Published in: Evolutionary Intelligence 4/2022

11-03-2019 | Special Issue

Fuzzy assessment of the risk factors causing cost overrun in construction industry

Authors: Savita Sharma, Pradeep K. Goyal

Published in: Evolutionary Intelligence | Issue 4/2022

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Cost is considered as one of the most important parameters for the success of any construction project. Therefore the risk factors causing cost overrun in the construction industry should be assessed. In this study, 55 important risk factors causing cost overrun in Indian construction projects are identified through intensive literature review and expert opinion. A new fuzzy based model has been proposed to estimate the risk magnitude of these factors, as the theory has the potential to deal with the vagueness, uncertainty and subjective nature of any problems and It is capable of handling the almost same analogous which is found in the complex construction projects. In order to assess the risk factors causing cost overrun, probability index and severity index are considered. A new cost overrun factor index, namely fuzzy index for cost overrun is calculated which indicates the risk magnitude of a certain factor. The applicability of the model has been shown by an example. The risk magnitude for the factor “fluctuation in price material” is determined by collecting the data from the experts of Indian construction industry. On the basis of these risk magnitudes, the importance level the factors are assessed. Top ten factors for causing cost overrun in the Indian construction industry are recognised as fluctuation in price material, lowest bid procurement policy, inflation inappropriate govt. Policy, mistakes and discrepancies in the contract document, inaccurate time and cost estimate, additional work, frequent design change, unrealistic contract duration and financial difficulty faced by contractors.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literature
1.
go back to reference Al-Hazim N, Salem ZA, Ahmad H (2017) Delay and cost overrun in infrastructure projects in Jordan. In: 7th international conference on engineering, project, and production management, Procedia Engineering, vol 182, pp 18–24 Al-Hazim N, Salem ZA, Ahmad H (2017) Delay and cost overrun in infrastructure projects in Jordan. In: 7th international conference on engineering, project, and production management, Procedia Engineering, vol 182, pp 18–24
2.
go back to reference Ashworth A (2008) Pre-contract studies: development economics, tendering and estimating, 3rd edn. Blackwell Publishing Limited, Oxford Ashworth A (2008) Pre-contract studies: development economics, tendering and estimating, 3rd edn. Blackwell Publishing Limited, Oxford
3.
go back to reference Avots I (1983) Cost-relevance analysis for overrun control. Int J Project Manag 1:142–148CrossRef Avots I (1983) Cost-relevance analysis for overrun control. Int J Project Manag 1:142–148CrossRef
4.
go back to reference Azhar N, Farooqui RU, Ahmed SM (2008) Cost overrun factors in construction industry of Pakistan. In: Paper presented at the first international conference on construction in developing countries (ICCIDC-I). Advancing and integrating construction education, research & practice Azhar N, Farooqui RU, Ahmed SM (2008) Cost overrun factors in construction industry of Pakistan. In: Paper presented at the first international conference on construction in developing countries (ICCIDC-I). Advancing and integrating construction education, research & practice
5.
go back to reference Baloi D, Price ADF (2003) Modeling global risk factors affecting construction cost performance. Int J Proj Manag 21(4):261–269CrossRef Baloi D, Price ADF (2003) Modeling global risk factors affecting construction cost performance. Int J Proj Manag 21(4):261–269CrossRef
6.
go back to reference Bojadziev G, Bojadziev M (1997) Fuzzy logic for business, finance, and management. World Scientific, SingaporeCrossRefMATH Bojadziev G, Bojadziev M (1997) Fuzzy logic for business, finance, and management. World Scientific, SingaporeCrossRefMATH
7.
go back to reference Chen P, Wang J (2009) Application of fuzzy AHP method to risk assessment of international construction projects. In 2009 international conference on electronic commerce and business intelligence, pp 459–462 Chen P, Wang J (2009) Application of fuzzy AHP method to risk assessment of international construction projects. In 2009 international conference on electronic commerce and business intelligence, pp 459–462
8.
go back to reference Cho HN, Choi HH, Kim YB (2002) A risk assessment methodology for incorporating uncertainties using fuzzy concepts. Reliab Eng Syst Saf 78(2):173–183CrossRef Cho HN, Choi HH, Kim YB (2002) A risk assessment methodology for incorporating uncertainties using fuzzy concepts. Reliab Eng Syst Saf 78(2):173–183CrossRef
9.
