The proactive and reactive resource-constrained project scheduling problem

verfasst von: Morteza Davari, Erik Demeulemeester

Erschienen in: Journal of Scheduling | Ausgabe 2/2019

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

Uncertainty has become an inevitable aspect of project scheduling. We study the resource-constrained project scheduling problem with stochastic durations. One of the most studied approaches to deal with stochastic durations is that of proactive and reactive scheduling. Previous researches often studied proactive and reactive scheduling rather separately and ignored the fact that proactive scheduling and reactive scheduling are closely connected. In this paper, we address this ignored aspect by formulating an integrated proactive and reactive scheduling problem with a combined cost function which includes a baseline schedule cost as well as costs of a series of reactions. We introduce solutions to this integrated problem as proactive-and-reactive policies (PR-policies). We discuss that PR-policies are more powerful and informative than their traditional counterparts (i.e., a combination of a baseline schedule and a reactive policy), provide better stability and robustness, and are more flexible when extra constraints are added to the problem. We also propose four dynamic programming based models (Models 1–4) that solve the problem to optimality over different classes of PR-policies. We compare our models with each other and with a combination of a traditional proactive approach (namely, the starting time criticality heuristic) and a reactive approach (namely, the robust parallel schedule generation scheme). Computational results show that Model 2 outperforms the traditional solution only when reaction costs are greater than zero. Moreover, Model 3 and Model 4 clearly outperform Model 1 and Model 2 in all settings and the traditional solution in most of the settings.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Fußnoten
1
Robustness refers to the ability of tolerating variabilities that may affect the feasibility of a schedule.
 
2
The free slack is the amount of time that each activity can be delayed without delaying any other activity.
 
3
A schedule \(\mathbf {s}\) is called infeasible if at least one activity i cannot be started at \(s_i\) without violating any resource or precedence constraint.
 
