Production Rate Estimation Using System Dynamics (Case Study: Clamshell Excavation at Top Down Construction)

Authors : Ibrahim Hamdan, Mohamed S. Eid, Ahmed Elhakeem

Published in: Advancements in Geotechnical Engineering

Publisher: Springer International Publishing

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Construction projects usually face delays and do not finish on time due to many factors, including inaccurate estimation of production rates. Production rate for an activity depends on many factors that are interdependent and stochastic in nature. However, most of the available models for production rate estimation assume deterministic factors and seldomly account for the interdependencies between the various factors. This research aims to provide accurate estimation of production rates through accounting for stochastic and interdependent factors. To this effect, this paper presents the modeling and testing of a System Dynamics (SD) model for excavation activities using clamshell in top-down construction projects. SD allows for representing the interdependencies between the various elements and sub-processes of the construction process. In addition, the SD simulation process allows for depicting the stochastic nature of the various parameters that other estimation techniques fail to achieve. To achieve the desired outcome, the authors: (1) carried out a thorough literature review to study the factors affecting the excavation process; (2) collected data through questionnaires and site reports to quantify the impact of each factor on production rate and its occurrence likelihood; (3) modeled the excavation process through SD toolkit on AnyLogic simulation platform; and (4) tested and validated the model through the case study. The model was able to provide results within a mean square error of 4.14% throughout the testing phase. Although the excavation process of top-down construction activities has a lot of complexity, the presented SD model has proved able to simulate the process and provide desired realistic production rates. The model can be improved to account for more factors, in order to capture the full nature of the excavation activity, nevertheless, the modeling approach can be replicated to estimate the production rates for other complex construction activities.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literature
go back to reference AbouRizk, S.: Role of simulation in construction engineering and management. J. Constr. Eng. Manage. 136(10), 1140–1153 (2010)CrossRef AbouRizk, S.: Role of simulation in construction engineering and management. J. Constr. Eng. Manage. 136(10), 1140–1153 (2010)CrossRef
go back to reference AbouRizk, S., Knowles, P., Hermann, U.R.: Estimating labor production rates for industrial construction activities. J. Constr. Eng. Manage. 127(6), 502–511 (2001)CrossRef AbouRizk, S., Knowles, P., Hermann, U.R.: Estimating labor production rates for industrial construction activities. J. Constr. Eng. Manage. 127(6), 502–511 (2001)CrossRef
go back to reference AbouRizk, S.M., Halpin, D.W.: Statistical properties of construction duration data. J. Constr. Eng. Manage. 118(3), 525–544 (1992)CrossRef AbouRizk, S.M., Halpin, D.W.: Statistical properties of construction duration data. J. Constr. Eng. Manage. 118(3), 525–544 (1992)CrossRef
go back to reference Bokor, O., Florez, L., Osborne, A., Gledson, B.J.: Overview of construction simulation approaches to model construction processes. Organ. Technol. Manage. Constr. Int. J. 11(1), 1853–1861 (2019) Bokor, O., Florez, L., Osborne, A., Gledson, B.J.: Overview of construction simulation approaches to model construction processes. Organ. Technol. Manage. Constr. Int. J. 11(1), 1853–1861 (2019)
go back to reference Borshchev, A.: The Big Book of Simulation Modeling: Multimethod Modeling with AnyLogic 6. AnyLogic North America, Chicago (2013) Borshchev, A.: The Big Book of Simulation Modeling: Multimethod Modeling with AnyLogic 6. AnyLogic North America, Chicago (2013)
go back to reference Borshchev, A., and Filippov, A.: From system dynamics and discrete event to practical agent based modeling: reasons, techniques, tools. In: Proceedings of the 22nd International Conference of the System Dynamics Society, vol. 23 (2004) Borshchev, A., and Filippov, A.: From system dynamics and discrete event to practical agent based modeling: reasons, techniques, tools. In: Proceedings of the 22nd International Conference of the System Dynamics Society, vol. 23 (2004)