go back to reference Choi HH, Cho HN, Seo JW (2004) Risk assessment methodology for underground construction projects. J Constr Eng Manag 130:258CrossRef Choi HH, Cho HN, Seo JW (2004) Risk assessment methodology for underground construction projects. J Constr Eng Manag 130:258CrossRef
10.
go back to reference Das TK (2003) Development of Highways and Airports in India. In: Proceedings of the 6th national conference on construction, CDROM, Technical Session 1, Paper No.7. 10–11 November 2003, New Delhi Das TK (2003) Development of Highways and Airports in India. In: Proceedings of the 6th national conference on construction, CDROM, Technical Session 1, Paper No.7. 10–11 November 2003, New Delhi
11.
go back to reference Dikmen I, Birgonul MT (2006) An analytic hierarchy process based model for risk and opportunity assessment of international construction projects. Can J Civ Eng 33(1):58–68CrossRef Dikmen I, Birgonul MT (2006) An analytic hierarchy process based model for risk and opportunity assessment of international construction projects. Can J Civ Eng 33(1):58–68CrossRef
12.
go back to reference Dikmen I, Birgonul MT, Han S (2007) Using fuzzy risk assessment to rate cost overrun risk in international construction projects. Int J Project Manag 25:494–505CrossRef Dikmen I, Birgonul MT, Han S (2007) Using fuzzy risk assessment to rate cost overrun risk in international construction projects. Int J Project Manag 25:494–505CrossRef
13.
go back to reference Doloi H, Sawhney A, Iyer KC, Rentala S (2012) Analysing factors affecting delays in Indian construction projects. Int J Project Manag 30(4):479–489CrossRef Doloi H, Sawhney A, Iyer KC, Rentala S (2012) Analysing factors affecting delays in Indian construction projects. Int J Project Manag 30(4):479–489CrossRef
14.
go back to reference Enshassi A, Al-Najjar J, Kumaraswamy M (2009) Delays and cost overruns in the construction projects in the Gaza Strip. J Financ Manag Prop Constr 14(2):126–151CrossRef Enshassi A, Al-Najjar J, Kumaraswamy M (2009) Delays and cost overruns in the construction projects in the Gaza Strip. J Financ Manag Prop Constr 14(2):126–151CrossRef
15.
go back to reference Flyvbjerg B, Holm MKS, Buhl SL (2002) Underestimating costs in public works projects: error or lie? J Am Plan Assoc 68(3):279–295CrossRef Flyvbjerg B, Holm MKS, Buhl SL (2002) Underestimating costs in public works projects: error or lie? J Am Plan Assoc 68(3):279–295CrossRef
16.
go back to reference Frimpong Y, Oluwoye J, Crawford L (2003) Causes of delays and cost overruns in construction of groundwater projects in developing countries; Ghana as a case study. Int J Project Manag 21:321–326CrossRef Frimpong Y, Oluwoye J, Crawford L (2003) Causes of delays and cost overruns in construction of groundwater projects in developing countries; Ghana as a case study. Int J Project Manag 21:321–326CrossRef
17.
go back to reference Fuzzy Logic Toolbox™ (2015) 2 user’s guide, MATLAB. The Math Works, Inc., Natick Fuzzy Logic Toolbox™ (2015) 2 user’s guide, MATLAB. The Math Works, Inc., Natick
20.
go back to reference Iyer KC, Jha KN (2005) Factors affecting cost performance: evidence from Indian construction projects. Int J Project Manag 23:283–295CrossRef Iyer KC, Jha KN (2005) Factors affecting cost performance: evidence from Indian construction projects. Int J Project Manag 23:283–295CrossRef
21.
go back to reference Jackson S (2002) Project cost overrun and risk management in Greenwood. In: Proceedings of association of researchers in construction management, 18th annual ARCOM conference, Newcastle, Northumber University, UK, 2–4 September Jackson S (2002) Project cost overrun and risk management in Greenwood. In: Proceedings of association of researchers in construction management, 18th annual ARCOM conference, Newcastle, Northumber University, UK, 2–4 September
22.