Literatur
Zurück zum Zitat Abbasi, B., Shadrokh, S., & Arkat, J. (2006). Bi-objective resource-constrained project scheduling with robustness and makespan criteria. Applied Mathematics and Computation, 180(1), 146–152.CrossRef Abbasi, B., Shadrokh, S., & Arkat, J. (2006). Bi-objective resource-constrained project scheduling with robustness and makespan criteria. Applied Mathematics and Computation, 180(1), 146–152.CrossRef
Zurück zum Zitat Akkan, C., Külünk, M. E., & Koçaş, C. C. (2016). Finding robust timetables for project presentations of student teams. European Journal of Operational Research, 249(2), 560–576.CrossRef Akkan, C., Külünk, M. E., & Koçaş, C. C. (2016). Finding robust timetables for project presentations of student teams. European Journal of Operational Research, 249(2), 560–576.CrossRef
Zurück zum Zitat Al-Fawzan, M. A., & Haouari, M. (2005). A bi-objective model for robust resource-constrained project scheduling. International Journal of Production Economics, 96(2), 175–187.CrossRef Al-Fawzan, M. A., & Haouari, M. (2005). A bi-objective model for robust resource-constrained project scheduling. International Journal of Production Economics, 96(2), 175–187.CrossRef
Zurück zum Zitat Alvarez-Valdes, R., & Tamarit, J. (1993). The project scheduling polyhedron: Dimension, facets and lifting theorems. European Journal of Operational Research, 67(2), 204–220.CrossRef Alvarez-Valdes, R., & Tamarit, J. (1993). The project scheduling polyhedron: Dimension, facets and lifting theorems. European Journal of Operational Research, 67(2), 204–220.CrossRef
Zurück zum Zitat Ashtiani, B., Leus, R., & Aryanezhad, M. B. (2011). New competitive results for the stochastic resource-constrained project scheduling problem: Exploring the benefits of pre-processing. Journal of Scheduling, 14(2), 157–171.CrossRef Ashtiani, B., Leus, R., & Aryanezhad, M. B. (2011). New competitive results for the stochastic resource-constrained project scheduling problem: Exploring the benefits of pre-processing. Journal of Scheduling, 14(2), 157–171.CrossRef
Zurück zum Zitat Ballestín, F., & Leus, R. (2009). Resource-constrained project scheduling for timely project completion with stochastic activity durations. Production and Operations Management, 18(4), 459–474.CrossRef Ballestín, F., & Leus, R. (2009). Resource-constrained project scheduling for timely project completion with stochastic activity durations. Production and Operations Management, 18(4), 459–474.CrossRef
Zurück zum Zitat Ben-Tal, A., Goryashko, A., Guslitzer, E., & Nemirovski, A. (2003). Adjustable robust solutions of uncertain linear programs. Mathematical Programming, 99(2), 351–376.CrossRef Ben-Tal, A., Goryashko, A., Guslitzer, E., & Nemirovski, A. (2003). Adjustable robust solutions of uncertain linear programs. Mathematical Programming, 99(2), 351–376.CrossRef
Zurück zum Zitat Chaari, T., Chaabane, S., Aissani, N., & Trentesaux, D. (2014). Scheduling under uncertainty: Survey and research directions. In 2014 International conference on advanced logistics and transport (ICALT) (pp. 229–234). Chaari, T., Chaabane, S., Aissani, N., & Trentesaux, D. (2014). Scheduling under uncertainty: Survey and research directions. In 2014 International conference on advanced logistics and transport (ICALT) (pp. 229–234).
Zurück zum Zitat Chtourou, H., & Haouari, M. (2008). A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling. Computers & Industrial Engineering, 55(1), 183–194.CrossRef Chtourou, H., & Haouari, M. (2008). A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling. Computers & Industrial Engineering, 55(1), 183–194.CrossRef
Zurück zum Zitat Creemers, S. (2015). Minimizing the expected makespan of a project with stochastic activity durations under resource constraints. Journal of Scheduling, 18(3), 263–273.CrossRef Creemers, S. (2015). Minimizing the expected makespan of a project with stochastic activity durations under resource constraints. Journal of Scheduling, 18(3), 263–273.CrossRef
Zurück zum Zitat Creemers, S., Leus, R., & Lambrecht, M. (2010). Scheduling markovian PERT networks to maximize the net present value. Operations Research Letters, 38(1), 51–56.CrossRef Creemers, S., Leus, R., & Lambrecht, M. (2010). Scheduling markovian PERT networks to maximize the net present value. Operations Research Letters, 38(1), 51–56.CrossRef
Zurück zum Zitat Deblaere, F., Demeulemeester, E., & Herroelen, W. (2011). Proactive policies for the stochastic resource-constrained project scheduling problem. European Journal of Operational Research, 214(2), 308–316.CrossRef Deblaere, F., Demeulemeester, E., & Herroelen, W. (2011). Proactive policies for the stochastic resource-constrained project scheduling problem. European Journal of Operational Research, 214(2), 308–316.CrossRef
Zurück zum Zitat Demeulemeester, E., & Herroelen, W. (1992). A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Management Science, 38(12), 1803–1818.CrossRef Demeulemeester, E., & Herroelen, W. (1992). A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Management Science, 38(12), 1803–1818.CrossRef
Zurück zum Zitat Demeulemeester, E., & Herroelen, W. (1997). New benchmark results for the resource-constrained project scheduling problem. Management Science, 43(11), 1485–1492.CrossRef Demeulemeester, E., & Herroelen, W. (1997). New benchmark results for the resource-constrained project scheduling problem. Management Science, 43(11), 1485–1492.CrossRef
Zurück zum Zitat Demeulemeester, E., & Herroelen, W. (2011). Robust project scheduling. Foundations and Trends in Technology, Information and Operations Management, 3, 201–376.CrossRef Demeulemeester, E., & Herroelen, W. (2011). Robust project scheduling. Foundations and Trends in Technology, Information and Operations Management, 3, 201–376.CrossRef
Zurück zum Zitat Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge: Cambridge University Press.CrossRef Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge: Cambridge University Press.CrossRef
