A Heuristic Project Buffer Management Algorithm in the Scheduling Phase of a Renewable Energies Project

verfasst von : Shakib Zohrehvandi, Lucia Knapčíková

Erschienen in: 7th EAI International Conference on Management of Manufacturing Systems

Verlag: Springer International Publishing

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Project buffer management while preventing the project from swelling results in efficient and reliable scheduling in the project. This research introduces a heuristic project buffer management (HPBM) algorithm. The purpose of this research is to determine the project buffer size in the planning phase. Introducing a heuristic algorithm to determine the buffer size of a project and implementing the algorithm in the implementation of a renewable wind farm is one of the innovations of this research. The proposed algorithm has two phases. In the first phase, the necessary operations to prepare a schedule of project activities are determined and in the second phase, the size of the project buffer is specified. The proposed algorithm for data analysis as well as its performance evaluation is coded and executed in MATLAB software, and the inputs of this project have been used and compared in several models recently presented by researchers. The results showed that the algorithm used had better results than the proposed models.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
1.
Zurück zum Zitat Zwikael, O., & Globerson, S. (2004). Evaluating the quality of project planning: A model and field results. International Journal of Production Research, 42(8), 1545–1556.CrossRef Zwikael, O., & Globerson, S. (2004). Evaluating the quality of project planning: A model and field results. International Journal of Production Research, 42(8), 1545–1556.CrossRef
2.
Zurück zum Zitat Vanhoucke, M. (2016). Buffer management. In Integrated project management sourcebook (pp. 155–193). Springer.CrossRef Vanhoucke, M. (2016). Buffer management. In Integrated project management sourcebook (pp. 155–193). Springer.CrossRef
3.
Zurück zum Zitat Hall, N. G. (2015). Further research opportunities in project management. In Handbook on project management and scheduling (Vol. 2, pp. 945–970). Springer.CrossRef Hall, N. G. (2015). Further research opportunities in project management. In Handbook on project management and scheduling (Vol. 2, pp. 945–970). Springer.CrossRef
4.
Zurück zum Zitat Goldratt, E. M. (1997). Critical chain. North River Press. Goldratt, E. M. (1997). Critical chain. North River Press.
5.
Zurück zum Zitat Goldratt, E. M., & Cox, J. (1984). The goal: Excellence in manufacturing. North River Press. Goldratt, E. M., & Cox, J. (1984). The goal: Excellence in manufacturing. North River Press.
6.
Zurück zum Zitat Newbold, R. C. (1998). Project management in the fast lane: Applying the theory of constraints. CRC Press.CrossRef Newbold, R. C. (1998). Project management in the fast lane: Applying the theory of constraints. CRC Press.CrossRef
7.
Zurück zum Zitat Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19(5), 559–577.CrossRef Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19(5), 559–577.CrossRef
8.
Zurück zum Zitat Leach, L. P. (2005). Critical chain project management (2nd ed.). Artech House. Leach, L. P. (2005). Critical chain project management (2nd ed.). Artech House.
9.
Zurück zum Zitat Tukel, O. I., Rom, W. O., & Eksioglu, S. D. (2006). An investigation of buffer sizing techniques in critical chain scheduling. European Journal of Operational Research, 172(2), 401–416.CrossRefMATH Tukel, O. I., Rom, W. O., & Eksioglu, S. D. (2006). An investigation of buffer sizing techniques in critical chain scheduling. European Journal of Operational Research, 172(2), 401–416.CrossRefMATH
10.
Zurück zum Zitat Woeppel, M. J. (2006). Projects in less time: A synopsis of critical chain. Pinnacle Strategies Pub. Woeppel, M. J. (2006). Projects in less time: A synopsis of critical chain. Pinnacle Strategies Pub.
11.
Zurück zum Zitat Rabbani, M., et al. (2007). A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept. European Journal of Operational Research, 176(2), 794–808.MathSciNetCrossRefMATH Rabbani, M., et al. (2007). A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept. European Journal of Operational Research, 176(2), 794–808.MathSciNetCrossRefMATH
12.
Zurück zum Zitat Blackstone, J. H., Cox, J. F., & Schleier, J. G. (2009). A tutorial on project management from a theory of constraints perspective. International Journal of Production Research, 47(24), 7029–7046.CrossRef Blackstone, J. H., Cox, J. F., & Schleier, J. G. (2009). A tutorial on project management from a theory of constraints perspective. International Journal of Production Research, 47(24), 7029–7046.CrossRef
14.
Zurück zum Zitat Bie, L., Cui, N., & Zhang, X. (2012). Buffer sizing approach with dependence assumption between activities in critical chain scheduling. International Journal of Production Research, 50(24), 7343–7356.CrossRef Bie, L., Cui, N., & Zhang, X. (2012). Buffer sizing approach with dependence assumption between activities in critical chain scheduling. International Journal of Production Research, 50(24), 7343–7356.CrossRef
15.
Zurück zum Zitat Zhang, J., Song, X., & Díaz, E. (2017). Critical chain project buffer sizing based on resource constraints. International Journal of Production Research, 55(3), 671–683.CrossRef Zhang, J., Song, X., & Díaz, E. (2017). Critical chain project buffer sizing based on resource constraints. International Journal of Production Research, 55(3), 671–683.CrossRef