go back to reference Kangari R, Riggs LS (1989) Construction risk assessment by linguistics. IEEE Trans Eng Manag 36(2):126–131CrossRef Kangari R, Riggs LS (1989) Construction risk assessment by linguistics. IEEE Trans Eng Manag 36(2):126–131CrossRef
23.
go back to reference Karimiazari AR et al (2011) Risk assessment model selection in construction industry. Expert Syst Appl 38:9105–9111CrossRef Karimiazari AR et al (2011) Risk assessment model selection in construction industry. Expert Syst Appl 38:9105–9111CrossRef
24.
go back to reference Khalek HAE, Aziz RF, Kamel HM (2016) Risk and uncertainty assessment model in construction projects using fuzzy logic. Am J Civ Eng 4(1):24–39CrossRef Khalek HAE, Aziz RF, Kamel HM (2016) Risk and uncertainty assessment model in construction projects using fuzzy logic. Am J Civ Eng 4(1):24–39CrossRef
25.
go back to reference Knight K, Fayek AR (2002) Use of fuzzy logic for predicting design cost overruns on building projects. J Constr Eng Manag 128(6):503–512CrossRef Knight K, Fayek AR (2002) Use of fuzzy logic for predicting design cost overruns on building projects. J Constr Eng Manag 128(6):503–512CrossRef
26.
go back to reference Koushki PA, Al-Rashid K, Kartam N (2005) Delays and cost increases in the construction of private residential projects in Kuwait. Constr Manag Econ 23(3):285–294CrossRef Koushki PA, Al-Rashid K, Kartam N (2005) Delays and cost increases in the construction of private residential projects in Kuwait. Constr Manag Econ 23(3):285–294CrossRef
27.
go back to reference Kuchta D (2001) Use of fuzzy numbers in project risk (criticality) assessment. Project Manag 19(5):305–310CrossRef Kuchta D (2001) Use of fuzzy numbers in project risk (criticality) assessment. Project Manag 19(5):305–310CrossRef
28.
go back to reference Lee HM, Lin L (2008) A new fuzzy risk assessment approach. Int J Project Manag 1(4):6–7 Lee HM, Lin L (2008) A new fuzzy risk assessment approach. Int J Project Manag 1(4):6–7
29.
go back to reference Mamdani EH, Assilian S (1975) An experiment in linguistic synthesis with a fuzzy logic controller. Int J Man Mach Stud 7:1–13CrossRefMATH Mamdani EH, Assilian S (1975) An experiment in linguistic synthesis with a fuzzy logic controller. Int J Man Mach Stud 7:1–13CrossRefMATH
30.
go back to reference Mansfield NR, Ugwu OO, Doran T (1994) Causes of delay and cost overruns in Nigerian construction projects. Int J Project Manag 12(4):254–260CrossRef Mansfield NR, Ugwu OO, Doran T (1994) Causes of delay and cost overruns in Nigerian construction projects. Int J Project Manag 12(4):254–260CrossRef
32.
go back to reference Memon AH, Rahman IA, Abdullah MR, Azis AAA (2010) Factors affecting construction cost in MARA large construction projects: perspective of project management consultant. Int J Sustain Constr Eng Technol 1:41–54 Memon AH, Rahman IA, Abdullah MR, Azis AAA (2010) Factors affecting construction cost in MARA large construction projects: perspective of project management consultant. Int J Sustain Constr Eng Technol 1:41–54
33.
go back to reference Nieto-Morote A, Ruz-Vila F (2011) A fuzzy approach to construction project risk assessment. Int J Project Manag 29:220–231CrossRefMATH Nieto-Morote A, Ruz-Vila F (2011) A fuzzy approach to construction project risk assessment. Int J Project Manag 29:220–231CrossRefMATH
34.
go back to reference Okpala DC, Aniekwu AN (1988) Causes of high costs of construction in Nigeria. J Constr Eng Manag 114(2):233–234CrossRef Okpala DC, Aniekwu AN (1988) Causes of high costs of construction in Nigeria. J Constr Eng Manag 114(2):233–234CrossRef
35.
