Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling

verfasst von: Rob Van Eynde, Mario Vanhoucke

Erschienen in: Journal of Scheduling | Ausgabe 3/2020

Einloggen

Aktivieren Sie unsere intelligente Suche, um passende Fachinhalte oder Patente zu finden.

search-config
loading …

Abstract

In this paper, we propose a new dataset for the resource-constrained multi-project scheduling problem and evaluate the performance of multi-project extensions of the single-project schedule generation schemes. This manuscript contributes to the existing research in three ways. First, we provide an overview of existing benchmark datasets and classify the multi-project literature based on the type of datasets that are used in these studies. Furthermore, we evaluate the existing summary measures that are used to classify instances and provide adaptations to the data generation procedure of Browning and Yassine (J Scheduling 13(2):143-161, 2010a). With this adapted generator we propose a new dataset that is complimentary to the existing ones. Second, we propose decoupled versions of the single-project scheduling schemes, building on insights from the existing literature. A computational experiment shows that the decoupled variants outperform the existing priority rule heuristics and that the best priority rules differ for the two objective functions under study. Furthermore, we analyse the effect of the different parameters on the performance of the heuristics. Third, we implement a genetic algorithm that incorporates specific multi-project operators and test it on all datasets. The experiment shows that the new datasets are challenging and provide opportunities for future research.

Sie haben noch keine Lizenz? Dann Informieren Sie sich jetzt über unsere Produkte:

Springer Professional "Wirtschaft+Technik"

Online-Abonnement

Mit Springer Professional "Wirtschaft+Technik" erhalten Sie Zugriff auf:

  • über 102.000 Bücher
  • über 537 Zeitschriften

aus folgenden Fachgebieten:

  • Automobil + Motoren
  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Elektrotechnik + Elektronik
  • Energie + Nachhaltigkeit
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Maschinenbau + Werkstoffe
  • Versicherung + Risiko

Jetzt Wissensvorsprung sichern!

Springer Professional "Wirtschaft"

Online-Abonnement

Mit Springer Professional "Wirtschaft" erhalten Sie Zugriff auf:

  • über 67.000 Bücher
  • über 340 Zeitschriften

aus folgenden Fachgebieten:

  • Bauwesen + Immobilien
  • Business IT + Informatik
  • Finance + Banking
  • Management + Führung
  • Marketing + Vertrieb
  • Versicherung + Risiko




Jetzt Wissensvorsprung sichern!

Anhänge
Nur mit Berechtigung zugänglich
Fußnoten
1
The instances in each of our datasets have the same number of activities, so all projects are tied for the MAXACT and MINACT rules. Because we set MINCP as tie breaker, MINACT and MAXACT are equivalent to MINCP in this case. Therefore, we omit these rules here from the discussion.
 