go back to reference Chong, W.K., O’Connor, J.T., Chou, J.-S., Lee, S.-H.: Predicting the production rates of foundation construction using factor and regression analysis. In: Construction Research Congress 2005, American Society of Civil Engineers, San Diego, California, pp.1–10 (2005) Chong, W.K., O’Connor, J.T., Chou, J.-S., Lee, S.-H.: Predicting the production rates of foundation construction using factor and regression analysis. In: Construction Research Congress 2005, American Society of Civil Engineers, San Diego, California, pp.1–10 (2005)
go back to reference Christian, J., Hachey, D.: Effects of delay times on production rates in construction. J. Constr. Eng. Manage. 121(1), 20–26 (1995)CrossRef Christian, J., Hachey, D.: Effects of delay times on production rates in construction. J. Constr. Eng. Manage. 121(1), 20–26 (1995)CrossRef
go back to reference Craig, W.K.: System Dynamics Methods A Quick Introduction (1998) Craig, W.K.: System Dynamics Methods A Quick Introduction (1998)
go back to reference El-Maghraby, E., Elshakour, H.A.: Predicting the production rate of pouring ready mixed concrete using regression analysis. J. Civil Eng. Sci. 3, 16 (2014) El-Maghraby, E., Elshakour, H.A.: Predicting the production rate of pouring ready mixed concrete using regression analysis. J. Civil Eng. Sci. 3, 16 (2014)
go back to reference Ergan, S.K., Akinci, B.: Automated approach for developing integrated model-based project histories to support estimation of activity production rates. J. Comput. Civil Eng. 26(3), 309–318 (2012)CrossRef Ergan, S.K., Akinci, B.: Automated approach for developing integrated model-based project histories to support estimation of activity production rates. J. Comput. Civil Eng. 26(3), 309–318 (2012)CrossRef
go back to reference Grigoryev, I.: AnyLogic 7 in Three Days: A Quick Course in Simulation Modeling. Verlag nicht ermittelbar, Erscheinungsort nicht ermittelbar (2016) Grigoryev, I.: AnyLogic 7 in Three Days: A Quick Course in Simulation Modeling. Verlag nicht ermittelbar, Erscheinungsort nicht ermittelbar (2016)
go back to reference Heravi, G., Eslamdoost, E.: Applying artificial neural networks for measuring and predicting construction-labor productivity. J. Constr. Eng. Manage. 141(10), 04015032 (2015)CrossRef Heravi, G., Eslamdoost, E.: Applying artificial neural networks for measuring and predicting construction-labor productivity. J. Constr. Eng. Manage. 141(10), 04015032 (2015)CrossRef
go back to reference Sterman, J.D.: System Dynamics: Systems Thinking and Modeling for a Complex World. Massachusetts Institute of Technology Engineering Systems Division Working Paper Series, Cambridge, p. 32 (2002) Sterman, J.D.: System Dynamics: Systems Thinking and Modeling for a Complex World. Massachusetts Institute of Technology Engineering Systems Division Working Paper Series, Cambridge, p. 32 (2002)
go back to reference Ulubeyli, S., Kazaz, A., Er, B.: Planning Engineers’ Estimates on Labor Productivity: Theory and Practice. Procedia Soc. Behav. Sci. 119, 12–19 (2014)CrossRef Ulubeyli, S., Kazaz, A., Er, B.: Planning Engineers’ Estimates on Labor Productivity: Theory and Practice. Procedia Soc. Behav. Sci. 119, 12–19 (2014)CrossRef
go back to reference Watkins, M., Mukherjee, A., Onder, N., Mattila, K.: Using agent-based modeling to study construction labor productivity as an emergent property of individual and crew interactions. J. Constr. Eng. Manage. 135(7), 657–667 (2009)CrossRef Watkins, M., Mukherjee, A., Onder, N., Mattila, K.: Using agent-based modeling to study construction labor productivity as an emergent property of individual and crew interactions. J. Constr. Eng. Manage. 135(7), 657–667 (2009)CrossRef
go back to reference Woldesenbet, A., Jeong, D.H., Oberlender, D.: Daily work reports-based production rate estimation for highway projects. J. Constr. Eng. Manage. 138(4), 481–490 (2012)CrossRef Woldesenbet, A., Jeong, D.H., Oberlender, D.: Daily work reports-based production rate estimation for highway projects. J. Constr. Eng. Manage. 138(4), 481–490 (2012)CrossRef
Metadata
Title
Production Rate Estimation Using System Dynamics (Case Study: Clamshell Excavation at Top Down Construction)
Authors
Ibrahim Hamdan
Mohamed S. Eid
Ahmed Elhakeem
Copyright Year
2021
DOI
https://doi.org/10.1007/978-3-030-62908-3_2