Published in: Research in Engineering Design 3/2010

01-07-2010 | Original Paper

Measuring information flow in the detailed design of construction projects

Authors: Effi Tribelsky, Rafael Sacks

Published in: Research in Engineering Design | Issue 3/2010

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Waste in engineering design has many facets, from partial utilization of the solution space, to wasteful management of design resources, and creation of erroneous and ineffective design documents. In the detailed construction documentation design phase of construction projects with teams comprising multiple independent designers, slow and interrupted information flows lead to significant waste. Applying lean principles, such as reducing batch sizes, cycle times and work in progress inventories, to the management of information flows may improve processes and reduce waste in this phase of the design process, but the lack of a method for measuring the volume, rate and effectiveness of information flow is an obstacle to research. This study proposes measuring the flow of information in the process of detailed design where construction documents are prepared. Measures and indices of flow were formulated based on examination of empirical data compiled by monitoring flows of design information in the detailed design stage of each of fourteen construction projects. Data describing the flows was drawn from the database logs created through practitioners’ use of a project extranet service. Indices for identifying information flow bottlenecks, large batch sizes and accumulation of work in process were computed and validated for four of the projects by comparing them with the results of independent observations of design coordination meetings. An index for measuring rework was also computed but could not be validated. The indices and information flow graphs are intended to assist in identifying faults or bottlenecks in the process either as they happen or in retrospective study, indicating disruptions in the information flow. As such, they are important tools for research of engineering design and may be of practical use in design management if incorporated in future online design management tools.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literature
go back to reference Alarcon LF, Diethelm S, Rojo O, Calderon R (2005) Assessing the impacts of implementing lean construction. In: Kenley R (ed) 13th conference of the international group for lean construction. UNSW, Sydney, Australia, pp 387–393 Alarcon LF, Diethelm S, Rojo O, Calderon R (2005) Assessing the impacts of implementing lean construction. In: Kenley R (ed) 13th conference of the international group for lean construction. UNSW, Sydney, Australia, pp 387–393
go back to reference Austin S, Baldwin A, Newton A (1996) A data flow model to plan and manage the building design process. J Eng Des 7(1):3–25CrossRef Austin S, Baldwin A, Newton A (1996) A data flow model to plan and manage the building design process. J Eng Des 7(1):3–25CrossRef
go back to reference Baldwin AN, Austin SA, Hassan TM, Thorpe A (1999) Modelling information flow during the conceptual and schematic stages of building design. Constr Manage Econ 17(2):155–167CrossRef Baldwin AN, Austin SA, Hassan TM, Thorpe A (1999) Modelling information flow during the conceptual and schematic stages of building design. Constr Manage Econ 17(2):155–167CrossRef
go back to reference Ballard G (1998) Positive vs. negative iteration in design. Sixth annual conference of the international group for lean construction (IGLC-6), Guaruja, Brazil, 12 Ballard G (1998) Positive vs. negative iteration in design. Sixth annual conference of the international group for lean construction (IGLC-6), Guaruja, Brazil, 12
go back to reference Ballard G (2000) The last planner™ system of production control. Ph.D. dissertation. The University of Birmingham, Birmingham, UK Ballard G (2000) The last planner™ system of production control. Ph.D. dissertation. The University of Birmingham, Birmingham, UK
go back to reference Ballard G, Howell GA (2003) Lean project management. Build Res Inf 31(2):119–133CrossRef Ballard G, Howell GA (2003) Lean project management. Build Res Inf 31(2):119–133CrossRef
go back to reference Bashford HH, Walsh K, Sawhney A (2005) Production system loading—cycle time relationship in residential construction. J Constr Eng Manag 131(1):15–22CrossRef Bashford HH, Walsh K, Sawhney A (2005) Production system loading—cycle time relationship in residential construction. J Constr Eng Manag 131(1):15–22CrossRef
go back to reference Bashir HA, Thomson V (1999) Metrics for design projects: a review. Des Stud 20(3):263–277 Bashir HA, Thomson V (1999) Metrics for design projects: a review. Des Stud 20(3):263–277
