Published in: Water Resources Management 8/2019

16-05-2019

Optimal Reservoir Flood Control Operation Using a Hedging Model and Considering the Near-Field Vibrations Induced by Flood Release

Authors: Ji-Jian Lian, Xin-Yu Guo, Chao Ma, Kui Xu

Published in: Water Resources Management | Issue 8/2019

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Several researchers have extensively investigated the flow-induced vibrations caused by flood release because numerous structures have been destroyed by such release. Nevertheless, none of the previous research has considered vibration safety during flood control operation. In this study, a hedging scheduling model considering the near-field vibrations induced by flood release and hydrological uncertainty is proposed to optimize the discharge process. The dispatch model was applied to the Xiangjiaba reservoir due to the reservoir’s classic problem of near-field vibrations induced by flood release. The measured root-mean square (RMS) data for the acceleration in the vertical direction of near-field vibrations were used to summarize safety constraints. The vibration safety discharge ceiling was determined according to field test records and was regarded as an operational safety constraint for the dispatch model. Based on this innovative safety constraint, this paper demonstrates the development of an optimal dispatch model for reservoirs by considering forecast uncertainty. The proposed strategy utilizes storage capacity to optimally allocate the gap between the expected flood volume and vibration safety discharge capacity (GBEV) in the discharge process. Optimal flood control operation considering the near-field vibrations induced by flood release falls into four categories, with each category corresponding to one optimal operation strategy. The solution set to this model can provide decision support for reservoirs with similar flood-induced vibration problems and optimize the power output of hydropower stations.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Appendix
Available only for authorised users
Literature
go back to reference Chou FNF, Wu CW (2013) Expected shortage based pre-release strategy for reservoir flood control. J Hydrol 497:1–14CrossRef Chou FNF, Wu CW (2013) Expected shortage based pre-release strategy for reservoir flood control. J Hydrol 497:1–14CrossRef
go back to reference Ding W, Zhang C, Yong P (2015) An analytical framework for flood water conservation considering forecast uncertainty and acceptable risk. Water Resour Res 10:4702–4726CrossRef Ding W, Zhang C, Yong P (2015) An analytical framework for flood water conservation considering forecast uncertainty and acceptable risk. Water Resour Res 10:4702–4726CrossRef
go back to reference Fu G (2008) A fuzzy optimization method for multicriteria decision making: An application to reservoir flood control operation. Expert Syst Appl 34:145–149CrossRef Fu G (2008) A fuzzy optimization method for multicriteria decision making: An application to reservoir flood control operation. Expert Syst Appl 34:145–149CrossRef
go back to reference Jia B, Simonovic SP, Zhong P (2016) A multi-objective best compromise decision model for real-time flood mitigation operations of multi-reservoir system. Water Resour Manag 30:3363–3387CrossRef Jia B, Simonovic SP, Zhong P (2016) A multi-objective best compromise decision model for real-time flood mitigation operations of multi-reservoir system. Water Resour Manag 30:3363–3387CrossRef
go back to reference Li C-X, Zhang J (2016) Nonlinear coupled dynamics analysis of a truss spar platform. China Ocean Engineering 30(6):835–850 Li C-X, Zhang J (2016) Nonlinear coupled dynamics analysis of a truss spar platform. China Ocean Engineering 30(6):835–850
go back to reference Li Q, Ouyang S (2015) Research on multi-objective joint optimal flood control model for cascade reservoirs in river basin system. Nat Hazards 77:2097–2115CrossRef Li Q, Ouyang S (2015) Research on multi-objective joint optimal flood control model for cascade reservoirs in river basin system. Nat Hazards 77:2097–2115CrossRef
go back to reference Lian J, Cui G, Lin J (1999) Calculation model for flow—induced high arch dam vibration and its verification. J Hydraul Eng 30:23–32 (in Chinese) Lian J, Cui G, Lin J (1999) Calculation model for flow—induced high arch dam vibration and its verification. J Hydraul Eng 30:23–32 (in Chinese)
