Foundation consolidation grouting applications in Deriner Dam and Hydroelectric Power Plant (Artvin, Turkey)

Author: Mehmet Özçelik

Published in: Bulletin of Engineering Geology and the Environment | Issue 2/2014

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Grouting is one of the most popular methods used to control water leakage in dam constructions. The geological and engineering geological properties of the rock/soil to be grouted are important parameters influencing the design of the grouting. In this study, the geotechnical properties of Deriner Dam’s foundation rock and the grouting procedure used for it were investigated to ascertain its suitability for grouting. Detailed investigations were conducted to unravel the reasons for and types of foundation grouting applications used on the main rock in Deriner Dam. The materials used in the grouting and the grouting pressures employed were investigated onsite, and the results obtained are presented in this paper.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Literature
go back to reference Alkaya D, Yesil B (2011) Grouting applications of grout curtains in Cindere dam and hydroelectric power plant. Sci Res Essays 6(19):4039–4047 Alkaya D, Yesil B (2011) Grouting applications of grout curtains in Cindere dam and hydroelectric power plant. Sci Res Essays 6(19):4039–4047
go back to reference Basarir H, Ozsan A, Karakus M (2005) Analysis of support requirements for a shallow diversion tunnel at Guledar dam site, Turkey. Eng Geol 81:131–145CrossRef Basarir H, Ozsan A, Karakus M (2005) Analysis of support requirements for a shallow diversion tunnel at Guledar dam site, Turkey. Eng Geol 81:131–145CrossRef
go back to reference Cekerevac C, Wohnlich A, Bellwald PH (2008) Deriner hydropower scheme—geotechnical Issues and the particular case of the spillway tunnels design and construction. Stucky Ltd., Renens Cekerevac C, Wohnlich A, Bellwald PH (2008) Deriner hydropower scheme—geotechnical Issues and the particular case of the spillway tunnels design and construction. Stucky Ltd., Renens
go back to reference Deriner Dam and HEPP Engineers Consortium (2010) Deriner Dam and HEPP: dam foundation and curtain grouting report no. 1. Deriner Dam and HEPP Engineers Consortium, Deriner Dam and HEPP Engineers Consortium (2010) Deriner Dam and HEPP: dam foundation and curtain grouting report no. 1. Deriner Dam and HEPP Engineers Consortium,
go back to reference DOLSAR Engineering Ltd., Electrowatt Engineering Services Ltd. (1991) Deriner Dam and Hydroelectric Power Plant (design report), vol. 1–2–3. DOLSAR Engineering Ltd./Electrowatt Engineering Services Ltd., Ankara/Riyadh DOLSAR Engineering Ltd., Electrowatt Engineering Services Ltd. (1991) Deriner Dam and Hydroelectric Power Plant (design report), vol. 1–2–3. DOLSAR Engineering Ltd./Electrowatt Engineering Services Ltd., Ankara/Riyadh
go back to reference DSI (1993) Boring and grout technical specifications. General Directorate of State Hydraulic Works (DSI), Ankara DSI (1993) Boring and grout technical specifications. General Directorate of State Hydraulic Works (DSI), Ankara
go back to reference DSI (2006) Letter no. B.15.1.DSI.1.26.01.00-515-112-1553, dated 9 Feb 2006. General Directorate of State Hydraulic Works (DSI), Ankara DSI (2006) Letter no. B.15.1.DSI.1.26.01.00-515-112-1553, dated 9 Feb 2006. General Directorate of State Hydraulic Works (DSI), Ankara
go back to reference DSI (2008) Letter no. B.18.1.DSI.1.26.06.01-604-10064, dated 19 Feb 2008. General Directorate of State Hydraulic Works (DSI), Ankara DSI (2008) Letter no. B.18.1.DSI.1.26.06.01-604-10064, dated 19 Feb 2008. General Directorate of State Hydraulic Works (DSI), Ankara
go back to reference DSI (2009) Letter no. B.18.1.DSI.1.26.06.01-114.02.01-36321, dated 30 April 2009. General Directorate of State Hydraulic Works (DSI), Ankara DSI (2009) Letter no. B.18.1.DSI.1.26.06.01-114.02.01-36321, dated 30 April 2009. General Directorate of State Hydraulic Works (DSI), Ankara
go back to reference EIEI (1991) Aşağı Coruh havzası Deriner barajı yeri mühendislik jeolojisi raporu. EIEI, (in Turkish) EIEI (1991) Aşağı Coruh havzası Deriner barajı yeri mühendislik jeolojisi raporu. EIEI, (in Turkish)
go back to reference Electrowatt Engineering Services Ltd. (1989) Deriner dam and hydroelectric power plant, Zurih Rapor no. 89-28. Electrowatt Engineering Services Ltd., Riyadh Electrowatt Engineering Services Ltd. (1989) Deriner dam and hydroelectric power plant, Zurih Rapor no. 89-28. Electrowatt Engineering Services Ltd., Riyadh
go back to reference Erg Engineering Ltd. (2008) Letter no. DER:17.20/7033-19254: Method statement for drilling and grouting works, rev. 01. Erg Engineering Ltd., Erg Engineering Ltd. (2008) Letter no. DER:17.20/7033-19254: Method statement for drilling and grouting works, rev. 01. Erg Engineering Ltd.,
go back to reference Erg Engineering Ltd. (2009) Letter no. DER:17.20/8227-22441: Method statement for contact and consolidation grouting from galleries, 180.50 and 190.50. Erg Engineering Ltd., Erg Engineering Ltd. (2009) Letter no. DER:17.20/8227-22441: Method statement for contact and consolidation grouting from galleries, 180.50 and 190.50. Erg Engineering Ltd.,
