Effective Management of Hazardous Asbestos Waste Within a Confined Water Main Pipeline Construction Project: Multiple Case Study Review

verfasst von : Paul Collins, John P. Spillane

Erschienen in: Sustainable Ecological Engineering Design

Verlag: Springer International Publishing

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

As urban sprawl continues to put pressure on cities across the globe, so too is the need to service those who live and work within these regions. The need to provide fresh, clean drinking water to each person is becoming increasing difficult and somewhat unsustainable. In the context of Ireland, this is no different, particularly with ageing and leaking services. To counteract such issues, there is a need to replace old and often hazardous asbestos water main pipelines with more durable solutions. However, in doing so, the process unearths particularly hazardous material to those whom have the task of replacing it. There is an ever-growing need for advanced methods of materials management and space scheduling on confined construction sites with a considerable gap in literature accounting for the management and removal of hazardous waste. Therefore, the aim of this study is to investigate the effective management of such hazardous waste, within what is invariably a confined construction site environment. To achieve this aim, three case studies are identified, all of which involve the removal of old asbestos water main, in a confined city centre environment. Three individuals on each case study are interviewed, using a semi-structured approach, to investigate how they effectively manage and mitigate the risks associated with the decommissioning, packaging and removal of hazardous asbestos waste from each of their respective projects. The findings indicate that, in order of importance, Space Scheduling, Critical Space Analysis, and Supply Chain Management are critical in the safe identification, decommissioning, excavation, extraction, packaging and ultimate removal and disposal of hazardous asbestos waste water main. This research is conducted with the ultimate viewpoint of increasing the efficiency of pipeline construction where hazardous waste is present, reducing costs on-site and, ultimately, improving the health and safety, both of those working on-site and also those in the vicinity of the removal of this hazardous waste.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Ala-Risku, T., & Kärkkäinen, M. (2004). Material delivery problems in construction projects: A possible solution. International Journal of Production Economics, 104(1), 19–29.CrossRef Ala-Risku, T., & Kärkkäinen, M. (2004). Material delivery problems in construction projects: A possible solution. International Journal of Production Economics, 104(1), 19–29.CrossRef
Zurück zum Zitat Begum, R. A., Siwar, C., Pereira, J. J., & Jaafar, A. H. (2006). A benefit–cost analysis on the economic feasibility of construction waste minimisation: The case of Malaysia. Resources, Conservation and Recycling, 48(1), 86–98.CrossRef Begum, R. A., Siwar, C., Pereira, J. J., & Jaafar, A. H. (2006). A benefit–cost analysis on the economic feasibility of construction waste minimisation: The case of Malaysia. Resources, Conservation and Recycling, 48(1), 86–98.CrossRef
Zurück zum Zitat Cheng, C. P., & Kumar, S. (2015). A BIM-based framework for material logistics planning. 23rd International Group for Lean Construction Conference (IGLC 2015), held at Perth, Australia, 28–31 July. Cheng, C. P., & Kumar, S. (2015). A BIM-based framework for material logistics planning. 23rd International Group for Lean Construction Conference (IGLC 2015), held at Perth, Australia, 28–31 July.
Zurück zum Zitat Choo, H. J., & Tommelein, I. D. (1999). Space scheduling using flow analysis. 7th International Group for Lean Construction Conference (IGLC 1999), held at University of California, Berkeley, California, USA, 26–28 July. Choo, H. J., & Tommelein, I. D. (1999). Space scheduling using flow analysis. 7th International Group for Lean Construction Conference (IGLC 1999), held at University of California, Berkeley, California, USA, 26–28 July.
Zurück zum Zitat Dawood, N., & Mallasi, Z. (2006). Construction workspace planning: Assignment and analysis utilizing 4D visualization technologies. Computer-Aided Civil and Infrastructure Engineering, 21(7), 498–513.CrossRef Dawood, N., & Mallasi, Z. (2006). Construction workspace planning: Assignment and analysis utilizing 4D visualization technologies. Computer-Aided Civil and Infrastructure Engineering, 21(7), 498–513.CrossRef
Zurück zum Zitat Fernie, S., & Thorpe, A. (2007). Exploring change in construction: supply chain management. Engineering Construction and Architectural Management, 14(4), 319–333.CrossRef Fernie, S., & Thorpe, A. (2007). Exploring change in construction: supply chain management. Engineering Construction and Architectural Management, 14(4), 319–333.CrossRef
