Abstract

In order to further improve the stability of TBM excavation passing through the underground station, this paper takes the Hemu Road station of Chongqing Metro Line 5 as the research background, and uses the numerical simulation software FLAC 3D to study the process optimization of TBM construction technology combined with double side drift method. The results show that: compared with the step by step construction of tunnel first excavated and then expanded into platform combined with double side drift method (working condition 1 ~ 5), the synchronous construction of tunnel before station combined with double side drift method (working condition 6 ~ 8) generally has less impact on surface settlement, final deformation of station, segment deformation and stress. Among them, the clearance convergence, segment deformation left inverted arch floats upward) and stress of working condition 8 are the minimum values, which are 1.87 mm, 0.16 mm and 0.595 MPa respectively. Compared with other methods, the clearance convergence, segment deformation and segment tensile stress of station structure are reduced by 59%, 50% and 40% respectively under working condition 8. It is recommended to apply the inverted edge construction sequence of synchronous construction in TBM excavation combined with double side drift method.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literature
go back to reference Freeman M (1998) Triple face slurry shield for Tokyo metro station. Tunnels & Tunnelling International 30 Freeman M (1998) Triple face slurry shield for Tokyo metro station. Tunnels & Tunnelling International 30
go back to reference Jia J, Shi JS, Zhou SH (2013) Forecast and analysis of surface settlement of metro station constructed by shield tunnel expanding. Chin J Rock Mech Eng 32(S1):2883–2890 Jia J, Shi JS, Zhou SH (2013) Forecast and analysis of surface settlement of metro station constructed by shield tunnel expanding. Chin J Rock Mech Eng 32(S1):2883–2890
go back to reference Jiang FG, Bai LL, Song M, Wang LT, Tan XT (2020) Analysis on construction stability of large section tunnel of Harbin City Metro. J Jilin Univ (Eng Technol Ed) 50(04):1419–1427 Jiang FG, Bai LL, Song M, Wang LT, Tan XT (2020) Analysis on construction stability of large section tunnel of Harbin City Metro. J Jilin Univ (Eng Technol Ed) 50(04):1419–1427
go back to reference Li QB (2014) Application of 95 m long pipe-shed in soil with great difference in the subway transfer station. Constr Technol 43(S1):53–56 Li QB (2014) Application of 95 m long pipe-shed in soil with great difference in the subway transfer station. Constr Technol 43(S1):53–56
go back to reference Li XD, Wang W (2015) Case study on construction of shallow metro tunnel by double side heading method with core rock kept. Tunn Constr 35(10):1060 Li XD, Wang W (2015) Case study on construction of shallow metro tunnel by double side heading method with core rock kept. Tunn Constr 35(10):1060
go back to reference Li XW, Zheng H, Wang QX (2016) Safety analysis for metro station constructed by enlarging large diameter shield tunnel with mining method. China Civ Eng J 49(9):96–102 Li XW, Zheng H, Wang QX (2016) Safety analysis for metro station constructed by enlarging large diameter shield tunnel with mining method. China Civ Eng J 49(9):96–102
go back to reference Lin ZH (2009) Stability analysis for large-span highway tunnel by side-expand excavation. J Railw Sci Eng 6(4):46–50 Lin ZH (2009) Stability analysis for large-span highway tunnel by side-expand excavation. J Railw Sci Eng 6(4):46–50
go back to reference Mashimo H, Ishimura T, Isago N et al (2005) Behavior of supportstructure of existing tunnels during enlargement of cross section. In: ITA—AITES 2005 world tunnel congress. Rotterdam, pp 133–138 Mashimo H, Ishimura T, Isago N et al (2005) Behavior of supportstructure of existing tunnels during enlargement of cross section. In: ITA—AITES 2005 world tunnel congress. Rotterdam, pp 133–138
go back to reference (MOC) Ministry of Transport of the People’s Republic of China (2004) Code for design of road tunnel. JTG D70-2004, Beijing, China (MOC) Ministry of Transport of the People’s Republic of China (2004) Code for design of road tunnel. JTG D70-2004, Beijing, China
go back to reference Mohamed AN, Elhashimy AM, Mansour MA (2019) Construction techniques for intersection of TBM tunnel and station at Cairo metro line 3 Mohamed AN, Elhashimy AM, Mansour MA (2019) Construction techniques for intersection of TBM tunnel and station at Cairo metro line 3
go back to reference Wu ZZ, Xu GL, Wu L, Ye Q (2009) Mechanical deformation characteristics of rock mass surround in lateral enlarging excavation of tunnels with ultra-large sections. Chin J Geotech Eng 31(2):172–177 Wu ZZ, Xu GL, Wu L, Ye Q (2009) Mechanical deformation characteristics of rock mass surround in lateral enlarging excavation of tunnels with ultra-large sections. Chin J Geotech Eng 31(2):172–177
Metadata
Title
Study on Underground Excavation Construction Technology of TBM with Tunnel First Excavated and then Expanded into Platform Based on Double Side Drift Method
Authors
Guangyao Cui
Hanghang Wei
Publication date
04-04-2022
Publisher
Springer International Publishing
Published in
Geotechnical and Geological Engineering / Issue 7/2022
Print ISSN: 0960-3182
Electronic ISSN: 1573-1529
DOI
https://doi.org/10.1007/s10706-022-02119-4

Other articles of this Issue 7/2022

Geotechnical and Geological Engineering 7/2022 Go to the issue