go back to reference Gattinger TE (1955) Bericht über geologische aufnahmearbeiten im gebiete zwischen Coruh und Erzurum, Nordost Turkei. Rep. no. 2379. MTA., Ankara Gattinger TE (1955) Bericht über geologische aufnahmearbeiten im gebiete zwischen Coruh und Erzurum, Nordost Turkei. Rep. no. 2379. MTA., Ankara
go back to reference Gattinger TE (1956) Bericht über geologische aufnahmeerganzungs und revisionsarbeiten in den ostpontiden im bereich von vilayet Trabzon, Rize, Gumushane, Erzurum, Artvin und Kars. Rep. no. 2380. MTA, Ankara Gattinger TE (1956) Bericht über geologische aufnahmeerganzungs und revisionsarbeiten in den ostpontiden im bereich von vilayet Trabzon, Rize, Gumushane, Erzurum, Artvin und Kars. Rep. no. 2380. MTA, Ankara
go back to reference Ghobadi MH, Khanlari GR, Djalali H (2005) Seepage problems in the right abutment of the Shahid Abbaspour Dam, southern Iran. Eng Geol 82:119–126CrossRef Ghobadi MH, Khanlari GR, Djalali H (2005) Seepage problems in the right abutment of the Shahid Abbaspour Dam, southern Iran. Eng Geol 82:119–126CrossRef
go back to reference Kocbay A, Kilic R (2006) Engineering geological assessment of the Obruk dam site (Corum, Turkey). Eng Geol 87:141–148CrossRef Kocbay A, Kilic R (2006) Engineering geological assessment of the Obruk dam site (Corum, Turkey). Eng Geol 87:141–148CrossRef
go back to reference Muller O (2009) Open air excavations at Deriner dam. Int Water Power Dam Constr (17 Mar):18–22 Muller O (2009) Open air excavations at Deriner dam. Int Water Power Dam Constr (17 Mar):18–22
go back to reference Nusier OK, Alawneh AS, Malkawi AH (2002) Remedial measures to control seepage problems in the Kafrein Dam, Jordan. Bull Eng Geol Environ 16:145–152 Nusier OK, Alawneh AS, Malkawi AH (2002) Remedial measures to control seepage problems in the Kafrein Dam, Jordan. Bull Eng Geol Environ 16:145–152
go back to reference Romanov D, Gabrovsek F, Dreybrodt W (2003) Dam sites in soluble rocks: a model of increasing leakage by dissolution widening of fractures beneath a dam. Eng Geol 70:17–35CrossRef Romanov D, Gabrovsek F, Dreybrodt W (2003) Dam sites in soluble rocks: a model of increasing leakage by dissolution widening of fractures beneath a dam. Eng Geol 70:17–35CrossRef
go back to reference Stucky Consulting Engineers Ltd (2001) Deriner dam and hydroelectric power plant project Turkey. Stucky Ltd., Renens Stucky Consulting Engineers Ltd (2001) Deriner dam and hydroelectric power plant project Turkey. Stucky Ltd., Renens
go back to reference Stucky Consulting Engineers Ltd. (2006) Dam consolidation grouting and grout curtain design method of work and site installations. Stucky Ltd., Renens Stucky Consulting Engineers Ltd. (2006) Dam consolidation grouting and grout curtain design method of work and site installations. Stucky Ltd., Renens
go back to reference Stucky Consulting Engineers Ltd. (2006) Dam and appurtenant structures foundation grouting. Stucky Ltd., Renens Stucky Consulting Engineers Ltd. (2006) Dam and appurtenant structures foundation grouting. Stucky Ltd., Renens
go back to reference Tekson Engineering Ltd. (2007) Deriner barajı perde enjeksiyonu test calısmaları. Tekson Engineering Ltd., (in Turkish) Tekson Engineering Ltd. (2007) Deriner barajı perde enjeksiyonu test calısmaları. Tekson Engineering Ltd., (in Turkish)
go back to reference Turkmen S (2003) Treatment of the seepage problems at Kalecik Dam (Turkey). Eng Geol 68:159–169CrossRef Turkmen S (2003) Treatment of the seepage problems at Kalecik Dam (Turkey). Eng Geol 68:159–169CrossRef
go back to reference Uromeihy A, Barzegari G (2007) Evaluation and treatment of seepage problems at Chapar-Abad Dam, Iran. Eng Geol 91:219–228CrossRef Uromeihy A, Barzegari G (2007) Evaluation and treatment of seepage problems at Chapar-Abad Dam, Iran. Eng Geol 91:219–228CrossRef
go back to reference Uromeihy A, Farrokhi R (2012) Evaluating groutability at the Kamal-Saleh dam based on Lugeon tests. Bull Eng Geol Environ 71:215–219CrossRef Uromeihy A, Farrokhi R (2012) Evaluating groutability at the Kamal-Saleh dam based on Lugeon tests. Bull Eng Geol Environ 71:215–219CrossRef
go back to reference Wieland M, Aemmer M, Ruoss R (2008) Design aspects of Deriner dam. Int Water Power Dam Constr 60(7):19–23 Wieland M, Aemmer M, Ruoss R (2008) Design aspects of Deriner dam. Int Water Power Dam Constr 60(7):19–23
Metadata
Title
Foundation consolidation grouting applications in Deriner Dam and Hydroelectric Power Plant (Artvin, Turkey)
Author
Mehmet Özçelik
Publication date
01-05-2014
Publisher
Springer Berlin Heidelberg
Published in
Bulletin of Engineering Geology and the Environment / Issue 2/2014
Print ISSN: 1435-9529
Electronic ISSN: 1435-9537
DOI
https://doi.org/10.1007/s10064-013-0547-7

Other articles of this Issue 2/2014

Bulletin of Engineering Geology and the Environment 2/2014 Go to the issue