Management of High-Volume Clashes During Clash Detection

verfasst von : Sagar Malsane, M. J. Merin, G. J. Gokul, P. Nithin Dev, Smitha Treesa Babu

Erschienen in: Mathematical, Computational Intelligence and Engineering Approaches for Tourism, Agriculture and Healthcare

Verlag: Springer Singapore

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Typically in construction projects, design drawings are usually developed by different trade teams like architectural, structural, and mechanical, electrical, and plumbing and fire-fighting (MEPF). Hence, when these drawings are integrated it results in clashes between various trade-specific components. Conventionally clashes are found by overlapping the drawings and resolved by manually coordinating between the different departments which is a chaotic and time-consuming process. The efficiency of this process is low and can even lead to conflicts between different departments. These clashes if not resolved before the construction lead to reworks on-site which results in time and cost overruns. This problem can be effectively overcome by using Building Information Modelling’s (BIM) Clash Detection (CD) application, which identifies clashes from the 3D building models by integrating them. A Clash detection test usually identifies a large number of relevant and non-relevant clashes. Amongst these, the relevant clashes need to be resolved before construction to avoid rework and idle time during construction and the non-relevant clashes can be dealt with in site during construction. For resolving the relevant clashes, they have to be notified to different departments. Due to their large volume and multiple stakeholders involved, many challenges are faced by BIM manager and hence scientific management of clashes is crucial for better segregation and streamlining. In this study, a method of codifying clashes is presented for effective and efficient management of clashes and to eradicate issues associated with it. The developed method was applied to a sample project to validate.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Literatur
1.
Zurück zum Zitat Eastman, C., Teicholz, P., Sacks, R., Liston, K.: BIM Handbook—A guide to Building Information Modeling, 2nd edn. John Wiley & Sons. Inc., London (2011) Eastman, C., Teicholz, P., Sacks, R., Liston, K.: BIM Handbook—A guide to Building Information Modeling, 2nd edn. John Wiley & Sons. Inc., London (2011)
2.
Zurück zum Zitat Kensek, K.: Building Information Modeling. Routledge, New York (2014)CrossRef Kensek, K.: Building Information Modeling. Routledge, New York (2014)CrossRef
3.
Zurück zum Zitat Akponeware, A., Adamu, Z.: Clash detection or clash avoidance? An investigation into coordination problems in 3D BIM. MDPI, Buildings 75(7), 1–28 (2017) Akponeware, A., Adamu, Z.: Clash detection or clash avoidance? An investigation into coordination problems in 3D BIM. MDPI, Buildings 75(7), 1–28 (2017)
4.
Zurück zum Zitat NITI Task Force: A Report on Project and Program Management. NITI Ayog, India (2019) NITI Task Force: A Report on Project and Program Management. NITI Ayog, India (2019)
5.
Zurück zum Zitat Azhar, S.: Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry. Leadersh. Manage. Eng. 11(3), 241–252 (2011)CrossRef Azhar, S.: Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry. Leadersh. Manage. Eng. 11(3), 241–252 (2011)CrossRef
6.
Zurück zum Zitat Roy, D., Malsane, S., Samanta, P.: Identification of critical challenges for adoption of integrated project delivery. Lean Constr. J. 01(2018), 01–15 (2018) Roy, D., Malsane, S., Samanta, P.: Identification of critical challenges for adoption of integrated project delivery. Lean Constr. J. 01(2018), 01–15 (2018)
7.
Zurück zum Zitat Hjelseth, E.: Classification of BIM-based model checking concepts. J. Inf. Technol. Constr. 21, 354–370 (2016) Hjelseth, E.: Classification of BIM-based model checking concepts. J. Inf. Technol. Constr. 21, 354–370 (2016)
8.
