (2013) Ismail, I., et al.: Comparative Study on Time Management Practices in Construction Industry Between Kedah and Kelantan (2013)
11.
go back to reference Rahman, I.A., et al.: Time and cost performance of costruction projects in southern and cenrtal regions of Penisular Malaysia. In: 2012 IEEE Colloquium on Humanities, Science and Engineering (CHUSER) (2012) Rahman, I.A., et al.: Time and cost performance of costruction projects in southern and cenrtal regions of Penisular Malaysia. In: 2012 IEEE Colloquium on Humanities, Science and Engineering (CHUSER) (2012)
12.
go back to reference Mohd-Nor, M., Grant, M.P.: Building information modelling (BIM) in the malaysian architecture industry. WSEAS Trans. Env. Dev. 10, 264–273 (2014) Mohd-Nor, M., Grant, M.P.: Building information modelling (BIM) in the malaysian architecture industry. WSEAS Trans. Env. Dev. 10, 264–273 (2014)
13.
go back to reference Yamin, R.A., Harmelink, D.J.: Comparison of linear scheduling model (LSM) and critical path method (CPM). J. Constr. Eng. Manage. 127(5), 374–381 (2001)CrossRef Yamin, R.A., Harmelink, D.J.: Comparison of linear scheduling model (LSM) and critical path method (CPM). J. Constr. Eng. Manage. 127(5), 374–381 (2001)CrossRef
14.
go back to reference John, N.: Project Management for Business and Technology. Prentice Hall (2003) John, N.: Project Management for Business and Technology. Prentice Hall (2003)
15.
go back to reference Lester, A.: Project Planning and Control. Butterworth-Heinemann (2003) Lester, A.: Project Planning and Control. Butterworth-Heinemann (2003)
16.
go back to reference Bazjanac, V.: Virtual Building Environments (VBE)-Applying Information Modeling to Buildings (2006) Bazjanac, V.: Virtual Building Environments (VBE)-Applying Information Modeling to Buildings (2006)
17.
go back to reference Ramanathan, C., Potty, N.S., Idrus, A.B.: Analysis of time and cost overrun in Malaysian construction. In: Advanced Materials Research. Trans Tech Publications (2012)CrossRef Ramanathan, C., Potty, N.S., Idrus, A.B.: Analysis of time and cost overrun in Malaysian construction. In: Advanced Materials Research. Trans Tech Publications (2012)CrossRef
18.
go back to reference Sambasivan, M., Soon, Y.W.: Causes and effects of delays in Malaysian construction industry. Int. J. Project Manage. 25(5), 517–526 (2007)CrossRef Sambasivan, M., Soon, Y.W.: Causes and effects of delays in Malaysian construction industry. Int. J. Project Manage. 25(5), 517–526 (2007)CrossRef
19.
go back to reference Ting, S., Khoo, H., Wong, S.: Project Management Development in Malaysia: A Case Study. Department of Civil Engineering, Faculty of Engineering, University Malaysia (2009) Ting, S., Khoo, H., Wong, S.: Project Management Development in Malaysia: A Case Study. Department of Civil Engineering, Faculty of Engineering, University Malaysia (2009)
20.
go back to reference Doloi, H., et al.: Analysing factors affecting delays in Indian construction projects. Int. J. Project Manage. 30(4), 479–489 (2012)CrossRef Doloi, H., et al.: Analysing factors affecting delays in Indian construction projects. Int. J. Project Manage. 30(4), 479–489 (2012)CrossRef
21.
go back to reference Memon, A.H., et al.: BIM in Malaysian construction industry: status, advantages, barriers and strategies to enhance the implementation level. Res. J. Appl. Sci. Eng. Technol. 8(5), 606–614 (2014) Memon, A.H., et al.: BIM in Malaysian construction industry: status, advantages, barriers and strategies to enhance the implementation level. Res. J. Appl. Sci. Eng. Technol. 8(5), 606–614 (2014)
22.
go back to reference Kaming, P.F., et al.: Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr. Manage. Econ. 15(1), 83–94 (1997)CrossRef Kaming, P.F., et al.: Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr. Manage. Econ. 15(1), 83–94 (1997)CrossRef
23.
