Simultaneous lotsizing and scheduling considering secondary resources: a general model, literature review and classification

Authors: Martin Wörbelauer, Herbert Meyr, Bernardo Almada-Lobo

Published in: OR Spectrum | Issue 1/2019

Log in

Activate our intelligent search to find suitable subject content or patents.

search-config
loading …

Abstract

Typical simultaneous lotsizing and scheduling models consider the limited capacity of the production system by respecting a maximum time the respective machines or production lines can be available. Further limitations of the production quantities can arise by the scarce availability of, e.g., setup tools, setup operators or raw materials which thus cannot be neglected in optimization models. In the literature on simultaneous lotsizing and scheduling, these production factors are called “secondary resources”. This paper provides a structured overview of the literature on simultaneous lotsizing and scheduling involving secondary resources. The proposed classification yields for the first time a unified view of scarce production factors. The insights about different types of secondary resources help to develop a new model formulation generalizing and extending the currently used approaches that are specific for some settings. Some illustrative examples demonstrate the functional principle and flexibility of this new formulation which can thus be used for a wide range of applications.

Dont have a licence yet? Then find out more about our products and how to get one now:

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Footnotes
1
This denomination has only later been introduced by Fleischmann (1990).
 
2
See also Copil (2016).
 
3
Using the same index sequence ji three times for \(z^{c}_{lji,s-1}\), \(z^{c}_{ljis}\) and \(z_{ljis}\) allows (10) to carry the information, which product had been produced last, over all microperiods of a continued setup.
 
4
We omit the index l of the production lines for ease of readability.
 
5
If a property o does only refer to some ingredient of the SRs, as for example the sugar content of orange and pineapple concentrate, a corresponding factor \(a_{on}\) can be introduced and (24) can be changed to \(\sum _{n \in \Xi _o} a_{on} x^{p}_{lns} \ge f^{p}_{jo}x_{ljs}\).
 
