2019 | OriginalPaper | Chapter

51. FLO/FLO Heavy Lift Critical Stability Phases

Authors : Paul Handler, Vincent Jarecki, Hendrik Bruhns

Published in: Contemporary Ideas on Ship Stability

Publisher: Springer International Publishing

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

The US Navy has used FLO/FLO heavy lift transport as an alternative to towing for the transport of damaged vessels as well as transport of smaller vessels not suited for ocean transit. There are critical stability considerations that have to be assessed prior to conducting a heavy lift operation, specifically “Draft at Instability” and “Minimum Stability”. During de-ballasting of the heavy lift ship with the lifted vessel on the docking blocks, the reaction of the docking blocks on the lifted vessel is effectively the same as removing weight from the lifted vessel’s keel (similar to what occurs when a floating dry-dock is de-ballasted). This raises the lifted vessel’s centre of gravity thus reducing the lifted vessel’s metacentric height (GM) until the lifted vessel’s GM is zero. During a critical part of the FLO/FLO heavy lift operation the cargo deck of the FLO/FLO heavy lift ship will be completely submerged. During this phase, only the water-plane of the hull structure which extends above the cargo deck will provide stability for the heavy lift ship. The heavy lift ship will pass through a phase of “Minimum Stability”, which should not occur at the same time that the lifted vessel assumes its “Draft at Instability”. The lifted vessel and the heavy lift ship may roll out of phase, causing landing problems, or causing the lifted vessel and/or the FLO/FLO heavy lift ship to become unstable, assume a large list or even capsize. Computer naval architectural software programs HECSALV and POSSE are effective tools in modelling critical stability phases for FLO/FLO heavy lift operations. This paper discusses the critical stability phases of a FLO/FLO heavy lift operation, and the methods and practices to plan for and mitigate the effects of reduced stability at these phases.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Metadata
Title
FLO/FLO Heavy Lift Critical Stability Phases
Authors
Paul Handler
Vincent Jarecki
Hendrik Bruhns
Copyright Year
2019
DOI
https://doi.org/10.1007/978-3-030-00516-0_51