Construction Programme Failure and the Impact on Waste, Resource Efficiency, and Natural Capital in Construction Project Environments

verfasst von : Neil Pickavance, Andrew Ross, Damian Fearon

Erschienen in: Sustainable Ecological Engineering Design

Verlag: Springer International Publishing

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Delayed and disrupted construction projects contribute poor sustainability in construction project environments. UK construction documents an extensive history of project delay and disruption, with contracting organisations operating in environments with a prevalence of excessive sub-letting, fragmentation, poor integration of sub-contractors, build strategy dislocation, contractual-adversarial relationships, and poor adoption of project planning frameworks.
This investigation reviews the extent and impact of individual and team behaviours and cultures within a contracting organisation project and the influences on the success of Critical Path Method (CPM) project planning and scheduling. CPM remains the standard method of project planning and scheduling in the construction industry, despite newer systems such as Lean Construction, Last Planner® System, Agile Project Management, and PRINCE2.
Exploratory qualitative data was collected through a purposive sample of six semi-structured interviews with UK construction management personnel on a sample case study project. Experienced project managers and project planning staff from contracting and sub-contracting organisations were consulted on project planning, scheduling and programme development, co-ordination, integration, procedures, methods, techniques, training, and development.
Results identify CPM planning operating in unstructured environments characterised by poor operating and application protocols, and poor understanding and ad hoc engagement by project teams. Poor leadership and facilitation of programme development by senior project management could be associated with later project failure. It is concluded that fundamental problems with basic project planning and scheduling undermine sustainability in construction due to late completions.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Ammar, M. A. (2012). LOB and CPMP integrated method for scheduling repetitive projects. Journal of Construction Engineering and Management, 139(1), 44–50.CrossRef Ammar, M. A. (2012). LOB and CPMP integrated method for scheduling repetitive projects. Journal of Construction Engineering and Management, 139(1), 44–50.CrossRef
Zurück zum Zitat Association of Project Management (Ed.). (2012). APM body of knowledge (6th ed.). Princes Risborough, Buckinghamshire: Association of Project Management. Association of Project Management (Ed.). (2012). APM body of knowledge (6th ed.). Princes Risborough, Buckinghamshire: Association of Project Management.
Zurück zum Zitat Aquilano, N. J., & Smith, D. E. (1980). A formal set of algorithms for project scheduling with critical path scheduling/material requirements planning. Journal of Operations Management, 1(2), 57–67.CrossRef Aquilano, N. J., & Smith, D. E. (1980). A formal set of algorithms for project scheduling with critical path scheduling/material requirements planning. Journal of Operations Management, 1(2), 57–67.CrossRef
Zurück zum Zitat Ballard, H.G., 2000. The last planner system of production control. Doctoral Dissertation, University of Birmingham. Ballard, H.G., 2000. The last planner system of production control. Doctoral Dissertation, University of Birmingham.
Zurück zum Zitat Bryman, A. (2015). Social research methods. Oxford: Oxford University Press. Bryman, A. (2015). Social research methods. Oxford: Oxford University Press.
Zurück zum Zitat Chartered Institute of Building (CIOB). (2008). A research on managing the risk of delayed completion in the 21st century. Ascot: CIOB. Chartered Institute of Building (CIOB). (2008). A research on managing the risk of delayed completion in the 21st century. Ascot: CIOB.
Zurück zum Zitat CIOB. (2016). Code of practice for programme management in the built environment. Chichester: Wiley Blackwell. CIOB. (2016). Code of practice for programme management in the built environment. Chichester: Wiley Blackwell.
