A genetic algorithm for the robust resource leveling problem

verfasst von: Hongbo Li, Erik Demeulemeester

Erschienen in: Journal of Scheduling | Ausgabe 1/2016

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

The resource leveling problem (RLP) involves the determination of a project baseline schedule that specifies the planned activity starting times while satisfying both the precedence constraints and the project deadline constraint under the objective of minimizing the variation in the resource utilization. However, uncertainty is inevitable during project execution. The baseline schedule generated by the deterministic RLP model tends to fail to achieve the desired objective when durations are uncertain. We study the robust resource leveling problem in which the activity durations are stochastic and the objective is to obtain a robust baseline schedule that minimizes the expected positive deviation of both resource utilizations and activity starting times. We present a genetic algorithm for the robust RLP. In order to demonstrate the effectiveness of our genetic algorithm, we conduct extensive computational experiments on a large number of randomly generated test instances and investigate the impact of different factors (the marginal cost of resource usage deviations, the marginal cost of activity starting time deviations, the activity duration variability, the due date, the order strength, the resource factor and the resource constrainedness).

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
Zurück zum Zitat Ahuja, H. N. (1976). Construction performance control by networks. New York: Wiley. Ahuja, H. N. (1976). Construction performance control by networks. New York: Wiley.
Zurück zum Zitat Ashuri, B., & Tavakolan, M. (2012). Fuzzy enabled hybrid genetic algorithm-particle swarm optimization approach to solve TCRO problems in construction project planning. Journal of Construction Engineering and Management, 138(9), 1065–1074.CrossRef Ashuri, B., & Tavakolan, M. (2012). Fuzzy enabled hybrid genetic algorithm-particle swarm optimization approach to solve TCRO problems in construction project planning. Journal of Construction Engineering and Management, 138(9), 1065–1074.CrossRef
Zurück zum Zitat Ballestín, F. (2007). When it is worthwhile to work with the stochastic RCPSP? Journal of Scheduling, 10(3), 153–166.CrossRef Ballestín, F. (2007). When it is worthwhile to work with the stochastic RCPSP? Journal of Scheduling, 10(3), 153–166.CrossRef
Zurück zum Zitat Ballestín, F., Schwindt, C., & Zimmermann, J. (2007). Resource leveling in make-to-order production: Modeling and heuristic solution method. International Journal of Operations Research, 4(1), 50–62. Ballestín, F., Schwindt, C., & Zimmermann, J. (2007). Resource leveling in make-to-order production: Modeling and heuristic solution method. International Journal of Operations Research, 4(1), 50–62.
Zurück zum Zitat Bandelloni, M., Tucci, M., & Rinaldi, R. (1994). Optimal resource leveling using non-serial dyanamic programming. European Journal of Operational Research, 78(2), 162–177.CrossRef Bandelloni, M., Tucci, M., & Rinaldi, R. (1994). Optimal resource leveling using non-serial dyanamic programming. European Journal of Operational Research, 78(2), 162–177.CrossRef
Zurück zum Zitat Burgess, A. R., & Killebrew, J. B. (1962). Variation in activity level on a cyclic arrow diagram. Journal of Industrial Engineering, 13(2), 76–83. Burgess, A. R., & Killebrew, J. B. (1962). Variation in activity level on a cyclic arrow diagram. Journal of Industrial Engineering, 13(2), 76–83.
Zurück zum Zitat Chan, W. T., Chua, D. K., & Kannan, G. (1996). Construction resource scheduling with genetic algorithms. Journal of Construction Engineering and Management, 122(2), 125–132.CrossRef Chan, W. T., Chua, D. K., & Kannan, G. (1996). Construction resource scheduling with genetic algorithms. Journal of Construction Engineering and Management, 122(2), 125–132.CrossRef
Zurück zum Zitat Debels, D., & Vanhoucke, M. (2007). A decomposition-based genetic algorithm for the resource-constrained project-scheduling problem. Operations Research, 55(3), 457–469.CrossRef Debels, D., & Vanhoucke, M. (2007). A decomposition-based genetic algorithm for the resource-constrained project-scheduling problem. Operations Research, 55(3), 457–469.CrossRef
Zurück zum Zitat Deblaere, F., Demeulemeester, E., & Herroelen, W. (2011). Proactive policies for the stochastic resource-constrained project scheduling problem. European Journal of Operational Research, 214(2), 308–316.CrossRef Deblaere, F., Demeulemeester, E., & Herroelen, W. (2011). Proactive policies for the stochastic resource-constrained project scheduling problem. European Journal of Operational Research, 214(2), 308–316.CrossRef
Zurück zum Zitat Demeulemeester, E. L., & Herroelen, W. (2002). Project scheduling: A research handbook. Boston: Kluwer Academic Pub. Demeulemeester, E. L., & Herroelen, W. (2002). Project scheduling: A research handbook. Boston: Kluwer Academic Pub.
