8. Resource-Constrained Scheduling Extensions

verfasst von : Mario Vanhoucke

Erschienen in: Project Management with Dynamic Scheduling

Verlag: Springer Berlin Heidelberg

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Resource-constrained project scheduling has been a topic in both the research community and the practical oriented business magazines. This chapter presents some advanced results obtained by various research projects, extends the resource models of the previous chapter to other scheduling objectives, studies the effect of activity splitting and setup times and introduces learning effects in a resource-constrained project environment. Each part of this section can be considered as a special topic of resource-constrained project scheduling and can be easily skipped without losing overview on the general dynamic scheduling theme described throughout the book.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Fußnoten
1
In Chap.​ 9, it will be shown that there is a trade-off between the project duration and the idle time of expensive freezing machines for the construction of a tunnel under the Westerschelde.
 
2
The activity durations, their start times and the corresponding project duration for each schedule depend on the degree of learning for each activity. The calculations and construction of the schedule are outside the scope of this section and are determined by an algorithm developed by Van Peteghem and Vanhoucke (2010a).
 
Literatur
Zurück zum Zitat Agrawal M, Elmaghraby S, Herroelen W (1996) DAGEN: a generator of testsets for project activity nets. Eur J Oper Res 90:376–382CrossRef Agrawal M, Elmaghraby S, Herroelen W (1996) DAGEN: a generator of testsets for project activity nets. Eur J Oper Res 90:376–382CrossRef
Zurück zum Zitat Akkan C, Drexl A, Kimms A (2005) Network decomposition-based benchmark results for the discrete time-cost tradeoff problem. Eur J Oper Res 165:339–358CrossRef Akkan C, Drexl A, Kimms A (2005) Network decomposition-based benchmark results for the discrete time-cost tradeoff problem. Eur J Oper Res 165:339–358CrossRef
Zurück zum Zitat Alvarez-Valdes R, Tamarit J (1989) Heuristic algorithms for resource-constrained project scheduling: a review and empirical analysis. In: Slowinski R, Weglarz J (eds) Advances in project scheduling. Elsevier, Amsterdam Alvarez-Valdes R, Tamarit J (1989) Heuristic algorithms for resource-constrained project scheduling: a review and empirical analysis. In: Slowinski R, Weglarz J (eds) Advances in project scheduling. Elsevier, Amsterdam
Zurück zum Zitat Amor J, Teplitz C (1998) An efficient approximation procedure for project composite learning curves. Proj Manag J 29:28–42 Amor J, Teplitz C (1998) An efficient approximation procedure for project composite learning curves. Proj Manag J 29:28–42
Zurück zum Zitat Ash R, Smith-Daniels DE (1999) The effects of learning, forgetting, and relearning on decision rule performance in multiproject scheduling. Decis Sci 30:47–82CrossRef Ash R, Smith-Daniels DE (1999) The effects of learning, forgetting, and relearning on decision rule performance in multiproject scheduling. Decis Sci 30:47–82CrossRef
Zurück zum Zitat Bein W, Kamburowski J, Stallmann M (1992) Optimal reduction of two-terminal directed acyclic graphs. SIAM J Comput 21:1112–1129CrossRef Bein W, Kamburowski J, Stallmann M (1992) Optimal reduction of two-terminal directed acyclic graphs. SIAM J Comput 21:1112–1129CrossRef
Zurück zum Zitat Brucker P, Drexl A, Möhring R, Neumann K, Pesch E (1999) Resource-constrained project scheduling: notation, classification, models, and methods. Eur J Oper Res 112:3–41CrossRef Brucker P, Drexl A, Möhring R, Neumann K, Pesch E (1999) Resource-constrained project scheduling: notation, classification, models, and methods. Eur J Oper Res 112:3–41CrossRef
Zurück zum Zitat Cooper D (1976) Heuristics for scheduling resource-constrained projects: an experimental investigation. Manag Sci 22:1186–1194CrossRef Cooper D (1976) Heuristics for scheduling resource-constrained projects: an experimental investigation. Manag Sci 22:1186–1194CrossRef
Zurück zum Zitat Dar-El E (1973) MALB - A heuristic technique for balancing large single-model assembly lines. IIE Trans 5:343–356 Dar-El E (1973) MALB - A heuristic technique for balancing large single-model assembly lines. IIE Trans 5:343–356