Zurück zum Zitat Corbin, J., & Strauss, A. (2008). Basics of qualitative research: Techniques and procedures for developing grounded theory. Los Angeles, CA: Sage.CrossRef Corbin, J., & Strauss, A. (2008). Basics of qualitative research: Techniques and procedures for developing grounded theory. Los Angeles, CA: Sage.CrossRef
Zurück zum Zitat Daniel, E.I., Pasquire, C., & Dickens, G., (2014, September). Social perspective of planning in construction: The UK experience. In Proceedings of the 30th Annual Association of Researchers in Construction (ARCOM) Conference (pp. 1–3). Daniel, E.I., Pasquire, C., & Dickens, G., (2014, September). Social perspective of planning in construction: The UK experience. In Proceedings of the 30th Annual Association of Researchers in Construction (ARCOM) Conference (pp. 1–3).
Zurück zum Zitat Egan, J. (1998). Rethinking construction. London: Department of Environment, Transport and the Region. Egan, J. (1998). Rethinking construction. London: Department of Environment, Transport and the Region.
Zurück zum Zitat Fondahl, J. W. (1962). A non-computer approach to the critical path method for the construction industry. Stanford, CA: Department of Civil Engineering, Stanford University. Fondahl, J. W. (1962). A non-computer approach to the critical path method for the construction industry. Stanford, CA: Department of Civil Engineering, Stanford University.
Zurück zum Zitat Gibson, G. E., Jr., Wang, Y. R., Cho, C. S., & Pappas, M. P. (2006). What is preproject planning, anyway? Journal of Management in Engineering, 22(1), 35–42.CrossRef Gibson, G. E., Jr., Wang, Y. R., Cho, C. S., & Pappas, M. P. (2006). What is preproject planning, anyway? Journal of Management in Engineering, 22(1), 35–42.CrossRef
Zurück zum Zitat Kelley, J. E., Jr. (1961). Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296–320.MathSciNetCrossRef Kelley, J. E., Jr. (1961). Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296–320.MathSciNetCrossRef
Zurück zum Zitat Kog, Y. C., Chua, D. K. H., Loh, P. K., & Jaselskis, E. J. (1999). Key determinants for construction schedule performance. International Journal of Project Management, 17(6), 351–359.CrossRef Kog, Y. C., Chua, D. K. H., Loh, P. K., & Jaselskis, E. J. (1999). Key determinants for construction schedule performance. International Journal of Project Management, 17(6), 351–359.CrossRef
Zurück zum Zitat Latham, M. (1994). Constructing the team. London: HMSO. Latham, M. (1994). Constructing the team. London: HMSO.
Zurück zum Zitat Laufer, A., & Tucker, R. L. (1987). Is construction project planning really doing its job? A critical examination of focus, role and process. Construction Management and Economics, 5(3), 243–266.CrossRef Laufer, A., & Tucker, R. L. (1987). Is construction project planning really doing its job? A critical examination of focus, role and process. Construction Management and Economics, 5(3), 243–266.CrossRef
Zurück zum Zitat Lester, A. (2006). Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards. Amsterdam: Elsevier. Lester, A. (2006). Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards. Amsterdam: Elsevier.
Zurück zum Zitat Livengood, J.C. (2016). Use of project schedules and the critical path method in claims. In Construction contract claims, changes, and dispute resolution (pp. 175–200). Livengood, J.C. (2016). Use of project schedules and the critical path method in claims. In Construction contract claims, changes, and dispute resolution (pp. 175–200).
Zurück zum Zitat Tommelein, I. D., Riley, D. R., & Howell, G. A. (1999). Parade game: Impact of work flow variability on trade performance. Journal of Construction Engineering and Management, 125(5), 304–310.CrossRef Tommelein, I. D., Riley, D. R., & Howell, G. A. (1999). Parade game: Impact of work flow variability on trade performance. Journal of Construction Engineering and Management, 125(5), 304–310.CrossRef
Zurück zum Zitat Winch, G. M., & Kelsey, J. (2005). What do construction project planners do? International Journal of Project Management, 23(2), 141–149.CrossRef Winch, G. M., & Kelsey, J. (2005). What do construction project planners do? International Journal of Project Management, 23(2), 141–149.CrossRef
Metadaten
Titel
Construction Programme Failure and the Impact on Waste, Resource Efficiency, and Natural Capital in Construction Project Environments
verfasst von
Neil Pickavance
Andrew Ross
Damian Fearon
Copyright-Jahr
2020
DOI
https://doi.org/10.1007/978-3-030-44381-8_21