Zurück zum Zitat Demeulemeester, E. L., & Herroelen, W. (2011). Robust project scheduling (Vol. 3, No. 3–4). Delft: Now Publishers Inc. Demeulemeester, E. L., & Herroelen, W. (2011). Robust project scheduling (Vol. 3, No. 3–4). Delft: Now Publishers Inc.
Zurück zum Zitat Demeulemeester, E., Vanhoucke, M., & Herroelen, W. (2003). RanGen: A random network generator for activity-on-the-node networks. Journal of Scheduling, 6(1), 17–38.CrossRef Demeulemeester, E., Vanhoucke, M., & Herroelen, W. (2003). RanGen: A random network generator for activity-on-the-node networks. Journal of Scheduling, 6(1), 17–38.CrossRef
Zurück zum Zitat Easa, S. M. (1989). Resource leveling in construction by optimization. Journal of Construction Engineering and Management, 115(2), 302–316.CrossRef Easa, S. M. (1989). Resource leveling in construction by optimization. Journal of Construction Engineering and Management, 115(2), 302–316.CrossRef
Zurück zum Zitat El-Rayes, K., & Jun, D. H. (2009). Optimizing resource leveling in construction projects. Journal of Construction Engineering and Management, 135(11), 1172–1180.CrossRef El-Rayes, K., & Jun, D. H. (2009). Optimizing resource leveling in construction projects. Journal of Construction Engineering and Management, 135(11), 1172–1180.CrossRef
Zurück zum Zitat Gather, T., Zimmermann, J., & Bartels, J. H. (2011). Exact methods for the resource levelling problem. Journal of Scheduling, 14(6), 557–569.CrossRef Gather, T., Zimmermann, J., & Bartels, J. H. (2011). Exact methods for the resource levelling problem. Journal of Scheduling, 14(6), 557–569.CrossRef
Zurück zum Zitat Goldberg, D. E., Korb, B., & Deb, K. (1989). Messy genetic algorithms: Motivation, analysis, and first results. Complex Systems, 3, 493–530. Goldberg, D. E., Korb, B., & Deb, K. (1989). Messy genetic algorithms: Motivation, analysis, and first results. Complex Systems, 3, 493–530.
Zurück zum Zitat Hariga, M., & El-Sayegh, S. M. (2011). Cost optimization model for the multiresource leveling problem with allowed activity splitting. Journal of Construction Engineering and Management, 137(1), 56–64.CrossRef Hariga, M., & El-Sayegh, S. M. (2011). Cost optimization model for the multiresource leveling problem with allowed activity splitting. Journal of Construction Engineering and Management, 137(1), 56–64.CrossRef
Zurück zum Zitat Harris, R. B. (1990). Packing method for resource leveling (PACK). Journal of Construction Engineering and Management, 116(2), 331–350.CrossRef Harris, R. B. (1990). Packing method for resource leveling (PACK). Journal of Construction Engineering and Management, 116(2), 331–350.CrossRef
Zurück zum Zitat Hartmann, S. (2002). A self-adapting genetic algorithm for project scheduling under resource constraints. Naval Research Logistics, 49(5), 433–448.CrossRef Hartmann, S. (2002). A self-adapting genetic algorithm for project scheduling under resource constraints. Naval Research Logistics, 49(5), 433–448.CrossRef
Zurück zum Zitat Herroelen, W., & De Reyck, B. (1999). Phase transitions in project scheduling. Journal of the Operational Research Society, 50(2), 148–156.CrossRef Herroelen, W., & De Reyck, B. (1999). Phase transitions in project scheduling. Journal of the Operational Research Society, 50(2), 148–156.CrossRef
Zurück zum Zitat Herroelen, W., De Reyck, B., & Demeulemeester, E. (2000). On the paper “Resource-constrained project scheduling: Notation, classification, models and methods” by Brucker et al. European Journal of Operational Research, 128(3), 221–230. Herroelen, W., De Reyck, B., & Demeulemeester, E. (2000). On the paper “Resource-constrained project scheduling: Notation, classification, models and methods” by Brucker et al. European Journal of Operational Research, 128(3), 221–230.
