Erschienen in: Global Journal of Flexible Systems Management 4/2017

01.09.2017 | Original Research

Critical Success Factors in Implementation of Urban Metro System on PPP: A Case Study of Hyderabad Metro

verfasst von: Rakesh Kulshreshtha, Anil Kumar, Ashish Tripathi, Dinesh Kumar Likhi

Erschienen in: Global Journal of Flexible Systems Management | Ausgabe 4/2017

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Rail-based metro system is crucial for supporting a city’s expansion and growth. However, urban metro projects being capital intensive with long gestation and pay back periods may not be financially viable but socially desirable. More and more cities in India are announcing metro projects committing huge budgetary resources to these projects at the cost of sectors such as health and education. Given the huge requirement of capital and possibility of attracting willing as well as capable private investors to undertake urban transport projects, promoting public–private partnerships (PPPs) could be a key priority. However, none of the metro projects launched during past 7 years in India have been planned on PPP framework. International experience in PPP metro and our own Delhi airport metro experience have demonstrated that many issues can influence the successful implementation of PPPs in such projects. In this context, outcome of Hyderabad metro is keenly watched as it is one of the largest metro rail projects built under a PPP framework anywhere in the world. The paper reviews the research conducted on critical success factors (CSFs) that are necessary for adopting PPP models in urban metros in Indian context. Eighteen CSFs identified through literature survey have been validated in a pilot study through structured questionnaire and grouped in seven macro-factors through hierarchical cluster analysis. A case study has been attempted using SAP–LAP framework to analyse the identified CSFs in real-life settings of the first two stages of Hyderabad metro project. Key players working on the project were interviewed during a field study to gather feedback on actions they took on factors critical to success. Observations and findings have been synthesised as learnings for future such projects.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Anhänge
Nur mit Berechtigung zugänglich
Fußnoten
1
Based on approved metro projects in Jaipur, Lucknow, Nagpur, Kochi, Ahmedabad, Bangalore, Mumbai, Hyderabad, Delhi, Kolkata, Chennai, Gurgaon, Pune and Noida up to 31 December 2016 (Source: MoUD).
 
2
Out of three stages of a metro project (pl refer “What Defines Success of a PPP Metro Project?” section), only contract success and implementation success up to the progress made till December, 2016 have been analysed as the ‘post-implementation success’ can be analysed only after commissioning of the project.
 