Literatur
Zurück zum Zitat Adhau, S., Mittal, M., & Mittal, A. (2012). A multi-agent system for distributed multi-project scheduling: An auction-based negotiation approach. Engineering Applications of Artificial Intelligence, 25(8), 1738–1751. Adhau, S., Mittal, M., & Mittal, A. (2012). A multi-agent system for distributed multi-project scheduling: An auction-based negotiation approach. Engineering Applications of Artificial Intelligence, 25(8), 1738–1751.
Zurück zum Zitat Adhau, S., Mittal, M., & Mittal, A. (2013). A multi-agent system for decentralized multi-project scheduling with resource transfers. International Journal of Production Economics, 146(2), 646–661. Adhau, S., Mittal, M., & Mittal, A. (2013). A multi-agent system for decentralized multi-project scheduling with resource transfers. International Journal of Production Economics, 146(2), 646–661.
Zurück zum Zitat Asta, S., Karapetyan, D., Kheiri, A., Özcan, E., & Parkes, A. J. (2016). Combining monte-carlo and hyper-heuristic methods for the multi-mode resource-constrained multi-project scheduling problem. Information Sciences, 373, 476–498. Asta, S., Karapetyan, D., Kheiri, A., Özcan, E., & Parkes, A. J. (2016). Combining monte-carlo and hyper-heuristic methods for the multi-mode resource-constrained multi-project scheduling problem. Information Sciences, 373, 476–498.
Zurück zum Zitat Beşikci, U., Bilge, Ü., & Ulusoy, G. (2013). Resource dedication problem in a multi-project environment. Flexible Services and Manufacturing Journal, 25(1–2), 206–229. Beşikci, U., Bilge, Ü., & Ulusoy, G. (2013). Resource dedication problem in a multi-project environment. Flexible Services and Manufacturing Journal, 25(1–2), 206–229.
Zurück zum Zitat Beşikci, U., Bilge, Ü., & Ulusoy, G. (2015). Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240(1), 22–31. Beşikci, U., Bilge, Ü., & Ulusoy, G. (2015). Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240(1), 22–31.
Zurück zum Zitat Browning, T. R., & Yassine, A. A. (2010a). A random generator of resource-constrained multi-project network problems. Journal of Scheduling, 13(2), 143–161. Browning, T. R., & Yassine, A. A. (2010a). A random generator of resource-constrained multi-project network problems. Journal of Scheduling, 13(2), 143–161.
Zurück zum Zitat Browning, T. R., & Yassine, A. A. (2010b). Resource-constrained multi-project scheduling: Priority rule performance revisited. International Journal of Production Economics, 126(2), 212–228. Browning, T. R., & Yassine, A. A. (2010b). Resource-constrained multi-project scheduling: Priority rule performance revisited. International Journal of Production Economics, 126(2), 212–228.
Zurück zum Zitat Chakrabortty, R. K., Sarker, R. A., & Essam, D. L. (2017). Resource constrained multi-project scheduling: A priority rule based evolutionary local search approach. In G. Leu, H. K. Singh, & S. Elsayed (Eds.), Intelligent and evolutionary systems (pp. 75–86). Canberra, Australia: Springer. Chakrabortty, R. K., Sarker, R. A., & Essam, D. L. (2017). Resource constrained multi-project scheduling: A priority rule based evolutionary local search approach. In G. Leu, H. K. Singh, & S. Elsayed (Eds.), Intelligent and evolutionary systems (pp. 75–86). Canberra, Australia: Springer.
Zurück zum Zitat Chen, P.-H., & Shahandashti, S. M. (2009). Hybrid of genetic algorithm and simulated annealing for multiple project scheduling with multiple resource constraints. Automation in Construction, 18(4), 434–443. Chen, P.-H., & Shahandashti, S. M. (2009). Hybrid of genetic algorithm and simulated annealing for multiple project scheduling with multiple resource constraints. Automation in Construction, 18(4), 434–443.
Zurück zum Zitat Chiu, H. N., & Tsai, D. M. (2002). An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flows. Construction Management and Economics, 20(1), 55–66. Chiu, H. N., & Tsai, D. M. (2002). An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flows. Construction Management and Economics, 20(1), 55–66.
Zurück zum Zitat Confessore, G., Giordani, S., & Rismondo, S. (2007). A market-based multi-agent system model for decentralized multi-project scheduling. Annals of Operations Research, 150(1), 115–135. Confessore, G., Giordani, S., & Rismondo, S. (2007). A market-based multi-agent system model for decentralized multi-project scheduling. Annals of Operations Research, 150(1), 115–135.
Zurück zum Zitat Davis, E. W. (1975). Project network summary measures constrained-resource scheduling. AIIE Transactions, 7(2), 132–142. Davis, E. W. (1975). Project network summary measures constrained-resource scheduling. AIIE Transactions, 7(2), 132–142.