go back to reference Paek JH, Lee YW, Ock JH (1993) Pricing construction risks: fuzzy set theory. J Constr Eng Manag 119(4):743–756CrossRef Paek JH, Lee YW, Ock JH (1993) Pricing construction risks: fuzzy set theory. J Constr Eng Manag 119(4):743–756CrossRef
36.
go back to reference PMI (2004) A guide to the project management body of knowledge: PMBOKGuide, 3rd edn. Project Management Institute Inc., Newtown Square PMI (2004) A guide to the project management body of knowledge: PMBOKGuide, 3rd edn. Project Management Institute Inc., Newtown Square
39.
go back to reference Shang H, Anumba CJ, Bouchlaghem DM, Miles JC, Cen M, Taylor M (2005) An intelligent risk assessment system for distributed construction teams. Eng Constr Archit Manag 12(4):391–409CrossRef Shang H, Anumba CJ, Bouchlaghem DM, Miles JC, Cen M, Taylor M (2005) An intelligent risk assessment system for distributed construction teams. Eng Constr Archit Manag 12(4):391–409CrossRef
40.
go back to reference Shaktawat A, Vadhera S (2016). Fuzzy logic based determination of cost overrun of hydro power plant. In: International conference on electrical power and Systems E (ICEPES), Dec. 14–16, Bhopal, India Shaktawat A, Vadhera S (2016). Fuzzy logic based determination of cost overrun of hydro power plant. In: International conference on electrical power and Systems E (ICEPES), Dec. 14–16, Bhopal, India
41.
go back to reference Taroun A, Yang JB, Lowe D (2011) Construction risk modelling and assessment: insights from a literature review. Built Hum Environ Rev 4(1):87–97 Taroun A, Yang JB, Lowe D (2011) Construction risk modelling and assessment: insights from a literature review. Built Hum Environ Rev 4(1):87–97
42.
go back to reference Tah JHM, Carr V (2000) A proposal for construction project risk assessment using fuzzy logic. Constr Manag Econ 18:491–500CrossRef Tah JHM, Carr V (2000) A proposal for construction project risk assessment using fuzzy logic. Constr Manag Econ 18:491–500CrossRef
43.
go back to reference Wakjira T (2011) Risk factors leading to cost overrun in Ethiopian Federal Road Construction projects and its consequences. M. Sc. Thesis, Construction Technology and Management Addis Abab University Ethiopia Wakjira T (2011) Risk factors leading to cost overrun in Ethiopian Federal Road Construction projects and its consequences. M. Sc. Thesis, Construction Technology and Management Addis Abab University Ethiopia
44.
go back to reference Wang RC, Liang TF (2004) Project management decisions with multiple fuzzy goals. Constr Manag Econ 22(10):1047–1056CrossRef Wang RC, Liang TF (2004) Project management decisions with multiple fuzzy goals. Constr Manag Econ 22(10):1047–1056CrossRef
45.
go back to reference Wang YM, Elhag TM (2007) A fuzzy group decision making approach for bridge risks assessment. Comput Ind Eng 53(1):137–148CrossRef Wang YM, Elhag TM (2007) A fuzzy group decision making approach for bridge risks assessment. Comput Ind Eng 53(1):137–148CrossRef
47.
go back to reference Wirba EN, Tah JHM, Howes R (1996) Risk interdependencies and natural language computations. J Eng Constr Architect Manag 3(4):251–269CrossRef Wirba EN, Tah JHM, Howes R (1996) Risk interdependencies and natural language computations. J Eng Constr Architect Manag 3(4):251–269CrossRef
51.
go back to reference Zheng DXM, Ng T (2005) Stochastic time-cost optimization model incorporating fuzzy sets theory and non-replacement. J Constr Eng Manag 131(2):176–186CrossRef Zheng DXM, Ng T (2005) Stochastic time-cost optimization model incorporating fuzzy sets theory and non-replacement. J Constr Eng Manag 131(2):176–186CrossRef
Metadata
Title
Fuzzy assessment of the risk factors causing cost overrun in construction industry
Authors
Savita Sharma
Pradeep K. Goyal
Publication date
11-03-2019
Publisher
Springer Berlin Heidelberg
Published in
Evolutionary Intelligence / Issue 4/2022
Print ISSN: 1864-5909
Electronic ISSN: 1864-5917
DOI
https://doi.org/10.1007/s12065-019-00214-9