Zurück zum Zitat Davies E (1974) An experimental investigation of resource allocation in multiactivity projects. Oper Res Q 24:587–591CrossRef Davies E (1974) An experimental investigation of resource allocation in multiactivity projects. Oper Res Q 24:587–591CrossRef
Zurück zum Zitat Davis E (1975) Project network summary measures constrained-resource scheduling. AIIE Trans 7:132–142CrossRef Davis E (1975) Project network summary measures constrained-resource scheduling. AIIE Trans 7:132–142CrossRef
Zurück zum Zitat De Boer R (1998) Resource-constrained multi-project management - A hierarchical decision support system. PhD thesis, Institute for Business Engineering and Technology Application, The Netherlands De Boer R (1998) Resource-constrained multi-project management - A hierarchical decision support system. PhD thesis, Institute for Business Engineering and Technology Application, The Netherlands
Zurück zum Zitat Demeulemeester E (1995) Minimizing resource availability costs in time-limited project networks. Manag Sci 41:1590–1598CrossRef Demeulemeester E (1995) Minimizing resource availability costs in time-limited project networks. Manag Sci 41:1590–1598CrossRef
Zurück zum Zitat Demeulemeester E, Dodin B, Herroelen W (1993) A random activity network generator. Oper Res 41:972–980CrossRef Demeulemeester E, Dodin B, Herroelen W (1993) A random activity network generator. Oper Res 41:972–980CrossRef
Zurück zum Zitat Demeulemeester E, Vanhoucke M, Herroelen W (2003) Rangen: a random network generator for activity-on-the-node networks. J Sched 6:17–38CrossRef Demeulemeester E, Vanhoucke M, Herroelen W (2003) Rangen: a random network generator for activity-on-the-node networks. J Sched 6:17–38CrossRef
Zurück zum Zitat Drexl A, Nissen R, Patterson J, Salewski F (2000) ProGen/πx - an instance generator for resource-constrained project scheduling problems with partially renewable resources and further extensions. Eur J Oper Res 125:59–72CrossRef Drexl A, Nissen R, Patterson J, Salewski F (2000) ProGen/πx - an instance generator for resource-constrained project scheduling problems with partially renewable resources and further extensions. Eur J Oper Res 125:59–72CrossRef
Zurück zum Zitat El-Rayes K, Moselhi O (1998) Resource-driven scheduling of repetitive activities. Constr Manage Econ 16:433–446CrossRef El-Rayes K, Moselhi O (1998) Resource-driven scheduling of repetitive activities. Constr Manage Econ 16:433–446CrossRef
Zurück zum Zitat Elmaghraby S, Herroelen W (1980) On the measurement of complexity in activity networks. Eur J Oper Res 5:223–234CrossRef Elmaghraby S, Herroelen W (1980) On the measurement of complexity in activity networks. Eur J Oper Res 5:223–234CrossRef
Zurück zum Zitat Gong D (1997) Optimization of float use in risk analysis-based network scheduling. Int J Proj Manag 15:187–192CrossRef Gong D (1997) Optimization of float use in risk analysis-based network scheduling. Int J Proj Manag 15:187–192CrossRef
Zurück zum Zitat Goto E, Joko T, Fujisawa K, Katoh N, Furusaka S (2000) Maximizing net present value for generalized resource constrained project scheduling problem. Working paper, Nomura Research Institute, Japan Goto E, Joko T, Fujisawa K, Katoh N, Furusaka S (2000) Maximizing net present value for generalized resource constrained project scheduling problem. Working paper, Nomura Research Institute, Japan
Zurück zum Zitat Harris R, Ioannou P (1998) Scheduling projects with repeating activities. J Constr Eng Manag 124:269–278CrossRef Harris R, Ioannou P (1998) Scheduling projects with repeating activities. J Constr Eng Manag 124:269–278CrossRef
Zurück zum Zitat Heimerl C, Kolisch R (2010) Scheduling and staffing multiple projects with a multi-skilled workforce. OR Spectr 32:343–368CrossRef Heimerl C, Kolisch R (2010) Scheduling and staffing multiple projects with a multi-skilled workforce. OR Spectr 32:343–368CrossRef
Zurück zum Zitat Herroelen W, De Reyck B (1999) Phase transitions in project scheduling. J Oper Res Soc 50: 148–156 Herroelen W, De Reyck B (1999) Phase transitions in project scheduling. J Oper Res Soc 50: 148–156
