Studying Lean-Kanban Approach Using Software Process Simulation
verfasst von : David Anderson, Giulio Concas, Maria Ilaria Lunesu, Michele Marchesi
Erschienen in: Agile Processes in Software Engineering and Extreme Programming
Verlag: Springer Berlin Heidelberg
Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.
Wählen Sie Textabschnitte aus um mit Künstlicher Intelligenz passenden Patente zu finden. powered by
Markieren Sie Textabschnitte, um KI-gestützt weitere passende Inhalte zu finden. powered by
We developed an event-driven simulator of the Kanban process a WIP limited pull system visualized by the Kanban board. WIP (work in process) represent the capacity in the activity to perform features simoultaneously. The simulator is fully object-oriented, and its design model reflects the objects of the Lean software development domain. We used this simulator to assess comparatively WIP-limited and unlimited processes. We also studied the optimum values of the working item limits in the activities, using a paradigmatic case of 4 activities and 100 work items. The cost function used is equal to the total time needed to complete the project, plus a weighted sum of the limits themselves. We performed an exhaustive search on all the admissible values of the solution, finding sensible optimal values, and a non-trivial behavior of the cost function in the optimization space.
This demonstrates the feasibility and usefulness of the approach.