The impact of decision criteria on deadline-based incentive contracts in project management

Authors: Jiao Wang, Kai Yang, Ruiqing Zhao

Published in: Journal of Intelligent Manufacturing | Issue 3/2017

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

This paper investigates the impact of decision criteria on incentives in a project management setting, where a project manager operates a project consisting of two tasks performed sequentially by two different subcontractors. The completion time is characterized as an uncertain variable, which depends on the subcontractor’s unobservable effort of each task. Within the framework of uncertainty theory, four classes of uncertain principal agent models are presented under the expected value criterion and the critical value criterion. According to the structural characteristics, each model can be decomposed into two equivalent sub-models, which can be solved to obtain the optimal deadline-based incentive contracts via a two-step optimization method. Further, the interconnections among these contracts are discussed. It’s demonstrated that the optimal deadline-based incentive contract depends on the confidence level of the party (either the project manager or the subcontractor) who adopts the critical value criterion. Meanwhile, the more conservative the subcontractor is, the higher the incentive coefficients will be. And the more conservative the project manager is, the lower the incentive coefficients will be. Finally, given some special confidence levels, it’s interesting to find that the four models can be equivalent.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literature
go back to reference Bayiz, M., & Corbett, C.J. (2005). Coordination and incentive contracts in project management under asymmetric information. Working paper, UCLA Anderson School. Bayiz, M., & Corbett, C.J. (2005). Coordination and incentive contracts in project management under asymmetric information. Working paper, UCLA Anderson School.
go back to reference Elmaghraby, S. E. (1990). Project bidding under deterministic and probabilistic activity durations. European Journal of Operational Research, 49(1), 14–34.CrossRef Elmaghraby, S. E. (1990). Project bidding under deterministic and probabilistic activity durations. European Journal of Operational Research, 49(1), 14–34.CrossRef
go back to reference Fulkerson, D. R. (1961). A network flow computation for project cost curves. Management Science, 7(2), 167–179.CrossRef Fulkerson, D. R. (1961). A network flow computation for project cost curves. Management Science, 7(2), 167–179.CrossRef
go back to reference Gutierrez, G., & Paul, A. (2000). Analysis of the effects of uncertainty, risk-pooling, and subcontracting mechanisms on project performance. Operations Research, 48(6), 927–938.CrossRef Gutierrez, G., & Paul, A. (2000). Analysis of the effects of uncertainty, risk-pooling, and subcontracting mechanisms on project performance. Operations Research, 48(6), 927–938.CrossRef
go back to reference Kelley, J. E. (1961). Critical path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296–320.CrossRef Kelley, J. E. (1961). Critical path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296–320.CrossRef
go back to reference Kwon, H. D., Lippman, H. D., & Tang, C. S. (2010). Optimal time-based and cost-based coordinated project contracts with unobservable work rates. International Journal of Production Economics, 126(2), 247–254.CrossRef Kwon, H. D., Lippman, H. D., & Tang, C. S. (2010). Optimal time-based and cost-based coordinated project contracts with unobservable work rates. International Journal of Production Economics, 126(2), 247–254.CrossRef
go back to reference Kwon, H. D., Lippman, S. A., & Tang, C. S. (2011). Sourcing decisions of project tasks with exponential completion times: Impact on operating profits. International Journal of Production Economics, 134(1), 138–150. Kwon, H. D., Lippman, S. A., & Tang, C. S. (2011). Sourcing decisions of project tasks with exponential completion times: Impact on operating profits. International Journal of Production Economics, 134(1), 138–150.
go back to reference Lan, Y., Zhao, R., & Tang, W. (2011). A bilevel fuzzy principal-agent model for optimal nonlinear taxation problems. Fuzzy Optimization and Decision Making, 10(3), 211–232. Lan, Y., Zhao, R., & Tang, W. (2011). A bilevel fuzzy principal-agent model for optimal nonlinear taxation problems. Fuzzy Optimization and Decision Making, 10(3), 211–232.
go back to reference Li, X., & Wong, H. (2010). Credibilistic satisfiability and credibilistic entailment. Journal of Multi-Valued Logic and Soft Computing, 16(1–2), 105–134. Li, X., & Wong, H. (2010). Credibilistic satisfiability and credibilistic entailment. Journal of Multi-Valued Logic and Soft Computing, 16(1–2), 105–134.
go back to reference Li, X., & Liu, B. (2009a). Foundation of credibilistic logic. Fuzzy Optimization and Decision Making, 8(3), 91–102.CrossRef Li, X., & Liu, B. (2009a). Foundation of credibilistic logic. Fuzzy Optimization and Decision Making, 8(3), 91–102.CrossRef
go back to reference Li, X., & Liu, B. (2009b). Hybrid logic and uncertain logic. Journal of Uncertain Systems, 3(2), 83–94. Li, X., & Liu, B. (2009b). Hybrid logic and uncertain logic. Journal of Uncertain Systems, 3(2), 83–94.