Zurück zum Zitat Herroelen W, Demeulemeester E, De Reyck B (1999) A classification scheme for project scheduling problem. In: Weglarz J (ed) Project scheduling - Recent models, algorithms and applications. Kluwer Academic Publishers, Dortrecht, pp 1–26 Herroelen W, Demeulemeester E, De Reyck B (1999) A classification scheme for project scheduling problem. In: Weglarz J (ed) Project scheduling - Recent models, algorithms and applications. Kluwer Academic Publishers, Dortrecht, pp 1–26
Zurück zum Zitat Kaimann R (1974) Coefficient of network complexity. Manag Sci 21:172–177CrossRef Kaimann R (1974) Coefficient of network complexity. Manag Sci 21:172–177CrossRef
Zurück zum Zitat Kaimann R (1975) Coefficient of network complexity: erratum. Manag Sci 21:1211–1212 Kaimann R (1975) Coefficient of network complexity: erratum. Manag Sci 21:1211–1212
Zurück zum Zitat Kang L, Park IC, Lee BH (2001) Optimal schedule planning for multiple, repetitive construction process. J Constr Eng Manag 127:382–390CrossRef Kang L, Park IC, Lee BH (2001) Optimal schedule planning for multiple, repetitive construction process. J Constr Eng Manag 127:382–390CrossRef
Zurück zum Zitat Kao E, Queyranne M (1982) On dynamic programming methods for assembly line balancing. Oper Res 30:375–390CrossRef Kao E, Queyranne M (1982) On dynamic programming methods for assembly line balancing. Oper Res 30:375–390CrossRef
Zurück zum Zitat Kolisch R, Sprecher A, Drexl A (1995) Characterization and generation of a general class of resource-constrained project scheduling problems. Manag Sci 41:1693–1703CrossRef Kolisch R, Sprecher A, Drexl A (1995) Characterization and generation of a general class of resource-constrained project scheduling problems. Manag Sci 41:1693–1703CrossRef
Zurück zum Zitat Mastor A (1970) An experimental and comparative evaluation of production line balancing techniques. Manag Sci 16:728–746CrossRef Mastor A (1970) An experimental and comparative evaluation of production line balancing techniques. Manag Sci 16:728–746CrossRef
Zurück zum Zitat Mika M (2006) Modelling setup times in project scheduling. In: Perspectives in modern project scheduling, vol 92, International series in operations research & management science. Springer, New York, pp 131–163 Mika M (2006) Modelling setup times in project scheduling. In: Perspectives in modern project scheduling, vol 92, International series in operations research & management science. Springer, New York, pp 131–163
Zurück zum Zitat Möhring R (1984) Minimizing costs of resource requirements in project networks subject to a fixed completion time. Oper Res 32:89–120CrossRef Möhring R (1984) Minimizing costs of resource requirements in project networks subject to a fixed completion time. Oper Res 32:89–120CrossRef
Zurück zum Zitat Nembhard D, Uzumeri M (2000) An individual-based description of learning within an organization. IEEE Trans Eng Manag 47(3):370–378CrossRef Nembhard D, Uzumeri M (2000) An individual-based description of learning within an organization. IEEE Trans Eng Manag 47(3):370–378CrossRef
Zurück zum Zitat Pascoe T (1966) Allocation of resources - CPM. Revue Française de Recherche Opérationnelle 38:31–38 Pascoe T (1966) Allocation of resources - CPM. Revue Française de Recherche Opérationnelle 38:31–38
Zurück zum Zitat Patterson J (1976) Project scheduling: the effects of problem structure on heuristic scheduling. Nav Res Logist 23:95–123CrossRef Patterson J (1976) Project scheduling: the effects of problem structure on heuristic scheduling. Nav Res Logist 23:95–123CrossRef
Zurück zum Zitat Schwindt C (1995) A new problem generator for different resource-constrained project scheduling problems with minimal and maximal time lags. WIOR-Report-449, Institut für Wirtschaftstheorie und Operations Research, University of Karlsruhe Schwindt C (1995) A new problem generator for different resource-constrained project scheduling problems with minimal and maximal time lags. WIOR-Report-449, Institut für Wirtschaftstheorie und Operations Research, University of Karlsruhe
Zurück zum Zitat Shtub A, LeBlanc L, Cai Z (1996) Scheduling programs with repetitive projects: a comparison of a simulated annealing, a genetic and a pair-wise swap algorithm. Eur J Oper Res 88:124–138CrossRef Shtub A, LeBlanc L, Cai Z (1996) Scheduling programs with repetitive projects: a comparison of a simulated annealing, a genetic and a pair-wise swap algorithm. Eur J Oper Res 88:124–138CrossRef
Zurück zum Zitat Tavares L (1999) Advanced models for project management. Kluwer Academic Publishers, Dordrecht Tavares L (1999) Advanced models for project management. Kluwer Academic Publishers, Dordrecht