Zurück zum Zitat Deckro, R. F., Winkofsky, E., Hebert, J. E., & Gagnon, R. (1991). A decomposition approach to multi-project scheduling. European Journal of Operational Research, 51(1), 110–118. Deckro, R. F., Winkofsky, E., Hebert, J. E., & Gagnon, R. (1991). A decomposition approach to multi-project scheduling. European Journal of Operational Research, 51(1), 110–118.
Zurück zum Zitat Demeulemeester, E., Vanhoucke, M., & Herroelen, W. (2003). Rangen: A random network generator for activity-on-the-node networks. Journal of scheduling, 6(1), 17–38. Demeulemeester, E., Vanhoucke, M., & Herroelen, W. (2003). Rangen: A random network generator for activity-on-the-node networks. Journal of scheduling, 6(1), 17–38.
Zurück zum Zitat Dumond, J., & Mabert, V. A. (1988). Evaluating project scheduling and due date assignment procedures: An experimental analysis. Management Science, 34(1), 101–118. Dumond, J., & Mabert, V. A. (1988). Evaluating project scheduling and due date assignment procedures: An experimental analysis. Management Science, 34(1), 101–118.
Zurück zum Zitat Elmaghraby, S. E. (1977). Activity networks: Project planning and control by network models. New York: Wiley. Elmaghraby, S. E. (1977). Activity networks: Project planning and control by network models. New York: Wiley.
Zurück zum Zitat Geiger, M. J. (2017). A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem. European Journal of Operational Research, 256(3), 729–741. Geiger, M. J. (2017). A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem. European Journal of Operational Research, 256(3), 729–741.
Zurück zum Zitat Gonçalves, J. F., Mendes, J. J., & Resende, M. G. (2008). A genetic algorithm for the resource constrained multi-project scheduling problem. European Journal of Operational Research, 189(3), 1171–1190. Gonçalves, J. F., Mendes, J. J., & Resende, M. G. (2008). A genetic algorithm for the resource constrained multi-project scheduling problem. European Journal of Operational Research, 189(3), 1171–1190.
Zurück zum Zitat Hartmann, S. (1998). A competitive genetic algorithm for resource-constrained project scheduling. Naval Research Logistics (NRL), 45(7), 733–750. Hartmann, S. (1998). A competitive genetic algorithm for resource-constrained project scheduling. Naval Research Logistics (NRL), 45(7), 733–750.
Zurück zum Zitat Hartmann, S., & Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of operational research, 207(1), 1–14. Hartmann, S., & Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of operational research, 207(1), 1–14.
Zurück zum Zitat Homberger, J. (2007). A multi-agent system for the decentralized resource-constrained multi-project scheduling problem. International Transactions in Operational Research, 14(6), 565–589. Homberger, J. (2007). A multi-agent system for the decentralized resource-constrained multi-project scheduling problem. International Transactions in Operational Research, 14(6), 565–589.
Zurück zum Zitat Homberger, J. (2012). A (\(\mu \), \(\lambda \))-coordination mechanism for agent-based multi-project scheduling. OR Spectrum, 34(1), 107–132. Homberger, J. (2012). A (\(\mu \), \(\lambda \))-coordination mechanism for agent-based multi-project scheduling. OR Spectrum, 34(1), 107–132.
Zurück zum Zitat Kolisch, R., & Sprecher, A. (1997). Psplib-a project scheduling problem library: Or software-orsep operations research software exchange program. European Journal of Operational Research, 96(1), 205–216. Kolisch, R., & Sprecher, A. (1997). Psplib-a project scheduling problem library: Or software-orsep operations research software exchange program. European Journal of Operational Research, 96(1), 205–216.
Zurück zum Zitat Krüger, D., & Scholl, A. (2009). A heuristic solution framework for the resource constrained (multi-) project scheduling problem with sequence-dependent transfer times. European Journal of Operational Research, 197(2), 492–508. Krüger, D., & Scholl, A. (2009). A heuristic solution framework for the resource constrained (multi-) project scheduling problem with sequence-dependent transfer times. European Journal of Operational Research, 197(2), 492–508.
Zurück zum Zitat Krüger, D., & Scholl, A. (2010). Managing and modelling general resource transfers in (multi-) project scheduling. OR Spectrum, 32(2), 369–394. Krüger, D., & Scholl, A. (2010). Managing and modelling general resource transfers in (multi-) project scheduling. OR Spectrum, 32(2), 369–394.
Zurück zum Zitat Kumanan, S., Jose, G. J., & Raja, K. (2006). Multi-project scheduling using an heuristic and a genetic algorithm. The International Journal of Advanced Manufacturing Technology, 31(3–4), 360–366. Kumanan, S., Jose, G. J., & Raja, K. (2006). Multi-project scheduling using an heuristic and a genetic algorithm. The International Journal of Advanced Manufacturing Technology, 31(3–4), 360–366.