16.
Zurück zum Zitat Sarkar, D., Jha, K. N., & Patel, S. (2018). Critical chain project management for a highway construction project with a focus on theory of constraints. International Journal of Construction Management, 21, 1–14. Sarkar, D., Jha, K. N., & Patel, S. (2018). Critical chain project management for a highway construction project with a focus on theory of constraints. International Journal of Construction Management, 21, 1–14.
20.
Zurück zum Zitat Poshdar, M., González, V. A., Raftery, G. M., Orozco, F., Romeo, J. S., & Forcael, E. (2016). A probabilistic-based method to determine optimum size of project buffer in construction schedules. Journal of Construction Engineering and Management, 142(10), 04016046.CrossRef Poshdar, M., González, V. A., Raftery, G. M., Orozco, F., Romeo, J. S., & Forcael, E. (2016). A probabilistic-based method to determine optimum size of project buffer in construction schedules. Journal of Construction Engineering and Management, 142(10), 04016046.CrossRef
21.
Zurück zum Zitat Bakry, I., Moselhi, O., & Zayed, T. (2016). Optimized scheduling and buffering of repetitive construction projects under uncertainty. Engineering, Construction and Architectural Management, 23(6), 782–800.CrossRef Bakry, I., Moselhi, O., & Zayed, T. (2016). Optimized scheduling and buffering of repetitive construction projects under uncertainty. Engineering, Construction and Architectural Management, 23(6), 782–800.CrossRef
22.
Zurück zum Zitat Zohrehvandi, S., & Soltani, R. (2022). Project scheduling and buffer management: A comprehensive review and future directions. Journal of Project Management, 7(2), 121–132.CrossRef Zohrehvandi, S., & Soltani, R. (2022). Project scheduling and buffer management: A comprehensive review and future directions. Journal of Project Management, 7(2), 121–132.CrossRef
24.
Zurück zum Zitat Alfieri, A., Matta, A., & Pastore, E. (2016). A column generation algorithm for the buffer allocation problem approximated by the time buffer concept. IFAC-PapersOnLine, 49(12), 739–744.CrossRefMATH Alfieri, A., Matta, A., & Pastore, E. (2016). A column generation algorithm for the buffer allocation problem approximated by the time buffer concept. IFAC-PapersOnLine, 49(12), 739–744.CrossRefMATH
25.
Zurück zum Zitat Hu, X., Demeulemeester, E., Cui, N., Wang, J., & Tian, W. (2017). Improved critical chain buffer management framework considering resource costs and schedule stability. Flexible Services and Manufacturing Journal, 29(2), 159–183.CrossRef Hu, X., Demeulemeester, E., Cui, N., Wang, J., & Tian, W. (2017). Improved critical chain buffer management framework considering resource costs and schedule stability. Flexible Services and Manufacturing Journal, 29(2), 159–183.CrossRef
26.
Zurück zum Zitat Ghoddousi, P., Ansari, R., & Makui, A. (2017). An improved robust buffer allocation method for the project scheduling problem. Engineering Optimization, 49(4), 718–731.MathSciNetCrossRef Ghoddousi, P., Ansari, R., & Makui, A. (2017). An improved robust buffer allocation method for the project scheduling problem. Engineering Optimization, 49(4), 718–731.MathSciNetCrossRef
29.
Zurück zum Zitat Ghoddousi, P., Ansari, R., & Makui, A. (2017). A risk-oriented buffer allocation model based on critical chain project management. KSCE Journal of Civil Engineering, 21(5), 1536–1548.CrossRef Ghoddousi, P., Ansari, R., & Makui, A. (2017). A risk-oriented buffer allocation model based on critical chain project management. KSCE Journal of Civil Engineering, 21(5), 1536–1548.CrossRef
30.
Zurück zum Zitat Martens, A., & Vanhoucke, M. (2017). A buffer control method for top-down project control. European Journal of Operational Research, 262(1), 274–286.CrossRefMATH Martens, A., & Vanhoucke, M. (2017). A buffer control method for top-down project control. European Journal of Operational Research, 262(1), 274–286.CrossRefMATH
31.
Zurück zum Zitat Zhang, J., Jia, S., & Diaz, E. (2018). Dynamic monitoring and control of a critical chain project based on phase buffer allocation. Journal of the Operational Research Society, 69, 1–12.CrossRef Zhang, J., Jia, S., & Diaz, E. (2018). Dynamic monitoring and control of a critical chain project based on phase buffer allocation. Journal of the Operational Research Society, 69, 1–12.CrossRef
32.
Zurück zum Zitat Zohrehvandi, S., Soltani, R., Lefebvre, D., Zohrehvandi, M., & Tenera, A. (2022). A two-stage machine learning-based heuristic algorithm for buffer management and project scheduling optimization. Communications in Computer and Information Science. Zohrehvandi, S., Soltani, R., Lefebvre, D., Zohrehvandi, M., & Tenera, A. (2022). A two-stage machine learning-based heuristic algorithm for buffer management and project scheduling optimization. Communications in Computer and Information Science.
Metadaten
Titel
A Heuristic Project Buffer Management Algorithm in the Scheduling Phase of a Renewable Energies Project
verfasst von
Shakib Zohrehvandi
Lucia Knapčíková
Copyright-Jahr
2023
DOI
https://doi.org/10.1007/978-3-031-22719-6_14

    Marktübersichten

    Die im Laufe eines Jahres in der „adhäsion“ veröffentlichten Marktübersichten helfen Anwendern verschiedenster Branchen, sich einen gezielten Überblick über Lieferantenangebote zu verschaffen.