go back to reference Lian J, Li C, Liu F (2014) A prediction method of flood discharge atomization for high dams. J Hydraul Res 52:274–282CrossRef Lian J, Li C, Liu F (2014) A prediction method of flood discharge atomization for high dams. J Hydraul Res 52:274–282CrossRef
go back to reference Lian J, Zhang Y, Liu F (2015) Analysis of the ground vibration induced by high dam flood discharge using the cross wavelet transform method. J Renew Sustain Energy 7:043146–041–22CrossRef Lian J, Zhang Y, Liu F (2015) Analysis of the ground vibration induced by high dam flood discharge using the cross wavelet transform method. J Renew Sustain Energy 7:043146–041–22CrossRef
go back to reference Ma B, Lian J, Yang M (2008) Hydroelastic model experimental study on large scale high arch dam vibration by discharge flow. Chinese Eng Sci 10:23–29 (in Chinese) Ma B, Lian J, Yang M (2008) Hydroelastic model experimental study on large scale high arch dam vibration by discharge flow. Chinese Eng Sci 10:23–29 (in Chinese)
go back to reference Ma C, Wang H, Lian J (2011) Short-term electricity dispatch optimization of Ertan hydropower plant based on data by field tests. J Renew Sustain Energy 3:1–14CrossRef Ma C, Wang H, Lian J (2011) Short-term electricity dispatch optimization of Ertan hydropower plant based on data by field tests. J Renew Sustain Energy 3:1–14CrossRef
go back to reference Peng Y, Xu W, Liu B (2017) Considering precipitation forecasts for real-time decision-making in hydropower operations. Int J Water Resour Dev 33:987–1002CrossRef Peng Y, Xu W, Liu B (2017) Considering precipitation forecasts for real-time decision-making in hydropower operations. Int J Water Resour Dev 33:987–1002CrossRef
go back to reference Shiau JT (2011) Analytical optimal hedging with explicit incorporation of reservoir release and carryover storage targets. Water Resour Res 47:W01515CrossRef Shiau JT (2011) Analytical optimal hedging with explicit incorporation of reservoir release and carryover storage targets. Water Resour Res 47:W01515CrossRef
go back to reference Sun X, Ma C, Lian J (2018) Optimal Operation of Danjiangkou Reservoir Using Improved Hedging Model and Considering the Effects of Historical Decisions. J Water Resour Plan Manag 144:04017080CrossRef Sun X, Ma C, Lian J (2018) Optimal Operation of Danjiangkou Reservoir Using Improved Hedging Model and Considering the Effects of Historical Decisions. J Water Resour Plan Manag 144:04017080CrossRef
go back to reference Tu M-Y, Hsu N-S, Tsai FT-C (2008) Optimization of Hedging Rules for Reservoir Operations. J Water Resour Plan Manag 134:3–13CrossRef Tu M-Y, Hsu N-S, Tsai FT-C (2008) Optimization of Hedging Rules for Reservoir Operations. J Water Resour Plan Manag 134:3–13CrossRef
go back to reference Yalcin E, Tigrek S (2017) The Tigris hydropower system operations: the need for an integrated approach. Int J Water Resour Dev:1–16 Yalcin E, Tigrek S (2017) The Tigris hydropower system operations: the need for an integrated approach. Int J Water Resour Dev:1–16
go back to reference Zhang J, Peng Y, Xu W (2017) Hydraulic prediction of near-field vibrations induced by releasing flood. J Hydraul Eng 143:05017002CrossRef Zhang J, Peng Y, Xu W (2017) Hydraulic prediction of near-field vibrations induced by releasing flood. J Hydraul Eng 143:05017002CrossRef
go back to reference Zhao T, Zhao J, Lund JR, Yang D (2014) Optimal hedging rules for reservoir flood operation from forecast uncertainties. J Water Resour Plan Manag 140(12):04014041 Zhao T, Zhao J, Lund JR, Yang D (2014) Optimal hedging rules for reservoir flood operation from forecast uncertainties. J Water Resour Plan Manag 140(12):04014041
Metadata
Title
Optimal Reservoir Flood Control Operation Using a Hedging Model and Considering the Near-Field Vibrations Induced by Flood Release
Authors
Ji-Jian Lian
Xin-Yu Guo
Chao Ma
Kui Xu
Publication date
16-05-2019
Publisher
Springer Netherlands
Published in
Water Resources Management / Issue 8/2019
Print ISSN: 0920-4741
Electronic ISSN: 1573-1650
DOI
https://doi.org/10.1007/s11269-019-02231-w

Other articles of this Issue 8/2019

Water Resources Management 8/2019 Go to the issue