Zurück zum Zitat Kurtulus, I. (1985). Multiproject scheduling: Analysis of scheduling strategies under unequal delay penalties. Journal of Operations Management, 5(3), 291–307. Kurtulus, I. (1985). Multiproject scheduling: Analysis of scheduling strategies under unequal delay penalties. Journal of Operations Management, 5(3), 291–307.
Zurück zum Zitat Kurtulus, I., & Davis, E. (1982). Multi-project scheduling: Categorization of heuristic rules performance. Management Science, 28(2), 161–172. Kurtulus, I., & Davis, E. (1982). Multi-project scheduling: Categorization of heuristic rules performance. Management Science, 28(2), 161–172.
Zurück zum Zitat Lawrence, S. R., & Morton, T. E. (1993). Resource-constrained multi-project scheduling with tardy costs: Comparing myopic, bottleneck, and resource pricing heuristics. European Journal of Operational Research, 64(2), 168–187. Lawrence, S. R., & Morton, T. E. (1993). Resource-constrained multi-project scheduling with tardy costs: Comparing myopic, bottleneck, and resource pricing heuristics. European Journal of Operational Research, 64(2), 168–187.
Zurück zum Zitat Lee, Y.-H., Kumara, S. R., & Chatterjee, K. (2003). Multiagent based dynamic resource scheduling for distributed multiple projects using a market mechanism. Journal of Intelligent Manufacturing, 14(5), 471–484. Lee, Y.-H., Kumara, S. R., & Chatterjee, K. (2003). Multiagent based dynamic resource scheduling for distributed multiple projects using a market mechanism. Journal of Intelligent Manufacturing, 14(5), 471–484.
Zurück zum Zitat Liberatore, M. J., & Pollack-Johnson, B. (2003). Factors influencing the usage and selection of project management software. IEEE transactions on Engineering Management, 50(2), 164–174. Liberatore, M. J., & Pollack-Johnson, B. (2003). Factors influencing the usage and selection of project management software. IEEE transactions on Engineering Management, 50(2), 164–174.
Zurück zum Zitat Lova, A., Maroto, C., & Tormos, P. (2000). A multicriteria heuristic method to improve resource allocation in multiproject scheduling. European Journal of Operational Research, 127(2), 408–424. Lova, A., Maroto, C., & Tormos, P. (2000). A multicriteria heuristic method to improve resource allocation in multiproject scheduling. European Journal of Operational Research, 127(2), 408–424.
Zurück zum Zitat Lova, A., & Tormos, P. (2001). Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling. Annals of Operations Research, 102(1–4), 263–286. Lova, A., & Tormos, P. (2001). Analysis of scheduling schemes and heuristic rules performance in resource-constrained multiproject scheduling. Annals of Operations Research, 102(1–4), 263–286.
Zurück zum Zitat Maroto, C., Tormos, P., & Lova, A. (1999). The evolution of software quality in project scheduling. In J. Weglarz (Ed.), Project scheduling (pp. 239–259). Boston, MA: Springer. Maroto, C., Tormos, P., & Lova, A. (1999). The evolution of software quality in project scheduling. In J. Weglarz (Ed.), Project scheduling (pp. 239–259). Boston, MA: Springer.
Zurück zum Zitat Mittal, M., & Kanda, A. (2009). Two-phase heuristics for scheduling of multiple projects. International Journal of Operational Research, 4(2), 159–177. Mittal, M., & Kanda, A. (2009). Two-phase heuristics for scheduling of multiple projects. International Journal of Operational Research, 4(2), 159–177.
Zurück zum Zitat Payne, J. H. (1995). Management of multiple simultaneous projects: A state-of-the-art review. International Journal of Project Management, 13(3), 163–168. Payne, J. H. (1995). Management of multiple simultaneous projects: A state-of-the-art review. International Journal of Project Management, 13(3), 163–168.
Zurück zum Zitat Pérez, E., Posada, M., & Lorenzana, A. (2016). Taking advantage of solving the resource constrained multi-project scheduling problems using multi-modal genetic algorithms. Soft Computing, 20(5), 1879–1896. Pérez, E., Posada, M., & Lorenzana, A. (2016). Taking advantage of solving the resource constrained multi-project scheduling problems using multi-modal genetic algorithms. Soft Computing, 20(5), 1879–1896.
Zurück zum Zitat Singh, A. (2014). Resource constrained multi-project scheduling with priority rules and analytic hierarchy process. Procedia Engineering, 69, 725–734. Singh, A. (2014). Resource constrained multi-project scheduling with priority rules and analytic hierarchy process. Procedia Engineering, 69, 725–734.
Zurück zum Zitat Song, W., Kang, D., Zhang, J., & Xi, H. (2017). A multi-unit combinatorial auction based approach for decentralized multi-project scheduling. Autonomous Agents and Multi-agent Systems, 31(6), 1548–1577. Song, W., Kang, D., Zhang, J., & Xi, H. (2017). A multi-unit combinatorial auction based approach for decentralized multi-project scheduling. Autonomous Agents and Multi-agent Systems, 31(6), 1548–1577.