go back to reference Liu, B. (2009). Some research problems in uncertainty theory. Journal of Uncertain Systems, 3(1), 3–10. Liu, B. (2009). Some research problems in uncertainty theory. Journal of Uncertain Systems, 3(1), 3–10.
go back to reference Liu, B. (2010). Uncertainty theory: A branch of mathematics for modeling human uncertainty. Berlin: Springer. Liu, B. (2010). Uncertainty theory: A branch of mathematics for modeling human uncertainty. Berlin: Springer.
go back to reference Liu, B. (2007). Uncertainty theory (2nd ed.). Berlin: Springer. Liu, B. (2007). Uncertainty theory (2nd ed.). Berlin: Springer.
go back to reference Liu, B. (2011). Uncertain logic for modeling human language. Journal of Uncertain Systems, 5(1), 3–20. Liu, B. (2011). Uncertain logic for modeling human language. Journal of Uncertain Systems, 5(1), 3–20.
go back to reference Liu, B. (2013a). Polyrectangular theorem and independence of uncertain vectors. Journal of Uncertainty Analysis and Applications, 1, 9.CrossRef Liu, B. (2013a). Polyrectangular theorem and independence of uncertain vectors. Journal of Uncertainty Analysis and Applications, 1, 9.CrossRef
go back to reference Liu, Y. (2013b). Uncertain random variables: A mixture of uncertainty and randomness. Soft Computing, 17(4), 625–634.CrossRef Liu, Y. (2013b). Uncertain random variables: A mixture of uncertainty and randomness. Soft Computing, 17(4), 625–634.CrossRef
go back to reference Liu, B. (2015). Uncertainty theory (4th ed.). Berlin: Springer. Liu, B. (2015). Uncertainty theory (4th ed.). Berlin: Springer.
go back to reference Mu, R., Lan, Y., & Tang, W. (2013). An uncertain contract model for rural migrant worker’s employment problems. Fuzzy Optimization and Decision Making, 12(1), 29–39.CrossRef Mu, R., Lan, Y., & Tang, W. (2013). An uncertain contract model for rural migrant worker’s employment problems. Fuzzy Optimization and Decision Making, 12(1), 29–39.CrossRef
go back to reference Paul, A., & Gutierrez, G. (2005). Simple probability models for project contracting. European Journal of Operational Research, 165(2), 329–338.CrossRef Paul, A., & Gutierrez, G. (2005). Simple probability models for project contracting. European Journal of Operational Research, 165(2), 329–338.CrossRef
go back to reference Wang, G., Tang, W., & Zhao, R. (2013). An uncertain price discrimination model in labor market. Soft Computing, 17(4), 579–585.CrossRef Wang, G., Tang, W., & Zhao, R. (2013). An uncertain price discrimination model in labor market. Soft Computing, 17(4), 579–585.CrossRef
go back to reference Wu, X., Zhao, R., & Tang, W. (2013). Uncertain agency models with multi-dimensional incomplete information based on confidence level. Fuzzy Optimization and Decision Making, 13(2), 231–258.CrossRef Wu, X., Zhao, R., & Tang, W. (2013). Uncertain agency models with multi-dimensional incomplete information based on confidence level. Fuzzy Optimization and Decision Making, 13(2), 231–258.CrossRef
go back to reference Yang, X., & Gao, J. (2013). Uncertain differential games with application to capitalism. Journal of Uncertainty Analysis and Applications, 1, 17.CrossRef Yang, X., & Gao, J. (2013). Uncertain differential games with application to capitalism. Journal of Uncertainty Analysis and Applications, 1, 17.CrossRef
go back to reference Yang, K., Liu, Y., & Yang, G. (2014). Optimizing fuzzy \(p\)-hub center problem with generalized value-at-risk criterion. Applied Mathematical Modelling, 38(15–16), 3987–4005.CrossRef Yang, K., Liu, Y., & Yang, G. (2014). Optimizing fuzzy \(p\)-hub center problem with generalized value-at-risk criterion. Applied Mathematical Modelling, 38(15–16), 3987–4005.CrossRef
go back to reference Yang, K., Zhao, R., & Lan, Y. (2014). The impact of risk attitude in new product development under dual information asymmetry. Computers & Industrial Engineering, 76(10), 122–137.CrossRef Yang, K., Zhao, R., & Lan, Y. (2014). The impact of risk attitude in new product development under dual information asymmetry. Computers & Industrial Engineering, 76(10), 122–137.CrossRef
go back to reference Yang, X., & Gao, J. (2014). Uncertain core for coalitional game with uncertain payoffs. Journal of Uncertain Systems, 8(2), 13–21. Yang, X., & Gao, J. (2014). Uncertain core for coalitional game with uncertain payoffs. Journal of Uncertain Systems, 8(2), 13–21.
go back to reference Yang, L., Liu, P., Li, S., Gao, Y., & Ralescu, D. (2015). Reduction methods of type-2 uncertain variables and their applications to solid transportation problem. Information Sciences, 291, 204–237.CrossRef Yang, L., Liu, P., Li, S., Gao, Y., & Ralescu, D. (2015). Reduction methods of type-2 uncertain variables and their applications to solid transportation problem. Information Sciences, 291, 204–237.CrossRef
go back to reference Zhu, Y. (2010). Uncertain optimal control with application to a portfolio selection model. Cybernetics and Systems, 41(7), 535–547.CrossRef Zhu, Y. (2010). Uncertain optimal control with application to a portfolio selection model. Cybernetics and Systems, 41(7), 535–547.CrossRef
Metadata
Title
The impact of decision criteria on deadline-based incentive contracts in project management
Authors
Jiao Wang
Kai Yang
Ruiqing Zhao
Publication date
04-11-2014
Publisher
Springer US
Published in
Journal of Intelligent Manufacturing / Issue 3/2017
Print ISSN: 0956-5515
Electronic ISSN: 1572-8145
DOI
https://doi.org/10.1007/s10845-014-0994-4