Zurück zum Zitat Gabrel, V., Murat, C., & Thiele, A. (2014). Recent advances in robust optimization: An overview. European Journal of Operational Research, 235(3), 471–483.CrossRef Gabrel, V., Murat, C., & Thiele, A. (2014). Recent advances in robust optimization: An overview. European Journal of Operational Research, 235(3), 471–483.CrossRef
Zurück zum Zitat Herroelen, W. (2005). Project scheduling: Theory and practice. Production and Operations Management, 14(4), 413–432.CrossRef Herroelen, W. (2005). Project scheduling: Theory and practice. Production and Operations Management, 14(4), 413–432.CrossRef
Zurück zum Zitat Herroelen, W., & Leus, R. (2004). The construction of stable project baseline schedules. European Journal of Operational Research, 156(3), 550–565.CrossRef Herroelen, W., & Leus, R. (2004). The construction of stable project baseline schedules. European Journal of Operational Research, 156(3), 550–565.CrossRef
Zurück zum Zitat Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306. Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306.
Zurück zum Zitat Igelmund, G., & Radermacher, F. J. (1983). Preselective strategies for the optimization of stochastic project networks under resource constraints. Networks, 13(1), 1–28.CrossRef Igelmund, G., & Radermacher, F. J. (1983). Preselective strategies for the optimization of stochastic project networks under resource constraints. Networks, 13(1), 1–28.CrossRef
Zurück zum Zitat Kolisch, R., & Sprecher, A. (1997). PSPLIB—A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef Kolisch, R., & Sprecher, A. (1997). PSPLIB—A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef
Zurück zum Zitat Lamas, P., & Demeulemeester, E. (2016). A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations. Journal of Scheduling, 19(4), 409–428.CrossRef Lamas, P., & Demeulemeester, E. (2016). A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations. Journal of Scheduling, 19(4), 409–428.CrossRef
Zurück zum Zitat Leus, R. (2003). The generation of stable project plans. Ph.D. thesis, KU Leuven. Leus, R. (2003). The generation of stable project plans. Ph.D. thesis, KU Leuven.
Zurück zum Zitat Leus, R., & Herroelen, W. (2005). The complexity of machine scheduling for stability with a single disrupted job. Operations Research Letters, 33(2), 151–156.CrossRef Leus, R., & Herroelen, W. (2005). The complexity of machine scheduling for stability with a single disrupted job. Operations Research Letters, 33(2), 151–156.CrossRef
Zurück zum Zitat Liebchen, C., Lübbecke, M., Möhring, R., & Stiller, S. (2009). The concept of recoverable robustness, linear programming recovery, and railway applications. In R. K. Ahuja, R. H. Möhring, & C. D. Zaroliagis (Eds.), Robust and online large-scale optimization: Models and techniques for transportation systems (pp. 1–27). Berlin: Springer. Liebchen, C., Lübbecke, M., Möhring, R., & Stiller, S. (2009). The concept of recoverable robustness, linear programming recovery, and railway applications. In R. K. Ahuja, R. H. Möhring, & C. D. Zaroliagis (Eds.), Robust and online large-scale optimization: Models and techniques for transportation systems (pp. 1–27). Berlin: Springer.
Zurück zum Zitat Möhring, R., Radermacher, F., & Weiss, G. (1984). Stochastic scheduling problems I—General strategies. Zeitschrift für Operations Research, 28(7), 193–260. Möhring, R., Radermacher, F., & Weiss, G. (1984). Stochastic scheduling problems I—General strategies. Zeitschrift für Operations Research, 28(7), 193–260.
Zurück zum Zitat Möhring, R., Radermacher, F., & Weiss, G. (1985). Stochastic scheduling problems II—Set strategies. Zeitschrift für Operations Research, 29(3), 65–104. Möhring, R., Radermacher, F., & Weiss, G. (1985). Stochastic scheduling problems II—Set strategies. Zeitschrift für Operations Research, 29(3), 65–104.
Zurück zum Zitat Shapiro, A. (2011). A dynamic programming approach to adjustable robust optimization. Operations Research Letters, 39(2), 83–87.CrossRef Shapiro, A. (2011). A dynamic programming approach to adjustable robust optimization. Operations Research Letters, 39(2), 83–87.CrossRef
Zurück zum Zitat Stork, F. (2001). Stochastic resource-constrained project scheduling. Ph.D. thesis, TU Berlin. Stork, F. (2001). Stochastic resource-constrained project scheduling. Ph.D. thesis, TU Berlin.
Zurück zum Zitat Van de Vonder, S., Ballestin, F., Demeulemeester, E., & Herroelen, W. (2007). Heuristic procedures for reactive project scheduling. Computers & Industrial Engineering, 52(1), 11–28.CrossRef Van de Vonder, S., Ballestin, F., Demeulemeester, E., & Herroelen, W. (2007). Heuristic procedures for reactive project scheduling. Computers & Industrial Engineering, 52(1), 11–28.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2008). Proactive heuristic procedures for robust project scheduling: An experimental analysis. European Journal of Operational Research, 189(3), 723–733.CrossRef Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2008). Proactive heuristic procedures for robust project scheduling: An experimental analysis. European Journal of Operational Research, 189(3), 723–733.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2005). The use of buffers in project management: The trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227–240.CrossRef Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2005). The use of buffers in project management: The trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227–240.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2006). The trade-off between stability and makespan in resource-constrained project scheduling. International Journal of Production Research, 44(2), 215–236.CrossRef Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2006). The trade-off between stability and makespan in resource-constrained project scheduling. International Journal of Production Research, 44(2), 215–236.CrossRef
Metadaten
Titel
The proactive and reactive resource-constrained project scheduling problem
verfasst von
Morteza Davari
Erik Demeulemeester
Publikationsdatum
13.12.2017
Verlag
Springer US
Erschienen in
Journal of Scheduling / Ausgabe 2/2019
Print ISSN: 1094-6136
Elektronische ISSN: 1099-1425
DOI
https://doi.org/10.1007/s10951-017-0553-x

Weitere Artikel der Ausgabe 2/2019

Journal of Scheduling 2/2019 Zur Ausgabe