go back to reference Caldwell BS, Palmer RC, Cuevas HM (2008) Information alignment and task coordination in organizations: an ‘information clutch’ metaphor. Inf Syst Manag 25(1):33–44CrossRef Caldwell BS, Palmer RC, Cuevas HM (2008) Information alignment and task coordination in organizations: an ‘information clutch’ metaphor. Inf Syst Manag 25(1):33–44CrossRef
go back to reference Cooper R, Aouad G, Lee A, Wu S, Fleming A, Kagioglou M (2004) Process management in design and construction. Blackwell, OxfordCrossRef Cooper R, Aouad G, Lee A, Wu S, Fleming A, Kagioglou M (2004) Process management in design and construction. Blackwell, OxfordCrossRef
go back to reference Davis JG, Subrahmanian E, Konda S, Granger H, Collins M, Westerberg AW (2001) Creating shared information spaces to support collaborative design work. Inf Syst Front 3(3):377–392CrossRef Davis JG, Subrahmanian E, Konda S, Granger H, Collins M, Westerberg AW (2001) Creating shared information spaces to support collaborative design work. Inf Syst Front 3(3):377–392CrossRef
go back to reference Drucker P (2001) The essential drucker: selections from the management works of Peter F. Drucker. Harper Business, New York Drucker P (2001) The essential drucker: selections from the management works of Peter F. Drucker. Harper Business, New York
go back to reference Eastman CM, Teicholz P, Sacks R, Liston K (2008) BIM handbook: a guide to building information modeling for owners, managers, architects, engineers, contractors, and fabricators. Wiley, Hoboken, NJ Eastman CM, Teicholz P, Sacks R, Liston K (2008) BIM handbook: a guide to building information modeling for owners, managers, architects, engineers, contractors, and fabricators. Wiley, Hoboken, NJ
go back to reference Eckert C, Clarkson J, Stacey M (2001) Information flow in engineering companies: problems and their causes. In: Culley S (ed) International conference on engineering design ICED 01. Wiley, Glasgow, pp 43–50 Eckert C, Clarkson J, Stacey M (2001) Information flow in engineering companies: problems and their causes. In: Culley S (ed) International conference on engineering design ICED 01. Wiley, Glasgow, pp 43–50
go back to reference Eppinger SD, Whitney DE, Smith RP, Gebala DA (1994) A model-based method for organizing tasks in product development. Res Eng Des 6(1):1–13CrossRef Eppinger SD, Whitney DE, Smith RP, Gebala DA (1994) A model-based method for organizing tasks in product development. Res Eng Des 6(1):1–13CrossRef
go back to reference Fisher N, Shen LY (1992) Information management within a contractor-a model for the flow of data. Thomas Telford Publications, LondonCrossRef Fisher N, Shen LY (1992) Information management within a contractor-a model for the flow of data. Thomas Telford Publications, LondonCrossRef
go back to reference Freire J, Alarcon LF (2002) Achieving lean design process: improvement methodology. J Constr Eng Manag 128(3):248–256CrossRef Freire J, Alarcon LF (2002) Achieving lean design process: improvement methodology. J Constr Eng Manag 128(3):248–256CrossRef
go back to reference Fyall M (2002) When project information flow becomes turbulent: toward an organizational reynolds number 138. CIFE—Center for Integrated Facility Engineering, Stanford Fyall M (2002) When project information flow becomes turbulent: toward an organizational reynolds number 138. CIFE—Center for Integrated Facility Engineering, Stanford
go back to reference Goldratt EM (1997) Critical chain. North River Press, Great Barrington, MA Goldratt EM (1997) Critical chain. North River Press, Great Barrington, MA
go back to reference Goldratt EM, Cox J (1993) The goal: a process of ongoing improvement. Gower Publishing, Aldershot, Hampshire Goldratt EM, Cox J (1993) The goal: a process of ongoing improvement. Gower Publishing, Aldershot, Hampshire
go back to reference Gray C, Hughes W (2001) Building design management. Butterworth-Heinemann, Oxford, UK Gray C, Hughes W (2001) Building design management. Butterworth-Heinemann, Oxford, UK
go back to reference Hicks BJ (2007) Lean information management: understanding and eliminating waste. Int J Inf Manag 27(4):233–249 Hicks BJ (2007) Lean information management: understanding and eliminating waste. Int J Inf Manag 27(4):233–249
go back to reference Hopp WJ, Spearman ML (1996) Factory physics. IRWIN, Chicago Hopp WJ, Spearman ML (1996) Factory physics. IRWIN, Chicago
go back to reference Hughes WP (2003) A comparison of two editions of the RIBA plan of work. Eng Constr Archit Manag 10(5):301–311 Hughes WP (2003) A comparison of two editions of the RIBA plan of work. Eng Constr Archit Manag 10(5):301–311
