1 Introduction and Literature Review
2 Cost Estimation Relationship Building Process
2.1 Data Collection
Cost driver [U.O.M.] | Reference value | Max value | Min value |
---|---|---|---|
Batch size [ad] | 1000 | 2000 | 10 |
Part volume [m3] | 0.00026300 | 0.00063120 | 0.00001325 |
Part thickness [mm] | 25 | 50 | 2 |
Raw material price [€/kg] | 3.4 | 5.4 | 0.8 |
Raw material density [kg/m3] | 7850 | 15000 | 2000 |
Labour cost [€/hour] | 30 | 70 | 3 |
2.2 CER Development
2.3 Validation
Component | Material | Reference cost | Calculated cost | Absolute deviation |
---|---|---|---|---|
1 | Aluminium 1100 | € 3.77 | € 4.40 | 17% |
2 | G 1800 grey cast iron | € 2.53 | € 2.44 | 4% |
3 | 42CrMo4 | € 5.85 | € 6.48 | 11% |
4 | 39NiCrMo4 | € 8.29 | € 9.44 | 14% |
5 | AISI 316 | € 20.03 | € 23.77 | 19% |
Average absolute deviation | 11% |