Literature
go back to reference Almada-Lobo B, Klabjan D, Carravilla MA, Oliveira JF (2010) Multiple machine continuous setup lotsizing with sequence-dependent setups. Comput Optim Appl 47(3):529–552CrossRef Almada-Lobo B, Klabjan D, Carravilla MA, Oliveira JF (2010) Multiple machine continuous setup lotsizing with sequence-dependent setups. Comput Optim Appl 47(3):529–552CrossRef
go back to reference Almeder C, Almada-Lobo B (2011) Synchronisation of scarce resources for a parallel machine lotsizing problem. Int J Prod Res 49(24):7315–7335CrossRef Almeder C, Almada-Lobo B (2011) Synchronisation of scarce resources for a parallel machine lotsizing problem. Int J Prod Res 49(24):7315–7335CrossRef
go back to reference Anupindi R, Chopra S, Deshmukh SD, Van Mieghem JA, Zemel E (2014) Managing business process flows, 3rd edn. Pearson Education Limited, London Anupindi R, Chopra S, Deshmukh SD, Van Mieghem JA, Zemel E (2014) Managing business process flows, 3rd edn. Pearson Education Limited, London
go back to reference Balakrishnan A, Geunes J (2000) Requirements planning with substitutions: exploiting bill-of-materials flexibility in production planning. Manuf Serv Oper Manag 2(2):166–185CrossRef Balakrishnan A, Geunes J (2000) Requirements planning with substitutions: exploiting bill-of-materials flexibility in production planning. Manuf Serv Oper Manag 2(2):166–185CrossRef
go back to reference Camargo VCB, Toledo FMB, Almada-Lobo B (2012) Three time-based scale formulations for the two stage lot sizing and scheduling in process industries. J Oper Res Soc 63:1613–1630CrossRef Camargo VCB, Toledo FMB, Almada-Lobo B (2012) Three time-based scale formulations for the two stage lot sizing and scheduling in process industries. J Oper Res Soc 63:1613–1630CrossRef
go back to reference Camargo VCB, Toledo FMB, Almada-Lobo B (2014) HOPS—hamming-oriented partition search for production planning in the spinning industry. Eur J Oper Res 234(1):266–277CrossRef Camargo VCB, Toledo FMB, Almada-Lobo B (2014) HOPS—hamming-oriented partition search for production planning in the spinning industry. Eur J Oper Res 234(1):266–277CrossRef
go back to reference Copil K (2016) Capacitated lot-sizing and scheduling with scarce setup resources. Books on Demand, Norderstedt Copil K (2016) Capacitated lot-sizing and scheduling with scarce setup resources. Books on Demand, Norderstedt
go back to reference Copil K, Wörbelauer M, Meyr H, Tempelmeier H (2017) Simultaneous lotsizing and scheduling problems: a classification and review of models. OR Spectr 39(1):1–64CrossRef Copil K, Wörbelauer M, Meyr H, Tempelmeier H (2017) Simultaneous lotsizing and scheduling problems: a classification and review of models. OR Spectr 39(1):1–64CrossRef
go back to reference Dastidar SG, Nagi R (2005) Scheduling injection molding operations with multiple resource constraints and sequence dependent setup times and costs. Comput Oper Res 32(11):2987–3005CrossRef Dastidar SG, Nagi R (2005) Scheduling injection molding operations with multiple resource constraints and sequence dependent setup times and costs. Comput Oper Res 32(11):2987–3005CrossRef
go back to reference Drexl A, Haase K (1995) Proportional lotsizing and scheduling. Int J Prod Econ 40(1):73–87CrossRef Drexl A, Haase K (1995) Proportional lotsizing and scheduling. Int J Prod Econ 40(1):73–87CrossRef
go back to reference Eppen GD, Martin RK (1987) Solving multi-item capacitated lot-sizing problems using variable redefinition. Oper Res 35(6):832–848CrossRef Eppen GD, Martin RK (1987) Solving multi-item capacitated lot-sizing problems using variable redefinition. Oper Res 35(6):832–848CrossRef
go back to reference Ferreira D, Morabito Neto R, Rangel S (2009) Solution approaches for the soft drink integrated production lot sizing and scheduling problem. Eur J Oper Res 196(2):697–706CrossRef Ferreira D, Morabito Neto R, Rangel S (2009) Solution approaches for the soft drink integrated production lot sizing and scheduling problem. Eur J Oper Res 196(2):697–706CrossRef
go back to reference Ferreira D, Morabito Neto R, Rangel S (2010) Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Comput Oper Res 37(4):684–691CrossRef Ferreira D, Morabito Neto R, Rangel S (2010) Relax and fix heuristics to solve one-stage one-machine lot-scheduling models for small-scale soft drink plants. Comput Oper Res 37(4):684–691CrossRef
go back to reference Ferreira D, Clark AR, Almada-Lobo B, Morabito Neto R (2012) Single-stage formulations for synchronised two-stage lot sizing and scheduling in soft drink production. Int J Prod Econ 136(2):255–265CrossRef Ferreira D, Clark AR, Almada-Lobo B, Morabito Neto R (2012) Single-stage formulations for synchronised two-stage lot sizing and scheduling in soft drink production. Int J Prod Econ 136(2):255–265CrossRef