Zurück zum Zitat Herroelen, W., & Leus, R. (2004a). Robust and reactive project scheduling: A review and classification of procedures. International Journal of Production Research, 42(8), 1599–1620.CrossRef Herroelen, W., & Leus, R. (2004a). Robust and reactive project scheduling: A review and classification of procedures. International Journal of Production Research, 42(8), 1599–1620.CrossRef
Zurück zum Zitat Herroelen, W., & Leus, R. (2004b). The construction of stable project baseline schedules. European Journal of Operational Research, 156(3), 550–565.CrossRef Herroelen, W., & Leus, R. (2004b). The construction of stable project baseline schedules. European Journal of Operational Research, 156(3), 550–565.CrossRef
Zurück zum Zitat Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306.CrossRef Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306.CrossRef
Zurück zum Zitat Ke, H., & Liu, B. (2005). Project scheduling problem with stochastic activity duration times. Applied Mathematics and Computation, 168(1), 342–353.CrossRef Ke, H., & Liu, B. (2005). Project scheduling problem with stochastic activity duration times. Applied Mathematics and Computation, 168(1), 342–353.CrossRef
Zurück zum Zitat Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Proceedings of the Eastern Joint Computer Conference (pp. 160–173). Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Proceedings of the Eastern Joint Computer Conference (pp. 160–173).
Zurück zum Zitat Kolisch, R., & Sprecher, A. (1997). PSPLIB: A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef Kolisch, R., & Sprecher, A. (1997). PSPLIB: A project scheduling problem library. European Journal of Operational Research, 96(1), 205–216.CrossRef
Zurück zum Zitat Kreter, S., Rieck, J., & Zimmermann, J. (2014). The total adjustment cost problem: Applications, models, and solution algorithms. Journal of Scheduling, 17(2), 145–160.CrossRef Kreter, S., Rieck, J., & Zimmermann, J. (2014). The total adjustment cost problem: Applications, models, and solution algorithms. Journal of Scheduling, 17(2), 145–160.CrossRef
Zurück zum Zitat Lamas, P., & Demeulemeester, E. (2015). A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations. Journal of Scheduling, 1–20. doi:10.1007/s10951-015-0423-3. Lamas, P., & Demeulemeester, E. (2015). A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations. Journal of Scheduling, 1–20. doi:10.​1007/​s10951-015-0423-3.
