1 Introduction
2 Design Approach
3 Case Study
Characteristics | Symbol | Unit | Round bilge | Hard chine | ||
---|---|---|---|---|---|---|
Original | Rebuilt | Original | Rebuilt | |||
Displacement | ∇ | m3 | 0.238 | 0.233 | 0.262 | 0.263 |
Length overall | LOA | m | 4.60 | 4.60 | 4.60 | 4.60 |
Length water line | LWL | m | 4.40 | 4.42 | 4.49 | 4.49 |
Max beam water line | BWL | m | 1.05 | 1.05 | 0.95 | 0.95 |
Wetted surface | SW | m2 | 3.38 | 3.40 | 3.46 | 3.50 |
Water plane area | AW | m2 | 3.14 | 3.17 | 3.10 | 3.14 |
Max transversal area | AX | m2 | 0.107 | 0.103 | 0.094 | 0.093 |
Long. centre of buoyancy | LCB | m | 2.48 | 2.52 | 2.25 | 2.26 |
Long. centre of flotation | LCF | m | 2.68 | 2.67 | 2.60 | 2.60 |
Max draught | Tc | m | 0.14 | 0.14 | 0.17 | 0.17 |