go back to reference Ofori, G.: Programmes for improving the performance of contracting firms in developing countries: A review of approaches and appropriate options. Constr. Manage. Econ. 9(1), 19–38 (1991)MathSciNetCrossRef Ofori, G.: Programmes for improving the performance of contracting firms in developing countries: A review of approaches and appropriate options. Constr. Manage. Econ. 9(1), 19–38 (1991)MathSciNetCrossRef
24.
go back to reference Ofori, G.: Research on construction industry development at the crossroads. Constr. Manage. Econ. 11(3), 175–185 (1993)CrossRef Ofori, G.: Research on construction industry development at the crossroads. Constr. Manage. Econ. 11(3), 175–185 (1993)CrossRef
25.
go back to reference Chan, D.W., Kumaraswamy, M.M.: A comparative study of causes of time overruns in Hong Kong construction projects. Int. J. Project Manage. 15(1), 55–63 (1997)CrossRef Chan, D.W., Kumaraswamy, M.M.: A comparative study of causes of time overruns in Hong Kong construction projects. Int. J. Project Manage. 15(1), 55–63 (1997)CrossRef
26.
go back to reference Al-Momani, A.H.: Construction delay: a quantitative analysis. Int. J. Project Manage. 18(1), 51–59 (2000)CrossRef Al-Momani, A.H.: Construction delay: a quantitative analysis. Int. J. Project Manage. 18(1), 51–59 (2000)CrossRef
27.
go back to reference Chan, D.W., Kumaraswamy, M.M.: Compressing construction durations: lessons learned from Hong Kong building projects. Int. J. Project Manage. 20(1), 23–35 (2002)CrossRef Chan, D.W., Kumaraswamy, M.M.: Compressing construction durations: lessons learned from Hong Kong building projects. Int. J. Project Manage. 20(1), 23–35 (2002)CrossRef
28.
go back to reference Kaliba, C., Muya, M., Mumba, K.: Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Project Manage. 27(5), 522–531 (2009)CrossRef Kaliba, C., Muya, M., Mumba, K.: Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Project Manage. 27(5), 522–531 (2009)CrossRef
29.
go back to reference Toor, S.U.R., Ogunlana, S.O.: Problems causing delays in major construction projects in Thailand. Constr. Manage. Econ. 26(4), 395–408 (2008)CrossRef Toor, S.U.R., Ogunlana, S.O.: Problems causing delays in major construction projects in Thailand. Constr. Manage. Econ. 26(4), 395–408 (2008)CrossRef
30.
go back to reference Olawale, Y.A., Sun, M.: Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Constr. Manage. Econ 28(5), 509–526 (2010)CrossRef Olawale, Y.A., Sun, M.: Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Constr. Manage. Econ 28(5), 509–526 (2010)CrossRef
31.
go back to reference Al-Tmeemy, S.M.H., Abdul-Rahman, H., Harun, Z.: Contractors’ perception of the use of costs of quality system in Malaysian building construction projects. Int. J. Project Manage. 30(7), 827–838 (2012)CrossRef Al-Tmeemy, S.M.H., Abdul-Rahman, H., Harun, Z.: Contractors’ perception of the use of costs of quality system in Malaysian building construction projects. Int. J. Project Manage. 30(7), 827–838 (2012)CrossRef
32.
go back to reference Cochran, W.G.: Sampling Techniques. Wiley (2007) Cochran, W.G.: Sampling Techniques. Wiley (2007)
33.
go back to reference Neill, J.: Writing up a Factor Analysis, 7 p. Retrieved 7 Sept 2008 Neill, J.: Writing up a Factor Analysis, 7 p. Retrieved 7 Sept 2008
34.
go back to reference Abd El-Razek, M., Bassioni, H., Mobarak, A.: Causes of delay in building construction projects in Egypt. J. Constr. Eng. Manage. 134(11), 831–841 (2008)CrossRef Abd El-Razek, M., Bassioni, H., Mobarak, A.: Causes of delay in building construction projects in Egypt. J. Constr. Eng. Manage. 134(11), 831–841 (2008)CrossRef
Metadata
Title
Causes of Delay and Cost Overrun in Malaysian Construction Industry
Authors
Muhammad Muhammad Tahir
Nuzul Azam Haron
Aidi Hizami Alias
Ikechukwu A. Diugwu
Copyright Year
2019
Publisher
Springer Singapore
DOI
https://doi.org/10.1007/978-981-10-8016-6_5