Zurück zum Zitat Lambrechts, O., Demeulemeester, E., & Herroelen, W. (2008). Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities. Journal of Scheduling, 11(2), 121–136.CrossRef Lambrechts, O., Demeulemeester, E., & Herroelen, W. (2008). Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities. Journal of Scheduling, 11(2), 121–136.CrossRef
Zurück zum Zitat Leu, S. S., Chen, A. T., & Yang, C. H. (1999). A fuzzy optimal model for construction resource leveling scheduling. Canadian Journal of Civil Engineering, 26(6), 673–684.CrossRef Leu, S. S., Chen, A. T., & Yang, C. H. (1999). A fuzzy optimal model for construction resource leveling scheduling. Canadian Journal of Civil Engineering, 26(6), 673–684.CrossRef
Zurück zum Zitat Leu, S. S., Yang, C. H., & Huang, J. C. (2000). Resource leveling in construction by genetic algorithm-based optimization and its decision support system application. Automation in Construction, 10(1), 27–41.CrossRef Leu, S. S., Yang, C. H., & Huang, J. C. (2000). Resource leveling in construction by genetic algorithm-based optimization and its decision support system application. Automation in Construction, 10(1), 27–41.CrossRef
Zurück zum Zitat Leu, S. S., & Hung, T. H. (2002). An optimal construction resource leveling scheduling simulation model. Canadian Journal of Civil Engineering, 29(2), 267–275.CrossRef Leu, S. S., & Hung, T. H. (2002). An optimal construction resource leveling scheduling simulation model. Canadian Journal of Civil Engineering, 29(2), 267–275.CrossRef
Zurück zum Zitat Li, H., Xu, Z., & Demeulemeester, E. (2015). Scheduling policies for the stochastic resource leveling problem. Journal of Construction Engineering and Management, 141(2), 04014072.CrossRef Li, H., Xu, Z., & Demeulemeester, E. (2015). Scheduling policies for the stochastic resource leveling problem. Journal of Construction Engineering and Management, 141(2), 04014072.CrossRef
Zurück zum Zitat Liu, B. (2009). Stochastic programming. Theory and practice of uncertain programming (2nd ed., pp. 25–56). Berlin, Heidelberg: Springer.CrossRef Liu, B. (2009). Stochastic programming. Theory and practice of uncertain programming (2nd ed., pp. 25–56). Berlin, Heidelberg: Springer.CrossRef
Zurück zum Zitat Masmoudi, M., & Haït, A. (2013). Project scheduling under uncertainty using fuzzy modelling and solving techniques. Engineering Applications of Artificial Intelligence, 26(1), 135–149.CrossRef Masmoudi, M., & Haït, A. (2013). Project scheduling under uncertainty using fuzzy modelling and solving techniques. Engineering Applications of Artificial Intelligence, 26(1), 135–149.CrossRef
Zurück zum Zitat Neumann, K., & Zimmermann, J. (1999). Resource levelling for projects with schedule-dependent time windows. European Journal of Operational Research, 117(3), 591–605.CrossRef Neumann, K., & Zimmermann, J. (1999). Resource levelling for projects with schedule-dependent time windows. European Journal of Operational Research, 117(3), 591–605.CrossRef
Zurück zum Zitat Neumann, K., & Zimmermann, J. (2000). Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints. European Journal of Operational Research, 127(2), 425–443.CrossRef Neumann, K., & Zimmermann, J. (2000). Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints. European Journal of Operational Research, 127(2), 425–443.CrossRef
Zurück zum Zitat Neumann, K., Schwindt, C., & Zimmermann, J. (2003). Project scheduling with time windows and scarce resources. Berlin: Springer.CrossRef Neumann, K., Schwindt, C., & Zimmermann, J. (2003). Project scheduling with time windows and scarce resources. Berlin: Springer.CrossRef
Zurück zum Zitat Ponz-Tienda, J. L., Yepes, V., Pellicer, E., & Moreno-Flores, J. (2013). The Resource Leveling Problem with multiple resources using an adaptive genetic algorithm. Automation in Construction, 29, 161–172.CrossRef Ponz-Tienda, J. L., Yepes, V., Pellicer, E., & Moreno-Flores, J. (2013). The Resource Leveling Problem with multiple resources using an adaptive genetic algorithm. Automation in Construction, 29, 161–172.CrossRef
Zurück zum Zitat Ranjbar, M. (2013). A path-relinking metaheuristic for the resource levelling problem. Journal of the Operational Research Society, 64(7), 1071–1078.CrossRef Ranjbar, M. (2013). A path-relinking metaheuristic for the resource levelling problem. Journal of the Operational Research Society, 64(7), 1071–1078.CrossRef
