Abstract

Although the construction industry has been adopting Building Information Modelling (BIM) for at least two decades, many of its concepts, practices and standards were created for and are now consolidated on building projects. Therefore, in order to use BIM methodology in infrastructure projects, it is frequently necessary to resort to some adaptation. Recently, there has been an increasing interest on the application of BIM to infrastructure, which has its own complexities and particularities. Infrastructure may imply very diverse kinds of structures like tunnels, dams, airports, highways, among others, each potentially requiring a different BIM-based approach, as the challenges arising on each one are not the same. On the other hand, even for building projects, studies related to the application of BIM in the bidding stage are still few. The aim of this article is to clarify, through a literature review and analysis, how BIM can be used to support the tendering process of infrastructure projects. The findings show that BIM can be used in the bidding stage of infrastructure projects to improve communication between stakeholders, reduce (or even eliminate) error-prone tasks and rework, generate accurate quantity take-offs and automate time-consuming activities during this usually time-pressed phase. BIM implementation can also be of great value as it can support risk identification and reduction by minimizing misinterpretation of schedules and design, as well as contributing to better constructability analysis, sub-contractor coordination, facilitating communication and supporting the risk analysis, leading to more reliable and accurate offers to the owner.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Technik"

Online-Abonnement

Mit Springer Professional "Technik" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 390 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Maschinenbau + Werkstoffe




 

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Literatur
1.
Zurück zum Zitat The Boston Consulting Group: Digital in Engineering and Construction - The Transformative Power of Building Information Modeling (2016) The Boston Consulting Group: Digital in Engineering and Construction - The Transformative Power of Building Information Modeling (2016)
2.
Zurück zum Zitat McKinsey & Company: Reinventing Construction: A Route to Higher Productivity (2017) McKinsey & Company: Reinventing Construction: A Route to Higher Productivity (2017)
3.
Zurück zum Zitat McKinsey & Company: Bridging global infrastructure gaps. McKinsey Glob. Inst., June 2016 McKinsey & Company: Bridging global infrastructure gaps. McKinsey Glob. Inst., June 2016
4.
Zurück zum Zitat Sacks, R., et al.: BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers, 3rd edn. Wiley (2018) Sacks, R., et al.: BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers, 3rd edn. Wiley (2018)
5.
Zurück zum Zitat Kassem, M., Succar, B.: Macro BIM adoption: comparative market analysis. Autom. Constr. 81, 286–299 (2017)CrossRef Kassem, M., Succar, B.: Macro BIM adoption: comparative market analysis. Autom. Constr. 81, 286–299 (2017)CrossRef
6.
Zurück zum Zitat Ma, Z., Liu, Z.: BIM-based intelligent acquisition of construction information for cost estimation of building projects. Procedia Eng. 85, 358–367 (2014)CrossRef Ma, Z., Liu, Z.: BIM-based intelligent acquisition of construction information for cost estimation of building projects. Procedia Eng. 85, 358–367 (2014)CrossRef
7.
Zurück zum Zitat Aslesen, S., et al.: Winning the bid – a step-wise approach using BIM to reduce uncertainty in construction bidding. In: Proceedings of the 26th Annual Conference International Group for Lean Construction, Chennai, India, pp. 68–78 (2018) Aslesen, S., et al.: Winning the bid – a step-wise approach using BIM to reduce uncertainty in construction bidding. In: Proceedings of the 26th Annual Conference International Group for Lean Construction, Chennai, India, pp. 68–78 (2018)
8.
Zurück zum Zitat Ma, Z., Wei, Z., Zhang, X.: Semi-automatic and specification-compliant cost estimation for tendering of building projects based on IFC data of design model. Autom. Constr. 30, 126–135 (2013)CrossRef Ma, Z., Wei, Z., Zhang, X.: Semi-automatic and specification-compliant cost estimation for tendering of building projects based on IFC data of design model. Autom. Constr. 30, 126–135 (2013)CrossRef
9.
Zurück zum Zitat Aram, S., Eastman, C., Sacks, R.: A knowledge-based framework for quantity takeoff and cost estimation in the AEC industry using BIM. In: 31st International Symposium on Automation and Robotics in Construction and Mining, ISARC 2014 - Proceedings, pp. 434–442 (2014) Aram, S., Eastman, C., Sacks, R.: A knowledge-based framework for quantity takeoff and cost estimation in the AEC industry using BIM. In: 31st International Symposium on Automation and Robotics in Construction and Mining, ISARC 2014 - Proceedings, pp. 434–442 (2014)
10.
