Published in: Energy Systems 1/2014

01-03-2014 | Original Paper

The north European power system dispatch in 2010 and 2020

Expecting a large share of renewable energy sources

Authors: Stefan Jaehnert, Gerard L. Doorman

Published in: Energy Systems | Issue 1/2014

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Prospectively, the European power system will need to incorporate a large share of power production from renewable energy sources. Likewise a significant change in the portfolio of thermal power plants and a strengthening of interconnections is expected. Moreover, the current process of integrating electricity markets will alter the system dispatch and have a significant impact on electricity prices as well. An operation optimisation model suited for hydro-thermal systems (EMPS), is applied to assess these changes. A 2010 and a 2020 scenario of the Northern European power system are developed and simulated. The scope of the analysis is on the increasing interaction of the Nordic and continental European power systems. Given nearly a doubling of interconnection capacity between the Nordic region and continental Europe up to 2020, the possibility of balancing the variable power production from renewable energy sources with Nordic hydro power will be enhanced. The simulations show reduced operation of thermal power plants, a higher variability of the Nordic hydro power production as well as an overall increased exchange among the areas. The impact of the level of wind power production on the system dispatch is illustrated. Moreover, electricity prices become more volatile, but their average decreases.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Footnotes
1
EFI’s Multi-area power-market simulator.
 
2
During wet years with high inflow to the Nordic system, prices are low due to excessive hydro production (0 % percentile). In contrary, during dry years with low inflow, prices become high (100 % percentile).
 
3
Outages of thermal power plants are taken into account by reducing the available thermal capacity in each individual week. The available capacity per week is based on published data at the European Energy Exchange [15].
 
Literature
2.
go back to reference Aigner, T., Gjengedal, T.: Modelling wind power production based on numerical prediction models and wind speed measurements. In: PSCC Conference, Stockholm, pp. 1–6 (2011) Aigner, T., Gjengedal, T.: Modelling wind power production based on numerical prediction models and wind speed measurements. In: PSCC Conference, Stockholm, pp. 1–6 (2011)
16.
go back to reference European Wind Energy Association: integrating wind—developing Europe’s power market for the large-scale integration of wind power. Report (2009). http://www.trade-wind.eu/ (Accessed 21 March 2011) European Wind Energy Association: integrating wind—developing Europe’s power market for the large-scale integration of wind power. Report (2009). http://​www.​trade-wind.​eu/​ (Accessed 21 March 2011)
18.
go back to reference Holttinen, H., Milligan, M., Kirby, B., Acker, T., Neimane, V., Molinski, T.: Using standard deviation as a measure of increased operational reserve requirement for wind power. Wind Eng. 32(4) (2008) Holttinen, H., Milligan, M., Kirby, B., Acker, T., Neimane, V., Molinski, T.: Using standard deviation as a measure of increased operational reserve requirement for wind power. Wind Eng. 32(4) (2008)
19.
go back to reference Jaehnert, S., Doorman, G.: Modelling an integrated northern European regulating power market based on a common day-ahead market. In: 33th IAEE International Conference, Rio de Janeiro (2010) Jaehnert, S., Doorman, G.: Modelling an integrated northern European regulating power market based on a common day-ahead market. In: 33th IAEE International Conference, Rio de Janeiro (2010)
20.
go back to reference Korpås, M., Warland, L., Tande, J., Uhlen, K., Purchala, K., Wagemans, S.: Further developing Europe’s power market for large scale integration of wind power—grid modelling and power system data. Tech. rep, SINTEF (2008) Korpås, M., Warland, L., Tande, J., Uhlen, K., Purchala, K., Wagemans, S.: Further developing Europe’s power market for large scale integration of wind power—grid modelling and power system data. Tech. rep, SINTEF (2008)
26.
go back to reference Schaber, K., Steinke, F., Hamacher, T.: Transmission grid extensions for the integration of variable renewable energies in Europe: who benefits where? Energy Policy 43(1), 123–135 (2012)CrossRef Schaber, K., Steinke, F., Hamacher, T.: Transmission grid extensions for the integration of variable renewable energies in Europe: who benefits where? Energy Policy 43(1), 123–135 (2012)CrossRef
28.
go back to reference Solvang, E., Harby, A., Killingveit, A.: Increasing balance power capacity in Norwegian hydroelectric power stations, TR A7195. Report (2011). http://www.cedren.no/ (Accessed 21 March 2011) Solvang, E., Harby, A., Killingveit, A.: Increasing balance power capacity in Norwegian hydroelectric power stations, TR A7195. Report (2011). http://​www.​cedren.​no/​ (Accessed 21 March 2011)
31.
go back to reference Svenska Kraftnät, Statnett: Swedish Norwegian grid development—three scenarios. Report (2010) (Accessed 20 Dec 2011) Svenska Kraftnät, Statnett: Swedish Norwegian grid development—three scenarios. Report (2010) (Accessed 20 Dec 2011)
34.
go back to reference Warland, G., Haugstad, A., Huse, E.: Including thermal unit start-up costs in a long-term hydro-thermal scheduling model. In: 2008 PSCC. 16th Power Systems Computation Conference, Glasgow, pp. 1–6 (2008) Warland, G., Haugstad, A., Huse, E.: Including thermal unit start-up costs in a long-term hydro-thermal scheduling model. In: 2008 PSCC. 16th Power Systems Computation Conference, Glasgow, pp. 1–6 (2008)
36.
go back to reference Wolfgang, O., Haugstad, A., Mo, B., Gjelsvik, A., Wangensteen, I., Doorman, G.: Hydro reservoir handling before and after deregulation. Energy 34, 1642–1651 (2009)CrossRef Wolfgang, O., Haugstad, A., Mo, B., Gjelsvik, A., Wangensteen, I., Doorman, G.: Hydro reservoir handling before and after deregulation. Energy 34, 1642–1651 (2009)CrossRef
Metadata
Title
The north European power system dispatch in 2010 and 2020
Expecting a large share of renewable energy sources
Authors
Stefan Jaehnert
Gerard L. Doorman
Publication date
01-03-2014
Publisher
Springer Berlin Heidelberg
Published in
Energy Systems / Issue 1/2014
Print ISSN: 1868-3967
Electronic ISSN: 1868-3975
DOI
https://doi.org/10.1007/s12667-013-0088-y

Other articles of this Issue 1/2014

Energy Systems 1/2014 Go to the issue