Zurück zum Zitat Li, J., Dong, Q., Yu, K., & Liu, L. (2014). Asbestos and asbestos waste management in the Asian-Pacific region: Trends, challenges and solutions. Journal of Cleaner Production, 81, 218–226.CrossRef Li, J., Dong, Q., Yu, K., & Liu, L. (2014). Asbestos and asbestos waste management in the Asian-Pacific region: Trends, challenges and solutions. Journal of Cleaner Production, 81, 218–226.CrossRef
Zurück zum Zitat Navon, R., & Berkovich, O. (2006). An automated model for materials management and control. Construction Management and Economics, 24(6), 635–646.CrossRef Navon, R., & Berkovich, O. (2006). An automated model for materials management and control. Construction Management and Economics, 24(6), 635–646.CrossRef
Zurück zum Zitat North, S., & Winch, G. M. (2002). VIRCON: A proposal for critical space analysis in construction planning. 4th European Conference on Product and Process Modelling in the Building and Related Industries (ECPPM). pp. 359–364. North, S., & Winch, G. M. (2002). VIRCON: A proposal for critical space analysis in construction planning. 4th European Conference on Product and Process Modelling in the Building and Related Industries (ECPPM). pp. 359–364.
Zurück zum Zitat Patel, K. V., & Vyas, C. M. (2011). Construction materials management on project sites. National conference on recent trends in engineering & technology, held at Anand, Gujarat, India, 13–14 May, pp. 1–5. Patel, K. V., & Vyas, C. M. (2011). Construction materials management on project sites. National conference on recent trends in engineering & technology, held at Anand, Gujarat, India, 13–14 May, pp. 1–5.
Zurück zum Zitat Spillane, J. P., & Oyedele, L. O. (2017). Effective material logistics in urban construction sites: a structural equation model. Construction Innovation, 17(4), 406–428.CrossRef Spillane, J. P., & Oyedele, L. O. (2017). Effective material logistics in urban construction sites: a structural equation model. Construction Innovation, 17(4), 406–428.CrossRef
Zurück zum Zitat Spillane, J. P., Oyedele, L. O., von Meding, J., Konanahalli, A., Babatunde, J. E., & Iyabo, T. K. (2011). Challenges of UK/Irish contractors regarding material management and logistics in confined site construction. International Journal of Construction Supply Chain Management, 1(1), 25–42.CrossRef Spillane, J. P., Oyedele, L. O., von Meding, J., Konanahalli, A., Babatunde, J. E., & Iyabo, T. K. (2011). Challenges of UK/Irish contractors regarding material management and logistics in confined site construction. International Journal of Construction Supply Chain Management, 1(1), 25–42.CrossRef
Zurück zum Zitat Spillane, J. P., Oyedele, L. O., Von Meding, J. K., & Konanahalli, A. (2010). Material management in confined construction sites. The Construction, Building and Real Estate Research Conference of the Royal Institution of Chartered Surveyors (RICS), held at Dauphine Université, Paris, 2–3 September. Spillane, J. P., Oyedele, L. O., Von Meding, J. K., & Konanahalli, A. (2010). Material management in confined construction sites. The Construction, Building and Real Estate Research Conference of the Royal Institution of Chartered Surveyors (RICS), held at Dauphine Université, Paris, 2–3 September.
Zurück zum Zitat Thomas, H. R., Riley, D. R., & Messner, J. I. (2005). Fundamental principles of site material management. Journal of Construction Engineering and Management, 131(7), 808–815.CrossRef Thomas, H. R., Riley, D. R., & Messner, J. I. (2005). Fundamental principles of site material management. Journal of Construction Engineering and Management, 131(7), 808–815.CrossRef
Zurück zum Zitat Tommelein, I. D., & Zouein, P. P. (1993). Space scheduling for construction progress planning and control. Automation and Robotics in Construction, 1993, 415–422. Tommelein, I. D., & Zouein, P. P. (1993). Space scheduling for construction progress planning and control. Automation and Robotics in Construction, 1993, 415–422.
Zurück zum Zitat Vrijhoef, R., & Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing and Supply Management, 6(3), 169–178.CrossRef Vrijhoef, R., & Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing and Supply Management, 6(3), 169–178.CrossRef
Zurück zum Zitat Winch, G. M., & North, S. (2006). Critical space analysis. Journal of Construction Engineering and Management, 132(5), 473–481.CrossRef Winch, G. M., & North, S. (2006). Critical space analysis. Journal of Construction Engineering and Management, 132(5), 473–481.CrossRef
Zurück zum Zitat Zouein, P. P., & Tommelein, I. D. (2001). Improvement algorithm for limited space scheduling. Journal of Construction Engineering and Management, 127(2), 116–124.CrossRef Zouein, P. P., & Tommelein, I. D. (2001). Improvement algorithm for limited space scheduling. Journal of Construction Engineering and Management, 127(2), 116–124.CrossRef
Metadaten
Titel
Effective Management of Hazardous Asbestos Waste Within a Confined Water Main Pipeline Construction Project: Multiple Case Study Review
verfasst von
Paul Collins
John P. Spillane
Copyright-Jahr
2020
DOI
https://doi.org/10.1007/978-3-030-44381-8_20