Zurück zum Zitat Tavares L, Ferreira J, Coelho J (1999) The risk of delay of a project in terms of the morphology of its network. Eur J Oper Res 119:510–537CrossRef Tavares L, Ferreira J, Coelho J (1999) The risk of delay of a project in terms of the morphology of its network. Eur J Oper Res 119:510–537CrossRef
Zurück zum Zitat Thesen A (1977) Measures of the restrictiveness of project networks. Networks 7:193–208CrossRef Thesen A (1977) Measures of the restrictiveness of project networks. Networks 7:193–208CrossRef
Zurück zum Zitat Uyttewaal E (2005) Dynamic scheduling with Microsoft Office Project 2003: the book by and for professionals. Co-published with International Institute for Learning Inc, Boca Raton Uyttewaal E (2005) Dynamic scheduling with Microsoft Office Project 2003: the book by and for professionals. Co-published with International Institute for Learning Inc, Boca Raton
Zurück zum Zitat Vanhoucke M (2006b) Work continuity constraints in project scheduling. J Constr Eng Manag 132:14–25CrossRef Vanhoucke M (2006b) Work continuity constraints in project scheduling. J Constr Eng Manag 132:14–25CrossRef
Zurück zum Zitat Vanhoucke M (2008c) Setup times and fast tracking in resource-constrained project scheduling. Comput Ind Eng 54:1062–1070CrossRef Vanhoucke M (2008c) Setup times and fast tracking in resource-constrained project scheduling. Comput Ind Eng 54:1062–1070CrossRef
Zurück zum Zitat Vanhoucke M (2010a) Measuring time - Improving project performance using earned value management, vol 136, International series in operations research and management science. Springer, New York Vanhoucke M (2010a) Measuring time - Improving project performance using earned value management, vol 136, International series in operations research and management science. Springer, New York
Zurück zum Zitat Vanhoucke M, Debels D (2008) The impact of various activity assumptions on the lead time and resource utilization of resource-constrained projects. Comput Ind Eng 54:140–154CrossRef Vanhoucke M, Debels D (2008) The impact of various activity assumptions on the lead time and resource utilization of resource-constrained projects. Comput Ind Eng 54:140–154CrossRef
Zurück zum Zitat Vanhoucke M, Vandevoorde S (2007b) A simulation and evaluation of earned value metrics to forecast the project duration. J Oper Res Soc 58:1361–1374CrossRef Vanhoucke M, Vandevoorde S (2007b) A simulation and evaluation of earned value metrics to forecast the project duration. J Oper Res Soc 58:1361–1374CrossRef
Zurück zum Zitat Vanhoucke M, Coelho J, Debels D, Maenhout B, Tavares L (2008) An evaluation of the adequacy of project network generators with systematically sampled networks. Eur J Oper Res 187: 511–524CrossRef Vanhoucke M, Coelho J, Debels D, Maenhout B, Tavares L (2008) An evaluation of the adequacy of project network generators with systematically sampled networks. Eur J Oper Res 187: 511–524CrossRef
Zurück zum Zitat Van Peteghem V, Vanhoucke M (2010a) A genetic algorithm for the preemptive and non-preemtive multi-mode resource-constrained project scheduling problem. Eur J Oper Res 201:409–418CrossRef Van Peteghem V, Vanhoucke M (2010a) A genetic algorithm for the preemptive and non-preemtive multi-mode resource-constrained project scheduling problem. Eur J Oper Res 201:409–418CrossRef
Zurück zum Zitat Van Peteghem V, Vanhoucke M (2010b) Introducing learning effects in resource-constrained project scheduling. Technical report, Ghent University, Ghent, Belgium Van Peteghem V, Vanhoucke M (2010b) Introducing learning effects in resource-constrained project scheduling. Technical report, Ghent University, Ghent, Belgium
Zurück zum Zitat Wright T (1936) Factors affecting the cost of airplanes. J Aeronaut Sci 3:122–128CrossRef Wright T (1936) Factors affecting the cost of airplanes. J Aeronaut Sci 3:122–128CrossRef
Zurück zum Zitat Yelle L (1979) The learning curves: historical review and comprehensive survey. Decis Sci 10(2):302–328CrossRef Yelle L (1979) The learning curves: historical review and comprehensive survey. Decis Sci 10(2):302–328CrossRef
Metadaten
Titel
Resource-Constrained Scheduling Extensions
verfasst von
Mario Vanhoucke
Copyright-Jahr
2013
Verlag
Springer Berlin Heidelberg
DOI
https://doi.org/10.1007/978-3-642-40438-2_8

Premium Partner