Zurück zum Zitat Rodriguez-Trejo, S., et al.: Hierarchy based information requirements for sustainable operations of buildings in Qatar. Sustain. CITIES Soc. 32, 435–448 (2017)CrossRef Rodriguez-Trejo, S., et al.: Hierarchy based information requirements for sustainable operations of buildings in Qatar. Sustain. CITIES Soc. 32, 435–448 (2017)CrossRef
11.
Zurück zum Zitat Zhiliang, M., Zhenhua, W., Wu, S., Zhe, L.: Application and extension of the IFC standard in construction cost estimating for tendering in China. Autom. Constr. 20(2), 196–204 (2011)CrossRef Zhiliang, M., Zhenhua, W., Wu, S., Zhe, L.: Application and extension of the IFC standard in construction cost estimating for tendering in China. Autom. Constr. 20(2), 196–204 (2011)CrossRef
12.
Zurück zum Zitat Aram, S., Eastman, C., Beetz, J.: Qualitative and quantitative cost estimation: a methodology analysis, in computing in civil and building engineering. In: Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 381–389 (2014) Aram, S., Eastman, C., Beetz, J.: Qualitative and quantitative cost estimation: a methodology analysis, in computing in civil and building engineering. In: Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 381–389 (2014)
13.
Zurück zum Zitat Olatunji, O.A., Sher, W.: Perspectives on modelling BIM-enabled estimating practices. Australas. J. Constr. Econ. Build. 14(4), 32–53 (2014) Olatunji, O.A., Sher, W.: Perspectives on modelling BIM-enabled estimating practices. Australas. J. Constr. Econ. Build. 14(4), 32–53 (2014)
14.
Zurück zum Zitat Taboada, J.A., Garrido-Lecca, A.: Case study on the use of BIM at the bidding stage of a building project. In: 22nd Annual Conference of the International Group for Lean Construction Understanding and Improving Project Based Production, IGLC 2014, pp. 1473–1482 (2014) Taboada, J.A., Garrido-Lecca, A.: Case study on the use of BIM at the bidding stage of a building project. In: 22nd Annual Conference of the International Group for Lean Construction Understanding and Improving Project Based Production, IGLC 2014, pp. 1473–1482 (2014)
15.
Zurück zum Zitat Al-Mashta, S., Alkass, S.: Integrated cost budgeting and estimating model for building projects. AACE Int. Trans. 1, 22–36 (2010) Al-Mashta, S., Alkass, S.: Integrated cost budgeting and estimating model for building projects. AACE Int. Trans. 1, 22–36 (2010)
16.
Zurück zum Zitat Collins, J., Gentry, R.: KBAD knowledge base for architectural detailing. In: Proceedings of the 35th eCAADe Conference, vol. 2, pp. 657–666 (2017) Collins, J., Gentry, R.: KBAD knowledge base for architectural detailing. In: Proceedings of the 35th eCAADe Conference, vol. 2, pp. 657–666 (2017)
17.
Zurück zum Zitat Eastman, C., Min Lee, J., Suk Jeong, Y., Kook Lee, J.: Automatic rule-based checking of building designs. Autom. Constr. 18(8), 1011–1033 (2009)CrossRef Eastman, C., Min Lee, J., Suk Jeong, Y., Kook Lee, J.: Automatic rule-based checking of building designs. Autom. Constr. 18(8), 1011–1033 (2009)CrossRef
18.
Zurück zum Zitat Berard, O., Karlshoej, J.: Information delivery manuals to integrate building product information into design. Electron. J. Inf. Technol. Constr. 17, 64–74 (2012) Berard, O., Karlshoej, J.: Information delivery manuals to integrate building product information into design. Electron. J. Inf. Technol. Constr. 17, 64–74 (2012)
19.
Zurück zum Zitat Ciribini, A.L.C., Bolpagni, M., Oliveri, E.: An innovative approach to e-public tendering based on model checking. Procedia Econ. Financ. 21, 32–39 (2015)CrossRef Ciribini, A.L.C., Bolpagni, M., Oliveri, E.: An innovative approach to e-public tendering based on model checking. Procedia Econ. Financ. 21, 32–39 (2015)CrossRef
20.
Zurück zum Zitat IRG: Managing Cost Risk and Uncertainty in Infrastructure Projects (2013) IRG: Managing Cost Risk and Uncertainty in Infrastructure Projects (2013)
21.
Zurück zum Zitat Zou, Y., Kiviniemi, A., Jones, S.W.: BIM-based risk management: challenges and opportunities. In: Proceedings of the 32nd CIB W78 Conference, pp. 847–855 (2015) Zou, Y., Kiviniemi, A., Jones, S.W.: BIM-based risk management: challenges and opportunities. In: Proceedings of the 32nd CIB W78 Conference, pp. 847–855 (2015)
22.
Zurück zum Zitat Dodge Data & Analytics: Managing Risk in the Construction Industry (2017) Dodge Data & Analytics: Managing Risk in the Construction Industry (2017)
23.