Zurück zum Zitat Toffolo, T. A., Santos, H. G., Carvalho, M. A., & Soares, J. A. (2016). An integer programming approach to the multimode resource-constrained multiproject scheduling problem. Journal of Scheduling, 19(3), 295–307. Toffolo, T. A., Santos, H. G., Carvalho, M. A., & Soares, J. A. (2016). An integer programming approach to the multimode resource-constrained multiproject scheduling problem. Journal of Scheduling, 19(3), 295–307.
Zurück zum Zitat Vanhoucke, M., Coelho, J., Debels, D., Maenhout, B., & Tavares, L. V. (2008). An evaluation of the adequacy of project network generators with systematically sampled networks. European Journal of Operational Research, 187(2), 511–524. Vanhoucke, M., Coelho, J., Debels, D., Maenhout, B., & Tavares, L. V. (2008). An evaluation of the adequacy of project network generators with systematically sampled networks. European Journal of Operational Research, 187(2), 511–524.
Zurück zum Zitat Vázquez, E. P., Calvo, M. P., & Ordóñez, P. M. (2015). Learning process on priority rules to solve the RCMPSP. Journal of Intelligent Manufacturing, 26(1), 123–138. Vázquez, E. P., Calvo, M. P., & Ordóñez, P. M. (2015). Learning process on priority rules to solve the RCMPSP. Journal of Intelligent Manufacturing, 26(1), 123–138.
Zurück zum Zitat Vercellis, C. (1994). Constrained multi-project plannings problems: A Lagrangean decomposition approach. European Journal of Operational Research, 78(2), 267–275. Vercellis, C. (1994). Constrained multi-project plannings problems: A Lagrangean decomposition approach. European Journal of Operational Research, 78(2), 267–275.
Zurück zum Zitat Wang, X., Chen, Q., Mao, N., Chen, X., & Li, Z. (2015). Proactive approach for stochastic rcmpsp based on multi-priority rule combinations. International Journal of Production Research, 53(4), 1098–1110. Wang, X., Chen, Q., Mao, N., Chen, X., & Li, Z. (2015). Proactive approach for stochastic rcmpsp based on multi-priority rule combinations. International Journal of Production Research, 53(4), 1098–1110.
Zurück zum Zitat Wang, Y., He, Z., Kerkhove, L.-P., & Vanhoucke, M. (2017). On the performance of priority rules for the stochastic resource constrained multi-project scheduling problem. Computers and Industrial Engineering, 114, 223–234. Wang, Y., He, Z., Kerkhove, L.-P., & Vanhoucke, M. (2017). On the performance of priority rules for the stochastic resource constrained multi-project scheduling problem. Computers and Industrial Engineering, 114, 223–234.
Zurück zum Zitat Wauters, T., Kinable, J., Smet, P., Vancroonenburg, W., Berghe, G. V., & Verstichel, J. (2016). The multi-mode resource-constrained multi-project scheduling problem. Journal of Scheduling, 19(3), 271–283. Wauters, T., Kinable, J., Smet, P., Vancroonenburg, W., Berghe, G. V., & Verstichel, J. (2016). The multi-mode resource-constrained multi-project scheduling problem. Journal of Scheduling, 19(3), 271–283.
Zurück zum Zitat Wauters, T., Verbeeck, K., De Causmaecker, P., & Berghe, G. V. (2015). A learning-based optimization approach to multi-project scheduling. Journal of Scheduling, 18(1), 61–74. Wauters, T., Verbeeck, K., De Causmaecker, P., & Berghe, G. V. (2015). A learning-based optimization approach to multi-project scheduling. Journal of Scheduling, 18(1), 61–74.
Zurück zum Zitat Yang, K.-K., & Sum, C.-C. (1993). A comparison of resource allocation and activity scheduling rules in a dynamic multi-project environment. Journal of Operations Management, 11(2), 207–218. Yang, K.-K., & Sum, C.-C. (1993). A comparison of resource allocation and activity scheduling rules in a dynamic multi-project environment. Journal of Operations Management, 11(2), 207–218.
Zurück zum Zitat Yang, K.-K., & Sum, C.-C. (1997). An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multiproject environment. European Journal of Operational Research, 103(1), 139–154. Yang, K.-K., & Sum, C.-C. (1997). An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multiproject environment. European Journal of Operational Research, 103(1), 139–154.
Zurück zum Zitat Zheng, Z., Shumin, L., Ze, G., & Yueni, Z. (2013). Resource-constraint multi-project scheduling with priorities and uncertain activity durations. International Journal of Computational Intelligence Systems, 6(3), 530–547. Zheng, Z., Shumin, L., Ze, G., & Yueni, Z. (2013). Resource-constraint multi-project scheduling with priorities and uncertain activity durations. International Journal of Computational Intelligence Systems, 6(3), 530–547.
Metadaten
Titel
Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling
verfasst von
Rob Van Eynde
Mario Vanhoucke
Publikationsdatum
10.04.2020
Verlag
Springer US
Erschienen in
Journal of Scheduling / Ausgabe 3/2020
Print ISSN: 1094-6136
Elektronische ISSN: 1099-1425
DOI
https://doi.org/10.1007/s10951-020-00651-w

Weitere Artikel der Ausgabe 3/2020

Journal of Scheduling 3/2020 Zur Ausgabe

Premium Partner