Zurück zum Zitat Sidiq, A., Thamilselvi, P.: Study on implementation of clash detection tool in housing project using BIM. Int. J. Adv. Res. Sci. Eng. 7(6), 215–225 (2018) Sidiq, A., Thamilselvi, P.: Study on implementation of clash detection tool in housing project using BIM. Int. J. Adv. Res. Sci. Eng. 7(6), 215–225 (2018)
9.
Zurück zum Zitat Bockstael, D., Issa, M.: A methodology for contractor clash detection using building information modelling on commercial construction projects. J. Inf. Technol. Constr. 21, 233–249 (2015) Bockstael, D., Issa, M.: A methodology for contractor clash detection using building information modelling on commercial construction projects. J. Inf. Technol. Constr. 21, 233–249 (2015)
10.
Zurück zum Zitat Gijezen, S., Hartmann, T., Buursema, N. and Hendriks, H.: Organizing 3d building information models with the help of work breakdown structures to improve the clash detection process. Visco-Centre for Visualization and Simulation in Construction, Working paper, pp. 1–18 (2009) Gijezen, S., Hartmann, T., Buursema, N. and Hendriks, H.: Organizing 3d building information models with the help of work breakdown structures to improve the clash detection process. Visco-Centre for Visualization and Simulation in Construction, Working paper, pp. 1–18 (2009)
11.
Zurück zum Zitat Raut, S., Valunjkar, S.: Improve the productivity of building project using building information modelling (BIM) based 4d simulation model. Int. J. Res. Appl. Sci. Eng. Technol. 5(4), 53–61 (2017)CrossRef Raut, S., Valunjkar, S.: Improve the productivity of building project using building information modelling (BIM) based 4d simulation model. Int. J. Res. Appl. Sci. Eng. Technol. 5(4), 53–61 (2017)CrossRef
12.
Zurück zum Zitat Hu, Y., Lacouture, D.: Clash relevance prediction in BIM-based design coordination using Bayesin statistics. In: Construction Research Congress, ASCE, pp. 649–658 (2018) Hu, Y., Lacouture, D.: Clash relevance prediction in BIM-based design coordination using Bayesin statistics. In: Construction Research Congress, ASCE, pp. 649–658 (2018)
13.
Zurück zum Zitat Bhagwat, P., Shinde, R.: Clash detection-a new tool in project management. Int. J. Sci. Res. Sci. Eng. Technol. 2(4), 193–197 (2016) Bhagwat, P., Shinde, R.: Clash detection-a new tool in project management. Int. J. Sci. Res. Sci. Eng. Technol. 2(4), 193–197 (2016)
14.
Zurück zum Zitat Shyamkant, B., Patil, A., Pataskar, S.: Cost and time optimization for construction of residential building by clash detection in building information model (BIM). Int. Res. J. Eng. Technol. 4(1), 550–553 (2017) Shyamkant, B., Patil, A., Pataskar, S.: Cost and time optimization for construction of residential building by clash detection in building information model (BIM). Int. Res. J. Eng. Technol. 4(1), 550–553 (2017)
15.
Zurück zum Zitat Moreau, S.: Navisworks manage—empowering clash detection. Autodesk University 2015, 1–20 (2015) Moreau, S.: Navisworks manage—empowering clash detection. Autodesk University 2015, 1–20 (2015)
16.
Zurück zum Zitat Guangbin, W., Wei, L., Xuru, D.: Exploring the High-efficiency clash detection between architecture and structure. In: International Conference on Information Management and Engineering 2011, vol. 52(85) (2011) Guangbin, W., Wei, L., Xuru, D.: Exploring the High-efficiency clash detection between architecture and structure. In: International Conference on Information Management and Engineering 2011, vol. 52(85) (2011)
17.
Zurück zum Zitat Abd, A., Khamees, A.: As built case studies for BIM as conflicts detection and documentation tool. Cogent Eng. 4, 1–11 (2017)CrossRef Abd, A., Khamees, A.: As built case studies for BIM as conflicts detection and documentation tool. Cogent Eng. 4, 1–11 (2017)CrossRef
Metadaten
Titel
Management of High-Volume Clashes During Clash Detection
verfasst von
Sagar Malsane
M. J. Merin
G. J. Gokul
P. Nithin Dev
Smitha Treesa Babu
Copyright-Jahr
2022
Verlag
Springer Singapore
DOI
https://doi.org/10.1007/978-981-16-3807-7_23

    Marktübersichten

    Die im Laufe eines Jahres in der „adhäsion“ veröffentlichten Marktübersichten helfen Anwendern verschiedenster Branchen, sich einen gezielten Überblick über Lieferantenangebote zu verschaffen.