3
Up to the progress made till December, 2016.
 
Literatur
Zurück zum Zitat 12th FYP (2012–2017). Twelfth five year plan. In Five year plan documents, planning commission. Government of India, II (p. 341). 12th FYP (2012–2017). Twelfth five year plan. In Five year plan documents, planning commission. Government of India, II (p. 341).
Zurück zum Zitat Ahluwalia, I. J. (2014). Hyderabad metro shows the way. In I. Ahluwalia (Ed.), Transforming our cities: Post cards of change (p. 274). Noida: HarperCollins Publishers. Ahluwalia, I. J. (2014). Hyderabad metro shows the way. In I. Ahluwalia (Ed.), Transforming our cities: Post cards of change (p. 274). Noida: HarperCollins Publishers.
Zurück zum Zitat Chan, P. (2010). Critical success factors for PPPs in infrastructure development: Chinese perspective. Journal of Construction Engineering and Management, 136(5), 484–494.CrossRef Chan, P. (2010). Critical success factors for PPPs in infrastructure development: Chinese perspective. Journal of Construction Engineering and Management, 136(5), 484–494.CrossRef
Zurück zum Zitat DMRC. (2007). Executive summary of detailed project report prepared by DMRC for corridor 1, 2 & 3. Hyderabad: Government of Andhra Pradesh. DMRC. (2007). Executive summary of detailed project report prepared by DMRC for corridor 1, 2 & 3. Hyderabad: Government of Andhra Pradesh.
Zurück zum Zitat Famakin, I. (2014). Assessment of critical success factors and benefits of public private partnership in construction projects. International Journal of Emerging Technology and Advanced Engineering, 4(6), 742–751. http://www.ijetae.com/index.html. Accessed 30 Mar 2015. Famakin, I. (2014). Assessment of critical success factors and benefits of public private partnership in construction projects. International Journal of Emerging Technology and Advanced Engineering, 4(6), 742–751. http://​www.​ijetae.​com/​index.​html. Accessed 30 Mar 2015.
Zurück zum Zitat Gates, L. P. (2010). Strategic planning with critical success factors and future scenarios: An integrated strategic planning framework. Technical Report, Carnegie Mellon University. http://www.sei.cmu.edu. Accessed 20 Feb 2015. Gates, L. P. (2010). Strategic planning with critical success factors and future scenarios: An integrated strategic planning framework. Technical Report, Carnegie Mellon University. http://​www.​sei.​cmu.​edu. Accessed 20 Feb 2015.
Zurück zum Zitat Goel, S., Dwivedi, R., & Sherry, A. M. (2012). Critical factors for successful implementation of E-governance: A case study of HUDA. Global Journal of Flexible Systems Management, 13(4), 233–244.CrossRef Goel, S., Dwivedi, R., & Sherry, A. M. (2012). Critical factors for successful implementation of E-governance: A case study of HUDA. Global Journal of Flexible Systems Management, 13(4), 233–244.CrossRef
Zurück zum Zitat Hardcastle, C., Eswards, P. J., Akintoye, A., & Li, B. (2005). Critical success factors for PPP/PFI projects in the UK construction industry: A factor analysis approach. Construction Management and Economics, 23(5), 459–471.CrossRef Hardcastle, C., Eswards, P. J., Akintoye, A., & Li, B. (2005). Critical success factors for PPP/PFI projects in the UK construction industry: A factor analysis approach. Construction Management and Economics, 23(5), 459–471.CrossRef
Zurück zum Zitat Ismail, S., & Ajija, S. (2013). Critical success factors of public partnership implementation in Malaysia. Asia-Pacific Journal of Business Administration, 5(1), 6–19.CrossRef Ismail, S., & Ajija, S. (2013). Critical success factors of public partnership implementation in Malaysia. Asia-Pacific Journal of Business Administration, 5(1), 6–19.CrossRef
Zurück zum Zitat Kabra, G., & Ramesh, A. (2015). Analyzing ICT issues in humanitarian supply chain management: A SAP-LAP linkages framework. Global Journal of Flexible Systems Management, 16(2), 157–171.CrossRef Kabra, G., & Ramesh, A. (2015). Analyzing ICT issues in humanitarian supply chain management: A SAP-LAP linkages framework. Global Journal of Flexible Systems Management, 16(2), 157–171.CrossRef
Zurück zum Zitat KPMG. (2010). Success and failures in Urban transport infrastructure projects. UK: KPMG International. KPMG. (2010). Success and failures in Urban transport infrastructure projects. UK: KPMG International.