Zurück zum Zitat Rieck, J., Zimmermann, J., & Gather, T. (2012). Mixed-integer linear programming for resource leveling problems. European Journal of Operational Research, 221(1), 27–37.CrossRef Rieck, J., Zimmermann, J., & Gather, T. (2012). Mixed-integer linear programming for resource leveling problems. European Journal of Operational Research, 221(1), 27–37.CrossRef
Zurück zum Zitat Tang, L., Zhao, Y., & Liu, J. (2014). An improved differential evolution algorithm for practical dynamic scheduling in steelmaking-continuous casting production. IEEE Transactions on Evolutionary Computation, 18(2), 209–225.CrossRef Tang, L., Zhao, Y., & Liu, J. (2014). An improved differential evolution algorithm for practical dynamic scheduling in steelmaking-continuous casting production. IEEE Transactions on Evolutionary Computation, 18(2), 209–225.CrossRef
Zurück zum Zitat Valls, V., Ballestin, F., & Quintanilla, S. (2008). A hybrid genetic algorithm for the resource-constrained project scheduling problem. European Journal of Operational Research, 185(2), 495–508.CrossRef Valls, V., Ballestin, F., & Quintanilla, S. (2008). A hybrid genetic algorithm for the resource-constrained project scheduling problem. European Journal of Operational Research, 185(2), 495–508.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2005). The use of buffers in project management: The trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227–240.CrossRef Van de Vonder, S., Demeulemeester, E., Herroelen, W., & Leus, R. (2005). The use of buffers in project management: The trade-off between stability and makespan. International Journal of Production Economics, 97(2), 227–240.CrossRef
Zurück zum Zitat Van de Vonder, S., Ballestin, F., Demeulemeester, E., & Herroelen, W. (2007a). Heuristic procedures for reactive project scheduling. Computers & Industrial Engineering, 52(1), 11–28.CrossRef Van de Vonder, S., Ballestin, F., Demeulemeester, E., & Herroelen, W. (2007a). Heuristic procedures for reactive project scheduling. Computers & Industrial Engineering, 52(1), 11–28.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2007b). A classification of predictive-reactive project scheduling procedures. Journal of Scheduling, 10(3), 195–207.CrossRef Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2007b). A classification of predictive-reactive project scheduling procedures. Journal of Scheduling, 10(3), 195–207.CrossRef
Zurück zum Zitat Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2008). Proactive heuristic procedures for robust project scheduling: An experimental analysis. European Journal of Operational Research, 189(3), 723–733.CrossRef Van de Vonder, S., Demeulemeester, E., & Herroelen, W. (2008). Proactive heuristic procedures for robust project scheduling: An experimental analysis. European Journal of Operational Research, 189(3), 723–733.CrossRef
Zurück zum Zitat Wiest, J., & Levy, F. (1977). A management guide to PERT/CPM. Englewood Cliffs: Prentice Hall. Wiest, J., & Levy, F. (1977). A management guide to PERT/CPM. Englewood Cliffs: Prentice Hall.
Zurück zum Zitat Wullink, G., Gademann, A. J. R. M., Hans, E. W., & Van Harten, A. (2004). Scenario-based approach for flexible resource loading under uncertainty. International Journal of Production Research, 42(24), 5079–5098.CrossRef Wullink, G., Gademann, A. J. R. M., Hans, E. W., & Van Harten, A. (2004). Scenario-based approach for flexible resource loading under uncertainty. International Journal of Production Research, 42(24), 5079–5098.CrossRef
Zurück zum Zitat Wullink, G. (2005). Resource loading under uncertainty. PhD thesis, University of Twente. Wullink, G. (2005). Resource loading under uncertainty. PhD thesis, University of Twente.
Zurück zum Zitat Zahraie, B., & Tavakolan, M. (2009). Stochastic time-cost-resource utilization optimization using nondominated sorting genetic algorithm and discrete fuzzy sets. Journal of Construction Engineering and Management, 135(11), 1162–1171.CrossRef Zahraie, B., & Tavakolan, M. (2009). Stochastic time-cost-resource utilization optimization using nondominated sorting genetic algorithm and discrete fuzzy sets. Journal of Construction Engineering and Management, 135(11), 1162–1171.CrossRef
Metadaten
Titel
A genetic algorithm for the robust resource leveling problem
verfasst von
Hongbo Li
Erik Demeulemeester
Publikationsdatum
01.02.2016
Verlag
Springer US
Erschienen in
Journal of Scheduling / Ausgabe 1/2016
Print ISSN: 1094-6136
Elektronische ISSN: 1099-1425
DOI
https://doi.org/10.1007/s10951-015-0457-6

Weitere Artikel der Ausgabe 1/2016

Journal of Scheduling 1/2016 Zur Ausgabe

Premium Partner