Zurück zum Zitat Chang, C.Y.: Harnessing BIM data in the management of project risks: the Bayesian risk-bearing capacity approach. In: Transforming the Future of Infrastructure through Smarter Information - Proceedings of the International Conference on Smart Infrastructure and Construction, ICSIC 2016, pp. 537–542 (2016) Chang, C.Y.: Harnessing BIM data in the management of project risks: the Bayesian risk-bearing capacity approach. In: Transforming the Future of Infrastructure through Smarter Information - Proceedings of the International Conference on Smart Infrastructure and Construction, ICSIC 2016, pp. 537–542 (2016)
24.
Zurück zum Zitat Tomek, P., Matejka, A.: The impact of BIM on risk management as an argument for its implementation in a construction company. Procedia Eng. 85, 501–509 (2014)CrossRef Tomek, P., Matejka, A.: The impact of BIM on risk management as an argument for its implementation in a construction company. Procedia Eng. 85, 501–509 (2014)CrossRef
25.
Zurück zum Zitat Ganbat, T., Chong, H., Liao, P., Wu, Y.: A Bibliometric review on risk management and building information modeling for international construction. Adv. Civ. Eng. 2018, 1–13 (2018)CrossRef Ganbat, T., Chong, H., Liao, P., Wu, Y.: A Bibliometric review on risk management and building information modeling for international construction. Adv. Civ. Eng. 2018, 1–13 (2018)CrossRef
26.
Zurück zum Zitat Ahmad, Z., Thaheem, M.J., Maqsoom, A.: Building information modeling as a risk transformer: an evolutionary insight into the project uncertainty. Autom. Constr. 92(March), 103–119 (2018)CrossRef Ahmad, Z., Thaheem, M.J., Maqsoom, A.: Building information modeling as a risk transformer: an evolutionary insight into the project uncertainty. Autom. Constr. 92(March), 103–119 (2018)CrossRef
27.
Zurück zum Zitat Zou, Y., Kiviniemi, A., Jones, S.W.: A review of risk management through BIM and BIM-related technologies. Saf. Sci. 97, 88–98 (2017)CrossRef Zou, Y., Kiviniemi, A., Jones, S.W.: A review of risk management through BIM and BIM-related technologies. Saf. Sci. 97, 88–98 (2017)CrossRef
28.
Zurück zum Zitat Chien, K.F., Wu, Z.H., Huang, S.C.: Identifying and assessing critical risk factors for BIM projects: empirical study. Autom. Constr. 45, 1–15 (2014)CrossRef Chien, K.F., Wu, Z.H., Huang, S.C.: Identifying and assessing critical risk factors for BIM projects: empirical study. Autom. Constr. 45, 1–15 (2014)CrossRef
29.
Zurück zum Zitat Tauscher, E., Smarsly, K., König, M., Beucke, K.: Automated generation of construction sequences using building information models, in computing in civil and building engineering. In: Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 745–752 (2014) Tauscher, E., Smarsly, K., König, M., Beucke, K.: Automated generation of construction sequences using building information models, in computing in civil and building engineering. In: Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 745–752 (2014)
30.
Zurück zum Zitat Choe, S., Leite, F.: Construction safety planning: site-specific temporal and spatial information integration. Autom. Constr. 84, 335–344 (2017)CrossRef Choe, S., Leite, F.: Construction safety planning: site-specific temporal and spatial information integration. Autom. Constr. 84, 335–344 (2017)CrossRef
31.
Zurück zum Zitat Bansal, V.K., Pal, M.: Construction projects scheduling using GIS tools. Int. J. Constr. Manag. 11(1), 1–18 (2011) Bansal, V.K., Pal, M.: Construction projects scheduling using GIS tools. Int. J. Constr. Manag. 11(1), 1–18 (2011)
32.
Zurück zum Zitat Choi, B., Lee, H.S., Park, M., Cho, Y.K., Kim, H.: Framework for work-space planning using four-dimensional BIM in construction projects. J. Constr. Eng. Manag. 140(9) (2014) Choi, B., Lee, H.S., Park, M., Cho, Y.K., Kim, H.: Framework for work-space planning using four-dimensional BIM in construction projects. J. Constr. Eng. Manag. 140(9) (2014)
33.
Zurück zum Zitat Shang, Z., Shen, Z.: A framework for a site safety assessment model using statistical 4D BIM-based spatial-temporal collision detection. In: Construction Research Congress 2016: Old and New Construction Technologies Converge In Historic San Juan, pp. 2187–2196 (2016) Shang, Z., Shen, Z.: A framework for a site safety assessment model using statistical 4D BIM-based spatial-temporal collision detection. In: Construction Research Congress 2016: Old and New Construction Technologies Converge In Historic San Juan, pp. 2187–2196 (2016)
34.