Zurück zum Zitat Kulshreshtha, R., Kumar, A., Tripathi, A., & Likhi, D. K. (2016). Critical success factors for public private partnerships in Urban metro systems in Indian context. Urban Transport Journal, 15(1), 60–75. Kulshreshtha, R., Kumar, A., Tripathi, A., & Likhi, D. K. (2016). Critical success factors for public private partnerships in Urban metro systems in Indian context. Urban Transport Journal, 15(1), 60–75.
Zurück zum Zitat Leedy, A. (1977). Practical research: Planning and design. Upper Saddle River: Prentice Hall. Leedy, A. (1977). Practical research: Planning and design. Upper Saddle River: Prentice Hall.
Zurück zum Zitat Li, B. (2005). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459–471.CrossRef Li, B. (2005). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459–471.CrossRef
Zurück zum Zitat Nasim, S., & Sushil (2014). Flexible strategy framework for managing continuity and change in E-Government. In Sushil and E. A. Stohr (Eds.), The Flexible Enterprise, Flexible Systems Management (pp. 47–66). New Delhi: Springer. Nasim, S., & Sushil (2014). Flexible strategy framework for managing continuity and change in E-Government. In Sushil and E. A. Stohr (Eds.), The Flexible Enterprise, Flexible Systems Management (pp. 47–66). New Delhi: Springer.
Zurück zum Zitat Saunders, E. (2007). Research methods for business students. Essex: Prentice Hall. Saunders, E. (2007). Research methods for business students. Essex: Prentice Hall.
Zurück zum Zitat Sushil, (2000a). Situation-actor-process options: Mapping and enhancing flexibility. Systems Research and Behavioral Science, 17(3), 301–309.CrossRef Sushil, (2000a). Situation-actor-process options: Mapping and enhancing flexibility. Systems Research and Behavioral Science, 17(3), 301–309.CrossRef
Zurück zum Zitat Sushil, (2000b). SAP-LAP models of enquiry. Management Decision, 38(5), 347–353.CrossRef Sushil, (2000b). SAP-LAP models of enquiry. Management Decision, 38(5), 347–353.CrossRef
Zurück zum Zitat Sushil, (2001). SAP-LAP framework. Global Journal of Flexible Management, 2(1), 51–55. Sushil, (2001). SAP-LAP framework. Global Journal of Flexible Management, 2(1), 51–55.
Zurück zum Zitat Sushil, (2009). SAP-LAP linkages—a generic interpretive framework for analysing managerial contexts. Global Journal of Flexible Systems Management, 10(2), 11–20. Sushil, (2009). SAP-LAP linkages—a generic interpretive framework for analysing managerial contexts. Global Journal of Flexible Systems Management, 10(2), 11–20.
Zurück zum Zitat Sushil, (2016). Theory of flexible systems management. In Sushil, J. Connel, & J. Burgess (Eds.), Flexible work organizations: The challenges of capacity building in Asia, flexible systems management (pp. 3–20). New Delhi: Springer.CrossRef Sushil, (2016). Theory of flexible systems management. In Sushil, J. Connel, & J. Burgess (Eds.), Flexible work organizations: The challenges of capacity building in Asia, flexible systems management (pp. 3–20). New Delhi: Springer.CrossRef
Zurück zum Zitat World Bank (2007). Public private partnership units: Lessons for their design and use in infrastructure. In Public private infrastructure advisory facility. World Bank. World Bank (2007). Public private partnership units: Lessons for their design and use in infrastructure. In Public private infrastructure advisory facility. World Bank.
Zurück zum Zitat Yadav, N., & Sushil, (2014). Theoretical roots of flexible strategy game-card: An evolving strategic performance management system. In Sushil & E. A. Stohr (Eds.), The flexible enterprise, flexible systems management (pp. 99–109). New Delhi: Springer.CrossRef Yadav, N., & Sushil, (2014). Theoretical roots of flexible strategy game-card: An evolving strategic performance management system. In Sushil & E. A. Stohr (Eds.), The flexible enterprise, flexible systems management (pp. 99–109). New Delhi: Springer.CrossRef
Zurück zum Zitat Zhang, X. (2005). Critical success factors for public private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3–14.CrossRef Zhang, X. (2005). Critical success factors for public private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3–14.CrossRef
Metadaten
Titel
Critical Success Factors in Implementation of Urban Metro System on PPP: A Case Study of Hyderabad Metro
verfasst von
Rakesh Kulshreshtha
Anil Kumar
Ashish Tripathi
Dinesh Kumar Likhi
Publikationsdatum
01.09.2017
Verlag
Springer India
Erschienen in
Global Journal of Flexible Systems Management / Ausgabe 4/2017
Print ISSN: 0972-2696
Elektronische ISSN: 0974-0198
DOI
https://doi.org/10.1007/s40171-017-0164-6

Weitere Artikel der Ausgabe 4/2017

Global Journal of Flexible Systems Management 4/2017 Zur Ausgabe

Premium Partner