go back to reference Figueira G, Santos MO, Almada-Lobo B (2013) A hybrid VNS approach for the short-term production planning and scheduling: a case study in the pulp and paper industry. Comput Oper Res 40(7):1804–1818CrossRef Figueira G, Santos MO, Almada-Lobo B (2013) A hybrid VNS approach for the short-term production planning and scheduling: a case study in the pulp and paper industry. Comput Oper Res 40(7):1804–1818CrossRef
go back to reference Fleischmann B (1990) The discrete lot-sizing and scheduling problem. Eur J Oper Res 44(3):337–348CrossRef Fleischmann B (1990) The discrete lot-sizing and scheduling problem. Eur J Oper Res 44(3):337–348CrossRef
go back to reference Fleischmann B, Meyr H (1997) The general lotsizing and scheduling problem. OR Spectr 19(1):11–21CrossRef Fleischmann B, Meyr H (1997) The general lotsizing and scheduling problem. OR Spectr 19(1):11–21CrossRef
go back to reference Furlan MM, Almada-Lobo B, Santos MO, Morabito Neto R (2015) Unequal individual genetic algorithm with intelligent diversification for the lot-scheduling problem in integrated mills using multiple-paper machines. Comput Oper Res 59:33–50CrossRef Furlan MM, Almada-Lobo B, Santos MO, Morabito Neto R (2015) Unequal individual genetic algorithm with intelligent diversification for the lot-scheduling problem in integrated mills using multiple-paper machines. Comput Oper Res 59:33–50CrossRef
go back to reference Geunes J (2003) Solving large-scale requirements planning problems with component substitution options. Comput Ind Eng 44(3):475–491CrossRef Geunes J (2003) Solving large-scale requirements planning problems with component substitution options. Comput Ind Eng 44(3):475–491CrossRef
go back to reference Göthe-Lundgren M, Lundgren JT, Persson JA (2002) An optimization model for refinery production scheduling. Int J Prod Econ 78(3):255–270CrossRef Göthe-Lundgren M, Lundgren JT, Persson JA (2002) An optimization model for refinery production scheduling. Int J Prod Econ 78(3):255–270CrossRef
go back to reference Haase K (1996) Capacitated lot-sizing with sequence dependent setup costs. OR Spectr 18(1):51–59CrossRef Haase K (1996) Capacitated lot-sizing with sequence dependent setup costs. OR Spectr 18(1):51–59CrossRef
go back to reference Hartmann S, Briskorn D (2010) A survey of variants and extensions of the resource-constrained project scheduling problem. Eur J Oper Res 207(1):1–14CrossRef Hartmann S, Briskorn D (2010) A survey of variants and extensions of the resource-constrained project scheduling problem. Eur J Oper Res 207(1):1–14CrossRef
go back to reference Jans R, Degraeve Z (2004) An industrial extension of the discrete lot-sizing and scheduling problem. IIE Trans 36(1):47–58CrossRef Jans R, Degraeve Z (2004) An industrial extension of the discrete lot-sizing and scheduling problem. IIE Trans 36(1):47–58CrossRef
go back to reference Karmarkar US, Schrage L (1985) The deterministic dynamic product cycling problem. Oper Res 33(2):326–345CrossRef Karmarkar US, Schrage L (1985) The deterministic dynamic product cycling problem. Oper Res 33(2):326–345CrossRef
go back to reference Kimms A, Drexl A (1998) Proportional lot sizing and scheduling: some extensions. Networks 32(2):85–101CrossRef Kimms A, Drexl A (1998) Proportional lot sizing and scheduling: some extensions. Networks 32(2):85–101CrossRef
go back to reference Koçlar A, Süral H (2005) A note on “The general lot sizing and scheduling problem”. OR Spectr 27(1):145–146CrossRef Koçlar A, Süral H (2005) A note on “The general lot sizing and scheduling problem”. OR Spectr 27(1):145–146CrossRef
go back to reference Lasdon L, Terjung RC (1971) An efficient algorithm for multi-item scheduling. Oper Res 19(4):946–969CrossRef Lasdon L, Terjung RC (1971) An efficient algorithm for multi-item scheduling. Oper Res 19(4):946–969CrossRef
go back to reference Mac Cawley AF (2014) The international wine supply chain: challenges from bottling to the glass. Ph.D. thesis, Georgia Institute of Technology Mac Cawley AF (2014) The international wine supply chain: challenges from bottling to the glass. Ph.D. thesis, Georgia Institute of Technology
go back to reference Maldonado M, Rangel S, Ferreira D (2014) A study of different subsequence elimination strategies for the soft drink production planning. J Appl Res Technol 12(4):631–641CrossRef Maldonado M, Rangel S, Ferreira D (2014) A study of different subsequence elimination strategies for the soft drink production planning. J Appl Res Technol 12(4):631–641CrossRef