go back to reference Huovila P, Koskela L, Lautanala M (1997) Fast or concurrent: the art of getting construction improved. In: Alarcon LF (ed) Lean construction. Balkema, Rotterdam, pp 143–159CrossRef Huovila P, Koskela L, Lautanala M (1997) Fast or concurrent: the art of getting construction improved. In: Alarcon LF (ed) Lean construction. Balkema, Rotterdam, pp 143–159CrossRef
go back to reference Josephson PE, Hammarlund Y (1999) The causes and costs of defects in construction: a study of seven building projects. Autom Constr 8:681–687CrossRef Josephson PE, Hammarlund Y (1999) The causes and costs of defects in construction: a study of seven building projects. Autom Constr 8:681–687CrossRef
go back to reference Kalay YE (2006) The impact of information technology on design methods, products and practices. Des Stud 27(3):357–380 Kalay YE (2006) The impact of information technology on design methods, products and practices. Des Stud 27(3):357–380
go back to reference Kenley R (2005) Dispelling the complexity myth: founding lean construction on location-based planning. 13th conference of the international group for lean construction. Sydney, Australia, pp 245–251 Kenley R (2005) Dispelling the complexity myth: founding lean construction on location-based planning. 13th conference of the international group for lean construction. Sydney, Australia, pp 245–251
go back to reference Koskela L (1992) Application of the new production philosophy to construction. Technical report # 72. Center for Integrated Facility Engineering, Department of Civil Engineering, Stanford University, Stanford Koskela L (1992) Application of the new production philosophy to construction. Technical report # 72. Center for Integrated Facility Engineering, Department of Civil Engineering, Stanford University, Stanford
go back to reference Koskela L (2000) An exploration towards a production theory and its application to construction. D. Tech, Helsinki University of Technology, Espoo Koskela L (2000) An exploration towards a production theory and its application to construction. D. Tech, Helsinki University of Technology, Espoo
go back to reference Koskela L, Ballard G, Tanhuanpaa V-P (1997) Towards lean design management. 5th annual conference of the international group for lean construction. Griffith University, Gold Coast, Australia Koskela L, Ballard G, Tanhuanpaa V-P (1997) Towards lean design management. 5th annual conference of the international group for lean construction. Griffith University, Gold Coast, Australia
go back to reference Krovi R, Chandra A, Rajagopalan B (2003) Information flow parameters for managing organizational processes. Commun ACM 46(2):77–82CrossRef Krovi R, Chandra A, Rajagopalan B (2003) Information flow parameters for managing organizational processes. Commun ACM 46(2):77–82CrossRef
go back to reference Lee G, Eastman CM, Sacks R (2007) Eliciting information for product modeling using process modeling. Data Knowl Eng 62(2):292–307CrossRef Lee G, Eastman CM, Sacks R (2007) Eliciting information for product modeling using process modeling. Data Knowl Eng 62(2):292–307CrossRef
go back to reference Liker JE (2003) The toyota way. McGraw-Hill, New York Liker JE (2003) The toyota way. McGraw-Hill, New York
go back to reference Love PED, Mandal P, Smith J, Li H (2000) Modeling the dynamics of design error induced rework in construction projects. Constr Manag Econ 18(5):567–574CrossRef Love PED, Mandal P, Smith J, Li H (2000) Modeling the dynamics of design error induced rework in construction projects. Constr Manag Econ 18(5):567–574CrossRef
go back to reference Love PED, Edwards DJ, Irani Z (2008) Forensic project management: an exploratory examination of the causal behavior of design-induced rework. IEEE Trans Eng Manag 55(2):234–247CrossRef Love PED, Edwards DJ, Irani Z (2008) Forensic project management: an exploratory examination of the causal behavior of design-induced rework. IEEE Trans Eng Manag 55(2):234–247CrossRef
go back to reference Manavazhi MR, Xunzhi Z (2001) Productivity oriented analysis of design revisions. Constr Manag Econ 19(4):379–391CrossRef Manavazhi MR, Xunzhi Z (2001) Productivity oriented analysis of design revisions. Constr Manag Econ 19(4):379–391CrossRef
go back to reference Moreau KA, Back WE (2000) Improving the design process with information management. Autom Constr 10:127–140CrossRef Moreau KA, Back WE (2000) Improving the design process with information management. Autom Constr 10:127–140CrossRef
go back to reference Morgan J, Liker JK (2006) The toyota product development system: integrating people, process and technology. Productivity Press, New York Morgan J, Liker JK (2006) The toyota product development system: integrating people, process and technology. Productivity Press, New York