Zurück zum Zitat Moon, H., Kim, H., Kim, C., Kang, L.: Development of a schedule-workspace interference management system simultaneously considering the overlap level of parallel schedules and workspaces. Autom. Constr. 39, 93–105 (2014)CrossRef Moon, H., Kim, H., Kim, C., Kang, L.: Development of a schedule-workspace interference management system simultaneously considering the overlap level of parallel schedules and workspaces. Autom. Constr. 39, 93–105 (2014)CrossRef
35.
Zurück zum Zitat Candelario-Garrido, A., García-Sanz-Calcedo, J., Rodríguez, A.M.R.: A quantitative analysis on the feasibility of 4D planning graphic systems versus conventional systems in building projects. Sustain. Cities Soc. 35, 378–384 (2017)CrossRef Candelario-Garrido, A., García-Sanz-Calcedo, J., Rodríguez, A.M.R.: A quantitative analysis on the feasibility of 4D planning graphic systems versus conventional systems in building projects. Sustain. Cities Soc. 35, 378–384 (2017)CrossRef
36.
Zurück zum Zitat Swallow, M., Zulu, S.: Benefits and barriers to the adoption of 4D modeling for site health and safety management. Front. Built Environ. 4 (2019) Swallow, M., Zulu, S.: Benefits and barriers to the adoption of 4D modeling for site health and safety management. Front. Built Environ. 4 (2019)
37.
Zurück zum Zitat Rolfsen, C.N., Merschbrock, C.: Acceptance of construction scheduling visualizations: bar-charts, flowline-charts, or perhaps BIM? Procedia Eng. 164, 558–566 (2016)CrossRef Rolfsen, C.N., Merschbrock, C.: Acceptance of construction scheduling visualizations: bar-charts, flowline-charts, or perhaps BIM? Procedia Eng. 164, 558–566 (2016)CrossRef
38.
Zurück zum Zitat Torres-Calderon, W., Chi, Y., Amer, F., Golparvar-Fard, M.: Automated mining of construction schedules for easy and quick assembly of 4D BIM simulations. In: Computing in Civil Engineering 2019: Visualization, Information Modeling, and Simulation - Selected Papers from the ASCE International Conference on Computing in Civil Engineering 2019, pp. 432–438 (2019) Torres-Calderon, W., Chi, Y., Amer, F., Golparvar-Fard, M.: Automated mining of construction schedules for easy and quick assembly of 4D BIM simulations. In: Computing in Civil Engineering 2019: Visualization, Information Modeling, and Simulation - Selected Papers from the ASCE International Conference on Computing in Civil Engineering 2019, pp. 432–438 (2019)
39.
Zurück zum Zitat Yun, S., Jun, K., Son, C., Kim, S.: Preliminary study for performance analysis of BIM-based building construction simulation system. KSCE J. Civ. Eng. 18(2), 531–540 (2014)CrossRef Yun, S., Jun, K., Son, C., Kim, S.: Preliminary study for performance analysis of BIM-based building construction simulation system. KSCE J. Civ. Eng. 18(2), 531–540 (2014)CrossRef
40.
Zurück zum Zitat Haiati, O., Von Heyl, J., Schmalz, S.: BIM and sequence simulation in structural work - development of a procedure for automation. In: IGLC 2016 - 24th Annual Conference of the International Group for Lean Construction, pp. 73–82 (2016) Haiati, O., Von Heyl, J., Schmalz, S.: BIM and sequence simulation in structural work - development of a procedure for automation. In: IGLC 2016 - 24th Annual Conference of the International Group for Lean Construction, pp. 73–82 (2016)
41.
Zurück zum Zitat Castronovo, F., Lee, S., Nikolic, D., Messner, J.I.: Visualization in 4D construction management software: a review of standards and guidelines. In: Computing in Civil and Building Engineering - Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 315–322 (2014) Castronovo, F., Lee, S., Nikolic, D., Messner, J.I.: Visualization in 4D construction management software: a review of standards and guidelines. In: Computing in Civil and Building Engineering - Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, pp. 315–322 (2014)
42.
Zurück zum Zitat Crowther, J., Ajayi, S.O.: Impacts of 4D BIM on construction project performance. Int. J. Constr. Manag. (2019) Crowther, J., Ajayi, S.O.: Impacts of 4D BIM on construction project performance. Int. J. Constr. Manag. (2019)
Metadaten
Titel
BIM Support in the Tendering Phase of Infrastructure Projects
verfasst von
Stefania Limp Muniz Correa
Eduardo Toledo Santos
Copyright-Jahr
2021
DOI
https://doi.org/10.1007/978-3-030-51295-8_27