go back to reference Meyr H (2002) Simultaneous lotsizing and scheduling on parallel machines. Eur J Oper Res 139(2):277–292CrossRef Meyr H (2002) Simultaneous lotsizing and scheduling on parallel machines. Eur J Oper Res 139(2):277–292CrossRef
go back to reference Meyr H (2004) Simultane Losgrößen- und Reihenfolgeplanung bei mehrstufiger kontinuierlicher Fertigung. Zeitschrift für Betriebswirtschaft 74(6):585–610 Meyr H (2004) Simultane Losgrößen- und Reihenfolgeplanung bei mehrstufiger kontinuierlicher Fertigung. Zeitschrift für Betriebswirtschaft 74(6):585–610
go back to reference Meyr H, Mann M (2013) A decomposition approach for the general lotsizing and scheduling problem for parallel production lines. Eur J Oper Res 229(3):718–731CrossRef Meyr H, Mann M (2013) A decomposition approach for the general lotsizing and scheduling problem for parallel production lines. Eur J Oper Res 229(3):718–731CrossRef
go back to reference Persson JA, Göthe-Lundgren M, Lundgren JT, Gendron B (2004) A tabu search heuristic for scheduling the production processes at an oil refinery. Int J Prod Res 42(3):445–471CrossRef Persson JA, Göthe-Lundgren M, Lundgren JT, Gendron B (2004) A tabu search heuristic for scheduling the production processes at an oil refinery. Int J Prod Res 42(3):445–471CrossRef
go back to reference Santos MO, Almada-Lobo B (2012) Integrated pulp and paper mill planning and scheduling. Comput Ind Eng 63(1):1–12CrossRef Santos MO, Almada-Lobo B (2012) Integrated pulp and paper mill planning and scheduling. Comput Ind Eng 63(1):1–12CrossRef
go back to reference Seeanner F (2013) Multi-stage simultaneous lot-sizing and scheduling—planning of flow lines with shifting bottlenecks. Produktion und Logistik. Springer Gabler, WiesbadenCrossRef Seeanner F (2013) Multi-stage simultaneous lot-sizing and scheduling—planning of flow lines with shifting bottlenecks. Produktion und Logistik. Springer Gabler, WiesbadenCrossRef
go back to reference Seeanner F, Meyr H (2013) Multi-stage simultaneous lot-sizing and scheduling for flow line production. OR Spectr 35(1):33–73CrossRef Seeanner F, Meyr H (2013) Multi-stage simultaneous lot-sizing and scheduling for flow line production. OR Spectr 35(1):33–73CrossRef
go back to reference Seeanner F, Almada-Lobo B, Meyr H (2013) Combining the principles of variable neighborhood decomposition search and the fix & optimize heuristic to solve multi-level lot-sizing and scheduling problems. Comput Oper Res 40(1):303–317CrossRef Seeanner F, Almada-Lobo B, Meyr H (2013) Combining the principles of variable neighborhood decomposition search and the fix & optimize heuristic to solve multi-level lot-sizing and scheduling problems. Comput Oper Res 40(1):303–317CrossRef
go back to reference Suerie C (2005) Time continuity in discrete time models: new approaches for production planning in process industries. Lecture notes in economics and mathematical systems. Springer, Berlin Suerie C (2005) Time continuity in discrete time models: new approaches for production planning in process industries. Lecture notes in economics and mathematical systems. Springer, Berlin
go back to reference Tempelmeier H, Buschkühl L (2008) Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource. Int J Prod Econ 113(1):401–412CrossRef Tempelmeier H, Buschkühl L (2008) Dynamic multi-machine lotsizing and sequencing with simultaneous scheduling of a common setup resource. Int J Prod Econ 113(1):401–412CrossRef
go back to reference Tempelmeier H, Copil K (2016) Capacitated lot sizing with parallel machines, sequence-dependent setups and a common setup operator. OR Spectr 38(4):819–847CrossRef Tempelmeier H, Copil K (2016) Capacitated lot sizing with parallel machines, sequence-dependent setups and a common setup operator. OR Spectr 38(4):819–847CrossRef
go back to reference Toledo CFM, Arantes MdS, de Oliveira RRR, Almada-Lobo B (2013) Glass container production scheduling through hybrid multi-population based evolutionary algorithm. Appl Soft Comput 13(3):1352–1364CrossRef Toledo CFM, Arantes MdS, de Oliveira RRR, Almada-Lobo B (2013) Glass container production scheduling through hybrid multi-population based evolutionary algorithm. Appl Soft Comput 13(3):1352–1364CrossRef
Metadata
Title
Simultaneous lotsizing and scheduling considering secondary resources: a general model, literature review and classification
Authors
Martin Wörbelauer
Herbert Meyr
Bernardo Almada-Lobo
Publication date
09-11-2018
Publisher
Springer Berlin Heidelberg
Published in
OR Spectrum / Issue 1/2019
Print ISSN: 0171-6468
Electronic ISSN: 1436-6304
DOI
https://doi.org/10.1007/s00291-018-0536-0

Other articles of this Issue 1/2019

OR Spectrum 1/2019 Go to the issue