go back to reference Ohno T (1988) Toyota production system: beyond large-scale production. Productivity Press, Cambridge Ohno T (1988) Toyota production system: beyond large-scale production. Productivity Press, Cambridge
go back to reference Ostergaard KJ, Summers JD (2007) Resistance based modeling of collaborative design. Concurr Eng 15(1):21–32CrossRef Ostergaard KJ, Summers JD (2007) Resistance based modeling of collaborative design. Concurr Eng 15(1):21–32CrossRef
go back to reference Pektas ST, Pultar M (2006) Modelling detailed information flows in building design with the parameter-based design structure matrix. Des Stud 27(1):99–122 Pektas ST, Pultar M (2006) Modelling detailed information flows in building design with the parameter-based design structure matrix. Des Stud 27(1):99–122
go back to reference Prasad B, Morenc RS, Rangan RM (1993) Information management for concurrent engineering: research issues. Concurr Eng 1(1):3–20CrossRef Prasad B, Morenc RS, Rangan RM (1993) Information management for concurrent engineering: research issues. Concurr Eng 1(1):3–20CrossRef
go back to reference Sacks R, Goldin M (2007) Lean management model for construction of high-rise apartment buildings. J Const Eng Manag 133(5):374–384CrossRef Sacks R, Goldin M (2007) Lean management model for construction of high-rise apartment buildings. J Const Eng Manag 133(5):374–384CrossRef
go back to reference Sacks R, Eastman CM, Lee G (2004a) Parametric 3D modeling in building construction with examples from precast concrete. Autom Constr 13:291–312CrossRef Sacks R, Eastman CM, Lee G (2004a) Parametric 3D modeling in building construction with examples from precast concrete. Autom Constr 13:291–312CrossRef
go back to reference Sacks R, Eastman CM, Lee G (2004b) Process model perspectives on management and engineering procedures in the precast/prestressed concrete industry. ASCE J Constr Eng Manag 130(2):206–215CrossRef Sacks R, Eastman CM, Lee G (2004b) Process model perspectives on management and engineering procedures in the precast/prestressed concrete industry. ASCE J Constr Eng Manag 130(2):206–215CrossRef
go back to reference Smith RP, Eppinger SD (1997) A predictive model of sequential iteration in engineering design. Manag Sci 43(8):1104–1120MATHCrossRef Smith RP, Eppinger SD (1997) A predictive model of sequential iteration in engineering design. Manag Sci 43(8):1104–1120MATHCrossRef
go back to reference Smith RP, Tjandra P (1998) Experimental observation of iteration in engineering design. Res Eng Des 10:107–117CrossRef Smith RP, Tjandra P (1998) Experimental observation of iteration in engineering design. Res Eng Des 10:107–117CrossRef
go back to reference Steward DV (1981) The design structure system: a method for managing the design of complex systems. IEEE Trans Eng Manag 28:71–74 Steward DV (1981) The design structure system: a method for managing the design of complex systems. IEEE Trans Eng Manag 28:71–74
go back to reference Thomas HR, Korte C, Sanvido VE, Parfitt MK (1999) Conceptual model for measuring productivity of design and engineering. J Archit Eng 5(1):1–7MATHCrossRef Thomas HR, Korte C, Sanvido VE, Parfitt MK (1999) Conceptual model for measuring productivity of design and engineering. J Archit Eng 5(1):1–7MATHCrossRef
go back to reference Tommelein ID (1998) Pull-driven scheduling for pipe-spool installation: simulation of lean construction technique. ASCE J Constr Eng Manag 124(4):279–288CrossRef Tommelein ID (1998) Pull-driven scheduling for pipe-spool installation: simulation of lean construction technique. ASCE J Constr Eng Manag 124(4):279–288CrossRef
go back to reference Torbett R, Salter AJ, Gann DM, Hobday M (2001) Design performance measurement in the construction sector: a pilot study. University of Sussex, Brighton Torbett R, Salter AJ, Gann DM, Hobday M (2001) Design performance measurement in the construction sector: a pilot study. University of Sussex, Brighton
go back to reference Womack JP, Jones DT (2003) Lean thinking: banish waste and create wealth in your corporation. Simon & Schuster, New York Womack JP, Jones DT (2003) Lean thinking: banish waste and create wealth in your corporation. Simon & Schuster, New York
go back to reference Womack JP, Jones DT, Roos D (1991) The machine that changed the world. Harper Business, New York Womack JP, Jones DT, Roos D (1991) The machine that changed the world. Harper Business, New York
Metadata
Title
Measuring information flow in the detailed design of construction projects
Authors
Effi Tribelsky
Rafael Sacks
Publication date
01-07-2010
Publisher
Springer-Verlag
Published in
Research in Engineering Design / Issue 3/2010
Print ISSN: 0934-9839
Electronic ISSN: 1435-6066
DOI
https://doi.org/10.1007/s00163-009-0084-3

Other articles of this Issue 3/2010

Research in Engineering Design 3/2010 Go to the issue

Premium Partners